[Federal Register Volume 59, Number 159 (Thursday, August 18, 1994)]
[Unknown Section]
[Page 0]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 94-20244]
[[Page Unknown]]
[Federal Register: August 18, 1994]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
[Docket No. CP94-707-000]
Northern Natural Gas Company; Request Under Blanket Authorization
August 12, 1994.
Take notice that on August 9, 1994, Northern Natural Gas Company
(Northern), 1111 South 103rd Street, Omaha, Nebraska 68124-1000, filed
in Docket No. CP94-707-000, a request pursuant to Secs. 157.205 and
157.212 of the Commission's Regulations under the Natural Gas Act (18
CFR 157.205 and 157.212) for authorization to upgrade the CRI Feeders
Delivery Point located at Section 34, T6N, R13E, in Texas County,
Oklahoma, in order to provide increased natural gas deliveries to
Amarillo Natural Gas, Inc. (Amarillo), under the blanket certificate
issued in Docket No. CP82-401-000, pursuant to Section 7(c) of the
Natural Gas Act, all as more fully set forth in the request which is on
file with the Commission and open to public inspection.
Northern states the proposed increased service at the Amarillo/CRI
Feeders Delivery Point will impact its peak day and annual deliveries
by increasing the peak day volumes from 80 Mcf to 1,100 Mcf and by
increasing the annual volumes from 19,000 Mcf to 133,200 Mcf. Northern
indicates that the total estimated cost to upgrade the Amarillo/CRI
Feeders Delivery Point will be $16,000, and will be financed in
accordance with the General Terms and Conditions of Northern's FERC Gas
Tariff, Fifth Revised Volume No. 1.
Northern advises that the total volumes to be delivered to the
customer after the request do not exceed the total volumes authorized
prior to the request. Northern states that the proposed activity is not
prohibited by its existing tariff and that it has sufficient capacity
to accomplish the increased service to the Amarillo/CRI Feeders
Delivery Point without detriment or disadvantage to Northern's other
customers.
Northern states that a copy of this filing has been mailed to each
of the affected state commissions.
Any person or the Commission's staff may, within 45 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to Sec. 157.205 of the
Regulations under the Natural Gas Act (18 CFR 157.205) a protest to the
request. If no protest is filed within the time allowed therefore, the
proposed activity shall be deemed to be authorized effective the day
after the time allowed for filing a protest. If a protest is filed and
not withdrawn within 30 days after the time allowed for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to Section 7 of the Natural Gas Act.
Lois D. Cashell,
Secretary.
[FR Doc. 94-20244 Filed 8-17-94; 8:45 am]
BILLING CODE 6717-01-M