94-20273. FORIA Hydro Corporation; Notice of Environmental Assessment Scoping\1\  

  • [Federal Register Volume 59, Number 159 (Thursday, August 18, 1994)]
    [Unknown Section]
    [Page 0]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 94-20273]
    
    
    [[Page Unknown]]
    
    [Federal Register: August 18, 1994]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Project No. 11346-001, IA]
    
     
    
    FORIA Hydro Corporation; Notice of Environmental Assessment 
    Scoping\1\
    
    August 12, 1994.
        On March 28, 1994, the Federal Energy Regulatory Commission 
    (Commission) issued a notice indicating that staff is ready to conduct 
    an environmental analysis (REA Notice) for the proposed Fort Dodge Mill 
    Dam Project, located on the Des Moines River, in Webster County, Iowa. 
    The REA Notice also requested comments (mandatory or recommended 
    license terms and conditions, or prescriptions) from federal, state, 
    and local resource agencies, licensees and developers, Indian tribes, 
    and any other interested groups (Parties). Parties were given until May 
    28, 1994, to file comments.
    ---------------------------------------------------------------------------
    
        \1\This supersedes the Notice of Environmental Assessment 
    Scoping previously issued July 15, 1994, 59 FR 37229, July 21, 1994.
    ---------------------------------------------------------------------------
    
        The purpose of this notice is to advise all Parties as to the scope 
    of our environmental analysis and to seek additional information 
    pertinent to this analysis. The scope as presented herein is based on 
    the information filed with the Commission by FORIA Hydro Corporation 
    (the Applicant), comments received from the Parties thus far, and the 
    staff's independent analysis.
    
    Proposed Action
    
        The Applicant proposes to install new generating equipment at an 
    existing dam, reservoir and powerhouse to be called the Fort Dodge Mill 
    Dam Project.
        The proposed project would include the following features: (1) An 
    existing dam 372 feet long and 18 feet high; (2) an existing 
    impoundment with a surface area of 90 acres with a normal surface 
    elevation of approximately 990 feet above mean sea level; (3) an 
    existing powerhouse containing two new turbine-generator units at a 
    total installed capacity of 1,260 kilowatts; and (4) a proposed 13.8-
    kilovolt transmission line.
        In addition to the proposed two new turbine-generator units, the 
    Applicant proposes to install a new flat trashrack (with 2-inch clear 
    bar spacing) at the project intake.
        The Applicant proposes the following measures relating to project 
    operation to protect environmental resources in the project area. A 34-
    cubic-feet-per-second minimum flow over the project dam is proposed to 
    protect water quality and fishery resources in the downstream pool area 
    and side channel. The project would be operated in a run-of-river mode, 
    with only minor fluctuations in the headpond elevation to account for 
    natural variations in river flow. In the operational plan for the Fort 
    Dodge Mill Dam Project, the Applicant also proposes to implement a plan 
    to verify run-of-river operation and a seasonal water quality 
    monitoring program for the impoundment.
    
    Project Alternatives
    
        The Commission staff will consider alternatives, including 
    environmental measures not proposed by the Applicant. The staff will 
    review and consider alternative recommendations for additional resource 
    protection, or environmental measures that may be appropriate to 
    include in an original license. Modifications could include 
    recommendations by the agencies, the general public, and the staff.
        In addition to these alternatives, the staff will evaluate the no-
    action alternative, which would maintain the existing environment or 
    status quo at the project. There would be no enhancement of existing 
    environmental resources.
    
    Scope of the Environmental Analysis
    
    Cumulative Effects
    
    a. Geographic Scope
        We believe that water quality and resident fisheries can be 
    affected in a cumulative manner by the Fort Dodge Mill Dam Project 
    being analyzed in this Environmental Assessment (EA) and by other 
    activities on the Des Moines River. These activities include sediment 
    and nutrient concentrations in the Des Moines River and associated 
    tributaries due to channel straightening, land cultivation, and water 
    treatment by the City of Fort Dodge.
        The geographic scope of analysis defines the physical limits or 
    boundaries of the proposed action's effect on the resources. Since the 
    proposed action affects the resources differently, the geographic scope 
    for each resource may vary. In this case, for water quality and fishery 
    resources, the geographic scope of analysis will encompass the mainstem 
    of the Des Moines River from river mile 387 upstream to the confluence 
    of the Raccoon River with the Des Moines River. We chose this 
    geographic scope for these resources because the effects of project 
    operation are limited to this area and, in this case, these resources 
    are directly and indirectly affected by project operation.
    b. Temporal Scope
        The temporal scope includes a discussion of the past, present, and 
    future actions and their effects on water quality and the fishery 
    resources. Based on the license term, the temporal scope will look 30 
    to 50 years into the future, concentrating on the effect on the 
    resource from reasonably foreseeable future actions (e.g., the effect 
    of potential future water withdrawals within the project vicinity). The 
    historical discussion will, by necessity, be limited to the amount of 
    available information for each resource.
        We are seeking further information from Federal, state, and other 
    agencies and non-governmental organizations (NGO's) pertaining to past, 
    present, and future actions and effects on the resources (in the form 
    of previous studies, present plans, and future plans, goals or 
    forecasts).
    
    Environmental Issues
    
        A preliminary list of environmental issues identified by the staff 
    for coverage in an EA is presented in this section. The list is not 
    intended to be exhaustive or final, but is an initial listing of issues 
    that have been raised and appear to be important. The staff will review 
    all issues raised during the scoping process and make decisions as to 
    the level of analysis needed. If preliminary analysis indicates that 
    any issues presented in this scoping document have little potential for 
    causing significant impacts, the issue or issues will be identified and 
    the reasons for not providing a more detailed analysis will be given.
        The following issues apply to the Fort Dodge Mill Dam Project:
         Potential effects on geology and soils resources due to 
    dredging upstream and downstream of the dam.
         An evaluation of the project's potential effect on 
    dissolved oxygen (DO) downstream of the project and the need for 
    additional studies of DO.
         Effects of project operation and non-project factors on 
    vegetation and wildlife.
         Effects of project operation on any federally listed 
    threatened or endangered species in the project area.
         Probability of eligibility of dam and powerhouse on the 
    National Register of Historic Places.
         Consider the need for measures to enhance recreational 
    opportunities.
        The EA will assess the project-specific effects on the above 
    resources and whether these effects contribute adversely or 
    beneficially to the affected environment.
    
    EA Preparation Schedule
    
        The preliminary schedule for preparing the EA for the Fort Dodge 
    Mill Dam Project is:
    
    ------------------------------------------------------------------------
                    Milestones                           Target date        
    ------------------------------------------------------------------------
    Scoping...................................                  Summer 1994.
    Draft EA..................................           September 30, 1994.
    Final EA..................................            November 30, 1994.
    ------------------------------------------------------------------------
    
    Request for Comments
    
        The Commission's scoping objectives are to:
         Identify significant environmental issues,
         Determine the depth of analysis appropriate to each issue,
         Identify the resource issues not requiring detailed 
    analysis, and
         Identify reasonable project alternatives.
        Federal, state, and local resource agencies, licensees and 
    developers, Indian tribes, NGO's and other interested groups, and the 
    general public are requested to file with the Commission information 
    that they believe will assist the Commission staff in conducting an 
    accurate and thorough analysis of the site-specific and cumulative 
    environmental effects of the proposed licensing of the Fort Dodge Mill 
    Dam Project being analyzed in this EA. The types of information sought 
    include:
         Information, quantified data, or professional opinion that 
    may contribute to defining the geographical and temporal scope of the 
    analysis and identifying significant environmental issues.
         Identification of, and information from, any other EA, 
    environmental impact statement, or similar document or study (previous, 
    on-going, or planned) relevant to the proposed licensing activity in 
    the mainstem of the Des Moines River.
         Existing information and any data that would aid in 
    describing the past and present actions and effects of the project on 
    water quality and the fisheries. For example, fish stocking/management 
    histories of the Des Moines River, historic water quality data and the 
    reasons for improvement or degradation of the quality, any wetland 
    habitat losses or proposals to develop land and water resources.
         Identification of any federal, state, or local resource 
    plans and future project proposals that encompass the mainstem of the 
    Des Moines River with information on when they will be implemented, if 
    known. For example, proposals to construct or operate water treatment 
    facilities, recreation areas, water diversions, or implement fishery 
    management programs.
         Documentation that would support a conclusion that the 
    project does not or does contribute to cumulative adverse or beneficial 
    effects on resources and therefore should be excluded from further 
    study or excluded from further consideration of cumulative effects 
    within the mainstem of the Des Moines River. Documentation should 
    include, but is not limited to: how the project interacts with other 
    projects and other developmental activities; results from studies; 
    resource management policies; and reports from Federal, state, and 
    local agencies.
        To be useful in preparing the EA, the requested information must be 
    filed with the Commission no later than 30 days past the date of this 
    notice. Address all communications to: Secretary, Federal Energy 
    Regulatory Commission, 825 North Capitol Street, NE, Washington, D.C. 
    20426.
        All filings must clearly show at the top of the first page ``Fort 
    Dodge Mill Dam Project, FERC No. 11346''.
        When filing scoping comments, you should submit an original and 8 
    copies; this will assure that staff receives your information quickly. 
    Parties to the proceedings (as identified on the official Service List 
    for the Fort Dodge Mill Dam Project) must also send copies of their 
    filings, and all attachments, to the other parties listed on the 
    official service list. The official service list is available from the 
    Secretary of the Commission at the same address above.
        Any questions concerning the scoping process should be directed to 
    Mary Golato (202-219-2804) at the Federal Energy Regulatory Commission, 
    Office of Hydropower Licensing (HL 20.1), 825 North Capitol Street, NE, 
    Washington, D.C. 20426.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 94-20273 Filed 8-17-94; 8:45 am]
    BILLING CODE 6717-01-P
    
    
    

Document Information

Published:
08/18/1994
Department:
Energy Department
Entry Type:
Uncategorized Document
Document Number:
94-20273
Pages:
0-0 (1 pages)
Docket Numbers:
Federal Register: August 18, 1994, Project No. 11346-001, IA