Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection.
a. Type of Application: Original Major License.
b. Project No.: 12686-004.
c. Date filed: April 30, 2013 (revised December 5, 2013).
d. Applicant: Baker County, Oregon (Baker County).
e. Name of Project: Mason Dam Hydroelectric Project.
f. Location: The proposed project would be located on the Powder River, at the existing U.S. Bureau of Reclamation's (Reclamation) Mason dam, near Baker City, in Baker County, Oregon. The project would occupy 6.4 acres of federal land managed by Reclamation and the U.S. Forest Service.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Fred Warner Jr., Baker County Board of Commissioners Chairman, 1995 Third Street, Baker City, OR 97814, (541) 523-8200.
i. FERC Contact: Jennifer Adams, Telephone (202) 502-8087, and email jennifer.adams@ferc.gov.
j. Deadline for filing motions to intervene and protests, comments, recommendations, preliminary terms and conditions, and preliminary prescriptions: 60 days from the issuance date of this notice; reply comments are due 105 days from the issuance date of this notice.
The Commission strongly encourages electronic filing. Please file motions to intervene, protests, comments, recommendations, preliminary terms and conditions, and preliminary fishway prescriptions using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, Start Printed Page 48738please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The first page of any filing should include docket number P-12686-004.
The Commission's Rules of Practice require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency.
k. This application has been accepted for filing and is now ready for environmental analysis.
l. The Project Description: The proposed project facilities include: (1) A 6-foot diameter, 105-foot-long steel penstock; (2) a 40-foot by 28-foot powerhouse containing a single horizontal shaft Francis turbine with an installed capacity of 3.4 megawatts; (3) an approximately 0.8-mile-long, 12.47-kilovolt (kV) overhead transmission line along Black Mountain Road; (4) a substation at the interconnection point with an existing Idaho Power Company 138-kV transmission line; and (5) appurtenant facilities.
The proposed project would operate utilizing flood control, irrigation, and instream flow releases from Mason dam and established under existing agreements between the Reclamation, the U.S. Army Corps of Engineers, and/or the Baker Valley Irrigation District. Generation flow discharge would be delivered to the Powder River at the base of Mason dam in the vicinity of the exiting discharge via the project's tailrace.
Baker County estimates that the average annual generation would be about 7,510 megawatt-hours.
m. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission's Web site at http://www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. A copy is also available for inspection and reproduction at the address in item h above.
Register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support.
n. Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, and .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission's Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application.
All filings must (1) bear in all capital letters the title “PROTEST”, “MOTION TO INTERVENE”, “COMMENTS,” “REPLY COMMENTS,” “RECOMMENDATIONS,” “PRELIMINARY TERMS AND CONDITIONS,” or “PRELIMINARY FISHWAY PRESCRIPTIONS;” (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, recommendations, terms and conditions or prescriptions must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
o. Procedural Schedule:
The application will be processed according to the following revised Hydro Licensing Schedule. Revisions to the schedule may be made as appropriate.
Milestone Target date Filing of recommendations, preliminary terms and conditions, and preliminary fishway prescriptions October 2014. Commission issues EA February 2015. Comments on EA March 2015. Modified terms and conditions April 2015. q. A license applicant must file no later than 60 days following the date of issuance of the notice of acceptance and ready for environmental analysis provided for in § 5.22: (1) A copy of the water quality certification; (2) a copy of the request for certification, including proof of the date on which the certifying agency received the request; or (3) evidence of waiver of water quality certification.
r. Any qualified applicant desiring to file a competing application must submit to the Commission, on or before the specified intervention deadline date, a competing development application, or a notice of intent to file such an application. Submission of a timely notice of intent allows an interested person to file the competing development application no later than 120 days after the specified intervention deadline date. Applications for preliminary permits will not be accepted in response to this notice.
A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit a development application. A notice of intent must be served on the applicant(s) named in this public notice.
Start SignatureDated: August 11, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-19467 Filed 8-15-14; 8:45 am]
BILLING CODE 6717-01-P
Document Information
- Published:
- 08/18/2014
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 2014-19467
- Pages:
- 48737-48738 (2 pages)
- Docket Numbers:
- Project No. 12686-004
- PDF File:
- 2014-19467.pdf