-
Start Preamble
AGENCY:
Nuclear Regulatory Commission.
ACTION:
Standard review plan—final section revision; final issuance.
SUMMARY:
The U.S. Nuclear Regulatory Commission (NRC) is issuing final revisions to the following sections in Chapter 13, “Conduct of Operations,” of NUREG-0800, “Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants: LWR Edition”: Section 13.1.1, “Management and Technical Support Organization”; Section 13.1.2-13.1.3, “Operating Organization”; Section 13.2.1, “Reactor Operator Requalification Program; Reactor Operator Training”; Section 13.2.2, “Non-licensed Plant Staff Training”; and Section 13.5.1.1, “Administrative Procedures—General.”
DATES:
The effective date of this Standard Review Plan (SRP) update is September 16, 2016.
ADDRESSES:
Please refer to Docket ID NRC-2014-0203 when contacting the NRC about the availability of information regarding this document. You may access publicly-available information related to this document using any of the following methods:
- Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2014-0203. Address questions about NRC dockets to Carol Gallagher; telephone: 301-415-3463; email: Carol.Gallagher@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document.
- NRC's Agencywide Documents Access and Management System (ADAMS): You may obtain publicly-available documents online in the ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select “ADAMS Public Documents” and then select “Begin Web-based ADAMS Search.” For problems with ADAMS, please contact the NRC's Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. For the convenience of the reader, the ADAMS accession numbers are provided in a table in the “Availability of Documents” section of this document.
- NRC's PDR: You may examine and purchase copies of public documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852.
- The NRC posts its issued staff guidance on the NRC's external Web page (http://www.nrc.gov/reading-rm/doc-collections/nuregs/staff/sr0800/).
FOR FURTHER INFORMATION CONTACT:
Mark D. Notich, Office of New Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-3053; email: Mark.Notich@nrc.gov.
End Further Info End Preamble Start Supplemental InformationSUPPLEMENTARY INFORMATION:
I. Background
On September 24, 2014 (79 FR 57141), the NRC published for public comment the proposed revisions to Chapter 13 of the SRP. A summary of the comments and the NRC staff's disposition of the comments are available in a separate document, “Public Comment Response Table SRP Section 13.1.1 through 13.5.1.1” (ADAMS Accession No. ML15008A024).
The Office of New Reactors is revising these sections from their current versions. Details of specific changes in the proposed revisions are included at the end of each of the proposed sections.
The changes to this SRP chapter reflect NRC staff's current review methods and practices based on lessons learned from the NRC's reviews of design certification and combined license applications completed since the last revision of this chapter.
II. Backfitting and Issue Finality
Issuance of these revised SRP sections does not constitute backfitting as defined in § 50.109 of title 10 of the Code of Federal Regulations (10 CFR), “Backfitting,” (the Backfit rule) or otherwise be inconsistent with the issue finality provisions in 10 CFR part 52. The NRC's position is based upon the following considerations:
1. The SRP positions would not constitute backfitting, inasmuch as the SRP is internal guidance directed at the NRC staff with respect to their regulatory responsibilities.
The SRP provides guidance to the NRC staff on how to review an application for NRC's regulatory approval in the form of licensing. Changes in internal staff guidance are not matters for which either nuclear power plant applicants or licensees are protected under either the Backfit Rule or the issue finality provisions of 10 CFR part 52.
2. The NRC staff has no intention to impose the SRP positions on existing licensees either now or in the future.
The staff does not intend to impose or apply the positions described in the SRP to existing (already issued) licenses and regulatory approvals. Therefore, the issuance of a final SRP—even if considered guidance that is within the purview of the issue finality provisions in 10 CFR part 52—need not be evaluated as if it were a backfit or as being inconsistent with issue finality provisions. If, in the future, the staff seeks to impose a position in the SRP on holders of already issued licenses in a manner which does not provide issue finality as described in the applicable issue finality provision, then the staff must make the showing as set forth in the Backfit Rule or address the criteria for avoiding issue finality as described in the applicable issue finality provision.
3. Backfitting and issue finality do not—with limited exceptions not applicable here—protect current or future applicants.
Applicants and potential applicants are not, with certain exceptions, protected by either the Backfit Rule or any issue finality provisions under 10 CFR part 52. This is because neither the Backfit Rule nor the issue finality provisions under 10 CFR part 52—with certain exclusions discussed in the next paragraph—were intended to apply to every NRC action that substantially changes the expectations of current and future applicants.
The exceptions to the general principle are applicable whenever an applicant references a 10 CFR part 52 license (e.g., an early site permit) and/or NRC regulatory approval (e.g., a design certification rule) with specified issue finality provisions. The staff does not, at this time, intend to impose the positions represented in the SRP in a manner that is inconsistent with any issue finality provisions. If, in the future, the staff seeks to impose a position in the SRP in a manner that does not provide issue finality as Start Printed Page 54855described in the applicable issue finality provision, then the staff must address the criteria for avoiding issue finality as described in the applicable issue finality provision.
III. Availability of Documents
The documents identified in the following table are available to interested persons.
SRP Section Current version Final revision Redline strikeout 13.1.1 ML13311B662 ML15005A449 ML16078A165 13.1.2-13.1.3 ML13311B719 ML15007A296 ML16081A063 13.2.1 ML13311B565 ML15006A035 ML16081A014 13.2.2 ML14030A091 ML15006A129 ML16081A022 13.5.1.1 ML13115A067 ML15006A205 ML16078A352 IV. Congressional Review Act
In accordance with the Congressional Review Act, the NRC has determined that this action is not a major rule and has verified this determination with the Office of Information and Regulatory Affairs of the Office of Management and Budget.
Start SignatureDated at Rockville, Maryland, this 11th day of August, 2016.
For the Nuclear Regulatory Commission.
Joseph Colaccino,
Chief, New Reactor Rulemaking and Guidance Branch, Division of Engineering, Infrastructure, and Advanced Reactors, Office of New Reactors.
[FR Doc. 2016-19562 Filed 8-16-16; 8:45 am]
BILLING CODE 7590-01-P
Document Information
- Effective Date:
- 9/16/2016
- Published:
- 08/17/2016
- Department:
- Nuclear Regulatory Commission
- Entry Type:
- Notice
- Action:
- Standard review plan--final section revision; final issuance.
- Document Number:
- 2016-19562
- Dates:
- The effective date of this Standard Review Plan (SRP) update is September 16, 2016.
- Pages:
- 54854-54855 (2 pages)
- Docket Numbers:
- NRC-2014-0203
- PDF File:
- 2016-19562.pdf