[Federal Register Volume 61, Number 160 (Friday, August 16, 1996)]
[Notices]
[Pages 42604-42605]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 96-20913]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
[Docket No. ER96-2616-000, et al.]
Duquesne Light Company, et al.; Electric Rate and Corporate
Regulation Filings
August 9, 1996.
Take notice that the following filings have been made with the
Commission:
1. Duquesne Light Company
[Docket No. ER96-2616-000]
Take notice that on August 2, 1996, Duquesne Light Company (DLC),
filed a Service Agreement dated June 25, 1996 with Coral Power L.L.C.
under DLC's FERC Coordination Sales Tariff (Tariff). The Service
Agreement adds Coral Power L.L.C. as a customer under the Tariff. DLC
requests an effective date of June 25, 1995 for the Service Agreement.
Comment date: August 23, 1996, in accordance with Standard
Paragraph E at the end of this notice.
2. Duquesne Light Company
[Docket No. ER96-2617-000]
Take notice that on August 2, 1996, Duquesne Light Company (DLC),
filed a Service Agreement dated July 11, 1996 with LG&E Power
Marketing, Inc. under DLC's FERC Coordination Sales Tariff (Tariff).
The Service Agreement adds LG&E Power Marketing, Inc. as a customer
under the Tariff. DLC requests an effective date of July 11, 1996 for
the Service Agreement.
Comment date: August 23, 1996, in accordance with Standard
Paragraph E at the end of this notice.
3. Duquesne Light Company
[Docket No. ER96-2618-000]
Take notice that on August 2, 1996, Duquesne Light Company (DLC),
filed a Service Agreement dated June 19, 1996 with NorAm Energy
Services, Inc. under DLC's FERC Coordination Sales Tariff (Tariff). The
Service Agreement adds NorAm Energy Services, Inc. as a customer under
the Tariff. DLC requests an effective date of June 19, 1996 for the
Service Agreement.
Comment date: August 23, 1996, in accordance with Standard
Paragraph E at the end of this notice.
4. Niagara Mohawk Power Corporation
[Docket No. ER96-2619-000]
Take notice that on August 5, 1996, Niagara Mohawk Power
Corporation (NMPC), tendered for filing with the Federal Energy
Regulatory Commission an executed Service Agreement between NMPC and
Public Service Electric and Gas Company (PSE&G). This Service Agreement
specifies that PSE&G has signed on to and has agreed to the terms and
conditions of NMPC's Power Sales Tariff designated as NMPC's FERC
Electric Tariff, Original Volume No. 2. This Tariff, approved by FERC
on April 15, 1994, and which has an effective date of March 13, 1993,
will allow NMPC and PSE&G to enter into separately scheduled
transactions under which NMPC will sell to PSE&G
[[Page 42605]]
capacity and/or energy as the parties may mutually agree.
In its filing letter, NMPC also included a Certificate of
Concurrence executed by the Purchaser.
NMPC requests an effective date of July 22, 1996. NMPC has
requested waiver of the notice requirements for good cause shown.
NMPC has served copies of the filing upon the New York State Public
Service Commission and PSE&G.
Comment date: August 23, 1996, in accordance with Standard
Paragraph E at the end of this notice.
5. Louisville Gas and Electric Company
[Docket No. ER96-2620-000]
Take notice that on August 5, 1996, Louisville Gas and Electric
Company, tendered for filing copies of a service agreement between
Louisville Gas and Electric Company and Rainbow Energy Marketing
Corporation under Rate GSS.
Comment date: August 23, 1996, in accordance with Standard
Paragraph E at the end of this notice.
6. Louisville Gas and Electric Company
[Docket No. ER96-2621-000]
Take notice that on August 5, 1996, Louisville Gas and Electric
Company, tendered for filing copies of a service agreement between
Louisville Gas and Electric Company and PanEnergy Power Services under
Rate GSS.
Comment date: August 23, 1996, in accordance with Standard
Paragraph E at the end of this notice.
7. Louisville Gas and Electric Company
[Docket No. ER96-2623-000]
Take notice that on August 5, 1996, Louisville Gas and Electric
Company, tendered for filing copies of a service agreement between
Louisville Gas and Electric Company and Entergy Services, Inc. under
Rate GSS.
Comment date: August 23, 1996, in accordance with Standard
Paragraph E at the end of this notice.
8. Wisconsin Power & Light Company
[Docket No. ER96-2625-000]
Take notice that on August 5, 1996, Wisconsin Power & Light Company
(WPL), tendered for filing an amended Wholesale Power Contract dated
July 31, 1996, between the City of Plymouth and WPL. WPL states that
this amended Wholesale Power Contract revises the previous agreement
between the two parties dated October 31, 1989, and designated Rate
Schedule Number 75 by the Commission.
The parties have amended the Wholesale Power Contract to add an
additional delivery point. Service under this amended Wholesale Power
Contract will be in accordance with standard WPL Rate Schedule W-3.
WPL requests that an effective date concurrent with the amendments
effective date be assigned. WPL states that copies of the filing have
been provided to the City of Plymouth and the Public Service Commission
of Wisconsin.
Comment date: August 23, 1996, in accordance with Standard
Paragraph E at the end of this notice.
9. Kansas City Power & Light Company
[Docket No. ER96-2626-000]
Take notice that on August 5, 1996, Kansas City Power & Light
Company (KCPL), tendered for filing a Service Agreement dated July 15,
1996, between KCPL and VTEC Energy Inc. (VTEC). KCPL proposes an
effective date of July 15, 1996, and requests waiver of the
Commission's notice requirement. This Agreement provides for the rates
and charges for Non-Firm Transmission Service between KCPL and VTEC.
In its filing, KCPL states that the rates included in the above-
mentioned Service Agreement are KCPL's rates and charges from the
compliance filing to FERC Order 888 in Docket No. ER96-1867-000.
Comment date: August 23, 1996, in accordance with Standard
Paragraph E at the end of this notice.
10. New Jersey Natural Energy Company
[Docket No. ER96-2627-000]
Take notice that on August 5, 1996, New Jersey Natural Energy
Company (NJNE), tendered for filing, pursuant to Section 207 of the
Commission's Rules of Practice and Procedure, 18 CFR 385.207, an
application requesting acceptance of its proposed FERC Electric Rate
Schedule No. 1, authorizing market-based rates, granting waivers of
certain Commission Regulations and granting certain blanket approvals.
Consistent with these requests, NJNE seeks authority to engage in
electric power marketing and to sell power at market-based rates.
Comment date: August 23, 1996, in accordance with Standard
Paragraph E at the end of this notice.
11. Kentucky Utilities Company
[Docket No. ER96-2628-000]
Take notice that on August 5, 1996, Kentucky Utilities Company
(KU), tendered for filing service agreements between KU and KOCH Power
Services, Inc., Industrial Energy Applications, Inc., Western Gas
Resources Power Marketing, Inc., Dayton Power & Light, AES Power, Inc.,
Morgan Stanley Capital Group, Inc., Delhi Energy Services, Inc.,
UtiliCorp United, Engelhard Power Marketing, Inc., KN Marketing, Inc.,
Entergy Services, Inc., Commonwealth Edison Company, Florida Power
Corporation, Southern Company Services, Inc., MIDCON Power Services
Corp., South Carolina Public Service Authority, Oglethorpe Power
Corporation, TransCanada Power Corp., DuPont Power Marketing, Inc.,
Valero Power Services Company, City of Tallahassee, Aquila Power
Corporation, Calpine Power Services Company, Illinova Power Marketing,
Alabama Electric Cooperative, Inc. and Duke/Louis Dreyfus L.L.C. under
its Power Services (PS) Tariff. KU requests an effective date of August
5, 1996.
Comment date: August 23, 1996, in accordance with Standard
Paragraph E at the end of this notice.
Standard Paragraph
E. Any person desiring to be heard or to protest said filing should
file a motion to intervene or protest with the Federal Energy
Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426,
in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such
motions or protests should be filed on or before the comment date.
Protests will be considered by the Commission in determining the
appropriate action to be taken, but will not serve to make protestants
parties to the proceeding. Any person wishing to become a party must
file a motion to intervene. Copies of this filing are on file with the
Commission and are available for public inspection.
Lois D. Cashell,
Secretary.
[FR Doc. 96-20913 Filed 8-15-96; 8:45 am]
BILLING CODE 6717-01-P