  98-22081. Duke Energy Corporation; Notice of Consideration of Issuance of Amendments To Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing  

  • [Federal Register Volume 63, Number 158 (Monday, August 17, 1998)]
    [Notices]
    [Pages 43962-43964]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-22081]
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket Nos. 50-413 and 50-414]
    
    
    Duke Energy Corporation; Notice of Consideration of Issuance of 
    Amendments To Facility Operating Licenses, Proposed No Significant 
    Hazards Consideration Determination, and Opportunity for a Hearing
    
        The U.S. Nuclear Regulatory Commission (the Commission) is 
    considering issuance of amendments to Facility Operating License Nos. 
    NPF-35 and NPF-52, issued to Duke Energy Corporation (the licensee), 
    for operation of the Catawba Nuclear Station, Units 1 and 2, located in 
    York County, South Carolina.
        The proposed amendments would revise the Technical Specifications 
    (TS), deleting Surveillance Requirement 4.8.1.1.2.i.2. This requires 
    the performance, every 10 years, of a pressure test of those portions 
    of the diesel fuel oil system designed to Section III, subsection ND of 
    the American Society of Mechanical Engineers (ASME) Boiler and Pressure 
    Vessel Code (ASME Code) at a test pressure equal to 110 percent of the 
    system design pressure. This requirement is in conflict with a relief 
    granted by the staff on February 13, 1995, authorizing the licensee to 
    implement the alternative rules of ASME Section XI, Code Case N-498-1. 
    Code Case N-498-1 permits the use of VT-2 visual examination in 
    conjunction with a system pressure test on Class 3 systems in lieu of 
    hydrostatic testing. The deletion of TS 4.8.1.1.2.i.2 would remove such 
    conflict.
        The licensee requested approval on an exigent basis pursuant to its 
    request for enforcement discretion. The staff verbally granted the 
    enforcement discretion on August 6, 1998, and affirmed it by a 
    subsequent notice of enforcement discretion (NOED) letter dated August 
    7, 1998. The NOED stated that the enforcement discretion is in effect 
    until the issuance of amendments to revise TS 4.8.1.1.2.i.2. The staff 
    intends to issue such amendments within 4 weeks of the NOED letter. 
    This issuance schedule would not be accommodated by the normal 30-day 
    notice to the public.
        Before issuance of the proposed license amendments, the Commission 
    will have made findings required by the Atomic Energy Act of 1954, as 
    amended (the Act) and the Commission's regulations.
        Pursuant to 10 CFR 50.91(a)(6) for amendments to be granted under 
    exigent circumstances, the NRC staff must determine that the amendment 
    request involves no significant hazards consideration. Under the 
    Commission's regulations in 10 CFR 50.92, this means that operation of 
    the facility in accordance with the proposed amendment would not (1) 
    involve a significant increase in the probability or consequences of an 
    accident previously evaluated; or (2) create the possibility of a new 
    or different kind of accident from any accident previously evaluated; 
    or (3) involve a significant reduction in a margin of safety. As 
    required by 10 CFR 50.91(a), the licensee has provided its analysis of 
    the issue of no significant hazards consideration, which is presented 
    below:
    
    First Standard
    
        Implementation of this amendment would not involve a significant 
    increase in the probability or consequences of an accident 
    previously evaluated. Approval of this amendment will have no 
    significant effect on accident probabilities or consequences. The 
    diesel generator fuel oil system is not an accident initiating 
    system; therefore, there will be no impact on any accident 
    probabilities by the approval of this amendment. Each unit's diesel 
    generator fuel oil system is currently fully capable of meeting its 
    design basis accident mitigating function. Therefore, there will be 
    no impact on any accident consequences.
    
    Second Standard
    
        Implementation of this amendment would not create the 
    possibility of a new or different kind of accident from any accident 
    previously evaluated. No new accident causal mechanisms are created 
    as a result of NRC approval of this amendment request. No changes 
    are being made to the plant which will introduce any new accident 
    causal mechanisms. This amendment request does not impact any plant 
    systems that are accident initiators, since the diesel generator 
    fuel oil system is an accident mitigating system.
    
    Third Standard
    
        Implementation of this amendment would not involve a significant 
    reduction in a margin of safety. Margin of safety is related to the 
    confidence in the ability of the fission product barriers to perform 
    their design functions during and following an accident situation. 
    These barriers include the fuel cladding, the reactor coolant 
    system, and the containment system. The performance of these fission 
    product barriers will not be impacted by implementation of this 
    proposed amendment. The diesel generator fuel oil system for each 
    unit is already capable of performing as designed. No safety margins 
    will be impacted.
        Based upon the preceding analysis, Duke Energy [Corporation] has 
    concluded that the proposed amendment does not involve a significant 
    hazards consideration.
    
        The NRC staff has reviewed the licensee's analysis and, based on 
    this review, it appears that the three
    
    [[Page 43963]]
    
    standards of 10 CFR 50.92(c) are satisfied. Therefore, the NRC staff 
    proposes to determine that the amendment request involves no 
    significant hazards consideration.
        The Commission is seeking public comments on this proposed 
    determination. Any comments received within 14 days after the date of 
    publication of this notice will be considered in making any final 
    determination.
        Normally, the Commission will not issue the amendments until the 
    expiration of the 14-day notice period. However, should circumstances 
    change during the notice period, such that failure to act in a timely 
    way would result, for example, in derating or shutdown of the facility, 
    the Commission may issue the license amendments before the expiration 
    of the 14-day notice period, provided that its final determination is 
    that the amendments involve no significant hazards consideration. The 
    final determination will consider all public and State comments 
    received. Should the Commission take this action, it will publish in 
    the Federal Register a notice of issuance. The Commission expects that 
    the need to take this action will occur very infrequently.
        Written comments may be submitted by mail to the Chief, Rules and 
    Directives Branch, Division of Administrative Services, Office of 
    Administration, U.S. Nuclear Regulatory Commission, Washington, DC 
    20555-0001, and should cite the publication date and page number of 
    this Federal Register notice. Written comments may also be delivered to 
    Room 6D59, Two White Flint North, 11545 Rockville Pike, Rockville, 
    Maryland, from 7:30 a.m. to 4:15 p.m. Federal workdays. Copies of 
    written comments received may be examined at the NRC Public Document 
    Room, the Gelman Building, 2120 L Street, NW., Washington, DC.
        The filing of requests for hearing and petitions for leave to 
    intervene is discussed below.
        By September 16, 1998, the licensee may file a request for a 
    hearing with respect to issuance of the amendments to the subject 
    facility operating license and any person whose interest may be 
    affected by this proceeding and who wishes to participate as a party in 
    the proceeding must file a written request for a hearing and a petition 
    for leave to intervene. Requests for a hearing and a petition for leave 
    to intervene shall be filed in accordance with the Commission's ``Rules 
    of Practice for Domestic Licensing Proceedings'' in 10 CFR Part 2. 
    Interested persons should consult a current copy of 10 CFR 2.714 which 
    is available at the Commission's Public Document Room, the Gelman 
    Building, 2120 L Street, NW., Washington, DC, and at the local public 
    document room located at the York County Library, 138 East Black 
    Street, Rock Hill, South Carolina. If a request for a hearing or 
    petition for leave to intervene is filed by the above date, the 
    Commission or an Atomic Safety and Licensing Board, designated by the 
    Commission or by the Chairman of the Atomic Safety and Licensing Board 
    Panel, will rule on the request and/or petition; and the Secretary or 
    the designated Atomic Safety and Licensing Board will issue a notice of 
    hearing or an appropriate order.
        As required by 10 CFR 2.714, a petition for leave to intervene 
    shall set forth with particularity the interest of the petitioner in 
    the proceeding, and how that interest may be affected by the results of 
    the proceeding. The petition should specifically explain the reasons 
    why intervention should be permitted with particular reference to the 
    following factors: (1) the nature of the petitioner's right under the 
    Act to be made a party to the proceeding; (2) the nature and extent of 
    the petitioner's property, financial, or other interest in the 
    proceeding; and (3) the possible effect of any order which may be 
    entered in the proceeding on the petitioner's interest. The petition 
    should also identify the specific aspect(s) of the subject matter of 
    the proceeding as to which petitioner wishes to intervene. Any person 
    who has filed a petition for leave to intervene or who has been 
    admitted as a party may amend the petition without requesting leave of 
    the Board up to 15 days prior to the first prehearing conference 
    scheduled in the proceeding, but such an amended petition must satisfy 
    the specificity requirements described above.
        Not later than 15 days prior to the first prehearing conference 
    scheduled in the proceeding, a petitioner shall file a supplement to 
    the petition to intervene which must include a list of the contentions 
    which are sought to be litigated in the matter. Each contention must 
    consist of a specific statement of the issue of law or fact to be 
    raised or controverted. In addition, the petitioner shall provide a 
    brief explanation of the bases of the contention and a concise 
    statement of the alleged facts or expert opinion which support the 
    contention and on which the petitioner intends to rely in proving the 
    contention at the hearing. The petitioner must also provide references 
    to those specific sources and documents of which the petitioner is 
    aware and on which the petitioner intends to rely to establish those 
    facts or expert opinion. Petitioner must provide sufficient information 
    to show that a genuine dispute exists with the applicant on a material 
    issue of law or fact. Contentions shall be limited to matters within 
    the scope of the amendments under consideration. The contention must be 
    one which, if proven, would entitle the petitioner to relief. A 
    petitioner who fails to file such a supplement which satisfies these 
    requirements with respect to at least one contention will not be 
    permitted to participate as a party.
        Those permitted to intervene become parties to the proceeding, 
    subject to any limitations in the order granting leave to intervene, 
    and have the opportunity to participate fully in the conduct of the 
    hearing, including the opportunity to present evidence and cross-
    examine witnesses.
        If the amendments are issued before the expiration of the 30-day 
    hearing period, the Commission will make a final determination on the 
    issue of no significant hazards consideration. If a hearing is 
    requested, the final determination will serve to decide when the 
    hearing is held.
        If the final determination is that the amendment request involves 
    no significant hazards consideration, the Commission may issue the 
    amendments and make them immediately effective, notwithstanding the 
    request for a hearing. Any hearing held would take place after issuance 
    of the amendments.
        If the final determination is that the amendment request involves a 
    significant hazards consideration, any hearing held would take place 
    before the issuance of any amendments.
        A request for a hearing or a petition for leave to intervene must 
    be filed with the Secretary of the Commission, U.S. Nuclear Regulatory 
    Commission, Washington, DC 20555-0001, Attention: Rulemakings and 
    Adjudications Staff, or may be delivered to the Commission's Public 
    Document Room, the Gelman Building, 2120 L Street, NW., Washington, DC, 
    by the above date. A copy of the petition should also be sent to the 
    Office of the General Counsel, U.S. Nuclear Regulatory Commission, 
    Washington, DC 20555-0001, and to Mr. Paul R. Newton, Legal Department 
    (PB05E), Duke Energy Corporation, 422 South Church Street, Charlotte, 
    North Carolina, 28242, attorney for the licensee.
        Nontimely filings of petitions for leave to intervene, amended 
    petitions, supplemental petitions and/or requests for hearing will not 
    be entertained absent a determination by the Commission, the presiding 
    officer or the presiding Atomic Safety and Licensing
    
    [[Page 43964]]
    
    Board that the petition and/or request should be granted based upon a 
    balancing of the factors specified in 10 CFR 2.714(a)(1)(I)-(v) and 
    2.714(d).
        For further details with respect to this action, see the 
    application for amendments dated August 6, 1998, which is available for 
    public inspection at the Commission's Public Document Room, the Gelman 
    Building, 2120 L Street, NW., Washington, DC, and at the local public 
    document room located at the York County Library, 138 East Black 
    Street, Rock Hill, South Carolina.
    
        Dated at Rockville, Maryland, this 11th day of August 1998.
    
        For the Nuclear Regulatory Commission.
    Peter S. Tam,
    Senior Project Manager, Project Directorate II-2, Division of Reactor 
    Projects--I/II, Office of Nuclear Reactor Regulation.
    [FR Doc. 98-22081 Filed 8-14-98; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
08/17/1998
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
98-22081
Pages:
43962-43964 (3 pages)
Docket Numbers:
Docket Nos. 50-413 and 50-414
PDF File:
98-22081.pdf