[Federal Register Volume 63, Number 158 (Monday, August 17, 1998)]
[Notices]
[Pages 43922-43925]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 98-21962]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. EG98-88-000, et al.]
East Syracuse Generating Company, L.P., et al.; Electric Rate and
Corporate Regulation Filings
August 10, 1998.
Take notice that the following filings have been made with the
Commission:
1. East Syracuse Generating Co., L.P.
[Docket No. EG98-88-000]
On August 6, 1998, East Syracuse Generating Company, L.P.
(Applicant), with its principal office at 7500 Old Georgetown Road,
13th Floor, Bethesda, Maryland, 20814-6161, filed with the Federal
Energy Regulatory Commission an amendment to its June 16, 1998
application for determination of exempt wholesale generator status
pursuant to Part 365 of the Commission's regulations.
Applicant states that it will be engaged in owning and operating
the East Syracuse project consisting of a 101 megawatt cogeneration
facility located in East Syracuse, New York (the Eligible Facility) and
selling electric energy exclusively at wholesale. Electric energy
[[Page 43923]]
produced by the Eligible Facility is sold exclusively at wholesale.
Applicant further states that, as lessor of the Eligible Facility, it
acts as an owner, with respect to its care, custody and control over
the Eligible Facility.
Comment date: August 26, 1998, in accordance with Standard
Paragraph E at the end of this notice. The Commission will limit its
consideration of comments to those that concern the adequacy or
accuracy of the application.
2. Central Hudson Gas & Electric Corporation
[Docket No. ER98-3684-000]
Take notice that on July 9, 1998, Central Hudson Gas & Electric
Corporation, tendered for filing its quarterly report for the period
ending June 30, 1998.
Comment date: August 21, 1998, in accordance with Standard
Paragraph E at the end of this notice.
3. Public Service Electric and Gas Company
[Docket No. ER98-3829-000]
Take notice that on July 21, 1998, Public Service Electric and Gas
Company, tendered for filing its second quarter report for 1998 in the
above-referenced docket.
Comment date: August 21, 1998, in accordance with Standard
Paragraph E at the end of this notice.
4. Consolidated Edison Company of New York, Inc
[Docket No. ER98-3846-000]
Take notice that on August 5, 1998, Consolidated Edison Company of
New York, Inc. (Con Edison), tendered for filing an amended filing of
the service agreement to provide Firm Point-To-Point Transmission
service under Con Edison's Open Access Transmission Tariff to Aquila
Power Corporation (the Customer).
The service agreement is proposed to be effective on July 20, 1998
and terminate on July 21, 1998.
Con Edison states that a copy of this filing has been served by
mail upon the Customer.
Comment date: August 25, 1998, in accordance with Standard
Paragraph E at the end of this notice.
5. Consolidated Edison Company of New York, Inc.
[Docket No. ER98-3850-000]
Take notice that on August 5, 1998, Consolidated Edison Company of
New York, Inc. (Con Edison), tendered for filing an amended filing of
the service agreement to provide Firm-Point-To-Point Transmission
service under Con Edison's Open Access Transmission Tariff to
Constellation Power Source, Inc. (Customer).
The service agreement is proposed to be effective on July 21, 1998
and terminate on July 21, 1998.
Con Edison states that a copy of this filing has been served by
mail upon the Customer.
Comment date: August 25, 1998, in accordance with Standard
Paragraph E at the end of this notice.
6. Consolidated Edison Company of New York, Inc.
[Docket No. ER98-3851-000]
Take notice that on August 5, 1998, Consolidated Edison Company of
New York, Inc. (Con Edison), tendered for filing an amended filing of
the service agreement to provide Firm-Point-To-Point Transmission
service under Con Edison's Open Access Transmission Tariff to PP&L
Energy Marketing (Customer).
The service agreement is proposed to be effective on July 21, 1998
and terminate on July 21, 1998.
Con Edison states that a copy of this filing has been served by
mail upon the Customer.
Comment date: August 25, 1998, in accordance with Standard
Paragraph E at the end of this notice.
7. Consolidated Edison Company of New York, Inc.
[Docket No. ER98-3852-000]
Take notice that on August 5, 1998, Consolidated Edison Company of
New York, Inc. (Con Edison), tendered for filing an amended filing of
the service agreement to provide Firm-Point-To-Point Transmission
service under Con Edison's Open Access Transmission Tariff to Aquila
Power Corporation (Customer).
The service agreement is proposed to be effective on July 21, 1998
and terminate on July 25, 1998.
Con Edison states that a copy of this filing has been served by
mail upon the Customer.
Comment date: August 25, 1998, in accordance with Standard
Paragraph E at the end of this notice.
8. Consolidated Edison Company of New York, Inc.
[Docket No. ER98-3870-000]
Take notice that on August 5, 1998 Consolidated Edison Company of
New York, Inc. (Con Edison), tendered for filing an amended filing of
the executed service agreement under Con Edison's Open Access
Transmission Tariff to Strategic Power Management, Inc. (the Customer).
Con Edison states that a copy of this filing has been served by
mail upon the Customer.
Comment date: August 25, 1998, in accordance with Standard
Paragraph E at the end of this notice.
9. Consolidated Edison Company of New York, Inc.
[Docket No. ER98-3957-000]
Take notice that on August 5, 1998, Consolidated Edison Company of
New York, Inc. (Con Edison), tendered for filing an amended filing of
the service agreement to provide Firm-Point-To-Point Transmission
service under Con Edison's Open Access Transmission Tariff to Coral
Power L.L.C. (the Customer).
The service agreement is proposed to be effective on July 23, 1998
and terminate on July 23, 1998.
Con Edison states that a copy of this filing has been served by
mail upon the Customer.
Comment date: August 25, 1998, in accordance with Standard
Paragraph E at the end of this notice.
10. Consolidated Edison Company Of New York, Inc.
[Docket No. ER98-3958-000]
Take notice that on August 5, 1998, Consolidated Edison Company of
New York, Inc. (Con Edison), tendered for filing an amended filing of
the firm point-to-point service agreement to provide service under Con
Edison's Open Access Transmission Tariff to PP&L Energy Marketing (the
Customer).
The service agreement is proposed to be effective on July 22, 1998
and terminate on July 22, 1998.
Con Edison states that a copy of this filing has been served by
mail upon the Customer.
Comment date: August 25, 1998, in accordance with Standard
Paragraph E at the end of this notice.
11. Consolidated Edison Company of New York, Inc.
[Docket No. ER98-3959-000]
Take notice that on August 5, 1998, Consolidated Edison Company of
New York, Inc. (Con Edison), tendered for filing an amended filing of
the service agreement to provide Firm Point-To-Point Transmission
service under Con Edison's Open Access Transmission Tariff to Coral
Power L.L.C. (the Customer).
The service agreement is proposed to be effective on July 22, 1998
and terminate on July 22, 1998.
Con Edison states that a copy of this filing has been served by
mail upon the Customer.
[[Page 43924]]
Comment date: August 25, 1998, in accordance with Standard
Paragraph E at the end of this notice.
12. Consolidated Edison Company of New York, Inc.
[Docket No. ER98-3960-000]
Take notice that on August 5, 1998, Consolidated Edison Company of
New York, Inc. (Con Edison), tendered for filing an amended filing of
the Firm Point-To-Point Transmission Service agreement to provide firm
electric service under Con Edison's Open Access Transmission Tariff to
PP&L Energy Marketing (the Customer).
This agreement is proposed to be effective on July 22, 1998 and
terminate on July 22, 1998.
Con Edison states that a copy of this filing has been served by
mail upon the Customer.
Comment date: August 25, 1998, in accordance with Standard
Paragraph E at the end of this notice.
13. Consolidated Edison Company of New York, Inc.
[Docket No. ER98-3961-000]
Take notice that on August 5, 1998, Consolidated Edison Company of
New York, Inc. (Con Edison), tendered for filing an amended filing of
the service agreement to provide Firm Point-To-Point Transmission
service under Con Edison's Open Access Transmission Tariff to PP&L
Energy Marketing (the Customer).
The service agreement is proposed to be effective on July 23, 1998
and terminate on July 23, 1998.
Con Edison states that a copy of this filing has been served by
mail upon the Customer.
Comment date: August 25, 1998, in accordance with Standard
Paragraph E at the end of this notice.
14. Tampa Electric Company
[Docket No. ER98-4126-000]
Take notice that on August 5, 1998, Tampa Electric Company (Tampa
Electric) tendered for filing pursuant to Section 205 of the Federal
Power Act and 18 CFR Part 35, et seq., a Contract for the Purchase and
Sale of Power and Energy (Contract) between Tampa Electric and Tenaska
Power Services Co. (Tenaska). The Contract provides for the negotiation
of individual transactions in which Tampa Electric will sell power and
energy to Tenaska.
Tampa Electric proposes an effective date of October 4, 1998 for
the Contract.
Copies of the filing have been served on Tenaska and the Florida
Public Service Commission.
Comment date: August 25, 1998, in accordance with Standard
Paragraph E at the end of this notice.
15. Northern States Power Company (Minnesota) and Northern States
Power Company (Wisconsin)
[Docket No. ER98-4127-000]
Take notice that on August 5, 1998, Northern States Power Company
(Minnesota) and Northern States Power Company (Wisconsin) (jointly
NSP), tendered for filing a Short-Term Firm Point-To-Point Transmission
Service Agreement between NSP and Enron Power Marketing.
NSP requests that the Commission accept the agreement effective
July 14, 1998, and requests waiver of the Commission's notice
requirements in order for the agreement to be accepted for filing on
the date requested.
Comment date: August 25, 1998, in accordance with Standard
Paragraph E at the end of this notice.
16. Questar Energy Trading Company
[Docket No. ER98-4128-000]
Take notice that on August 5, 1998, Questar Energy Trading Company
(Questar) submitted for filing its Notice of Termination, effective
July 6, 1998, of the power sales Confirmation Letter between Questar
and The Power Company of America, L.P. (PCA), dated as of March 27,
1998.
Notice of the termination previously was provided to and service
has been made upon PCA.
Comment date: August 25, 1998, in accordance with Standard
Paragraph E at the end of this notice.
17. Consolidated Edison Company of New York, Inc.
[Docket No. ER98-4129-000]
Take notice that on August 5, 1998, Consolidated Edison Company of
New York, Inc. (Con Edison) tendered for filing a service agreement to
provide firm transmission service pursuant to its Open Access
Transmission Tariff to Enron Power Marketing, Inc. (Customer).
Con Edison states that a copy of this filing has been served by
mail upon Customer.
Comment date: August 25, 1998, in accordance with Standard
Paragraph E at the end of this notice.
18. Tenaska Frontier Partners, Ltd.
[Docket No. ER98-4130-000]
Take notice that on August 5, 1998, Tenaska Frontier Partners, Ltd.
filed a Certificate of Concurrence of Energy Gulf States, Inc. in Rate
Schedule No. 178.
Comment date: August 25, 1998, in accordance with Standard
Paragraph E at the end of this notice.
19. South Jersey Energy Company
[Docket No. ER98-4131-000]
Take notice that on August 5, 1998, South Jersey Energy Company
(SJEC), filed a notice of termination pursuant to a request for waiver
of the 60-day advance-notice requirement, to be effective June 30,
1998, relating to SJEC's termination of all power purchase and sales
transactions under the Power Agreement with The Power Company of
America. L.P.
Comment date: August 25, 1998, in accordance with Standard
Paragraph E at the end of this notice.
20. Portland General Electric Company
[Docket No. ER98-4132-000]
Take notice that on August 5, 1998, pursuant to 18 CFR 35.15, of
the Commission's Regulations, Portland General Electric Company (PGE)
filed a notice of termination and request for emergency waiver of the
Commission's 60-day advance notice requirement relating to the
Transaction Confirmation Agreement dated October 3, 1997 entered into
between PGE and The Power Company of America, L.P. pursuant to the
Western System Power Pool Agreement.
Comment date: August 25, 1998, in accordance with Standard
Paragraph E at the end of this notice.
21. Public Service Electric and Gas
[Docket No. ER98-4135-000]
Take Notice that on August 5, 1998, Public Service Electric and Gas
Company (PSE&G) tendered for filing a Withdrawal of its FERC Electric
Tariff, Original Volume No. 1 (Docket No. ER82-719-000) and FERC
Electric Tariff, Original Volume No. 1 (Docket No. ER88-78-000).
Wholesale customers previously served under these tariffs are now
taking service under PSE&G's Market-Based Power Sales Tariff, FERC
Electric Tariff, Original Volume No. 6 (Docket No. ER97-837-000).
Comment date: August 25, 1998, in accordance with Standard
Paragraph E at the end of this notice.
22. Rochester Gas and Electric Corporation
[Docket No. ER98-4158-000]
Take notice that on August 5, 1998, Rochester Gas and Electric
Corporation (RG&E) tendered for filing with the Federal Energy
Regulatory Commission an executed transmission service agreement
between RG&E and NEV East,
[[Page 43925]]
L.L.C. An unexecuted version of this service agreement was submitted
previously in response to a Commission deficiency letter.
A copy of the service agreement has been served on the New York
Public Service Commission and on the Customer.
Comment date: August 25, 1998, in accordance with Standard
Paragraph E at the end of this notice.
Standard Paragraphs
E. Any person desiring to be heard or to protest said filing should
file a motion to intervene or protest with the Federal Energy
Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426,
in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such
motions or protests should be filed on or before the comment date.
Protests will be considered by the Commission in determining the
appropriate action to be taken, but will not serve to make protestants
parties to the proceeding. Any person wishing to become a party must
file a motion to intervene. Copies of these filings are on file with
the Commission and are available for public inspection.
David P. Boergers,
Secretary.
[FR Doc. 98-21962 Filed 8-14-98; 8:45 am]