94-20423. Abnormal Occurrences for First Quarter CY 1994; Dissemination of Information  

  • [Federal Register Volume 59, Number 160 (Friday, August 19, 1994)]
    [Unknown Section]
    [Page 0]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 94-20423]
    
    
    [[Page Unknown]]
    
    [Federal Register: August 19, 1994]
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
     
    
    Abnormal Occurrences for First Quarter CY 1994; Dissemination of 
    Information
    
        Section 208 of the Energy Reorganization Act of 1974, as amended, 
    requires NRC to disseminate information on abnormal occurrences (i.e., 
    unscheduled incidents or events that the Commission determines are 
    significant from the standpoint of public health and safety). During 
    the first quarter of CY 1994, the following incidents at NRC licensees 
    were determined to be abnormal occurrences (AOs) and are described 
    below, together with the remedial actions taken. The events are also 
    being included in NUREG-0090, Vol. 17, No. 1, (``Report to Congress on 
    Abnormal Occurrences: January-March 1994''). This report will be 
    available at NRC's Public Document Room, 2120 L Street NW. (Lower 
    Level), Washington, DC 20555 about three weeks after the publication 
    date of this Federal Register Notice.
    
    Nuclear Power Plants
    
    94-1  Inoperable Main Steam Line Isolation Valves at Perry Nuclear 
    Power Plant
    
        One of the AO reporting guidelines notes that a major reduction in 
    the degree of protection to public health and safety from a major 
    degradation of essential safety-related equipment can be considered an 
    AO.
        Date and Place--March 1992; Perry Nuclear Power Plant, a General 
    Electric-designed boiling water reactor (BWR), operated by Cleveland 
    Electric Illuminating Company and located about 11 kilometers (7 miles) 
    northeast of Painesville, Ohio.
        Nature and Probable Consequences--The main steam isolation, leakage 
    control and outboard drain valves in three of four main steam lines 
    penetrating containment failed to meet the Technical Specifications 
    limiting condition of operation (LCO) for leak tightness.
        For many BWRs, the LCO for leakage of each main steam isolation 
    valve (MSIV) is 0.326 standard cubic meters (11.5 standard cubic feet) 
    per hour. Because it is difficult to measure the leakage of each valve 
    individually, a maximum combined allowed leakage is specified for the 
    inboard and outboard MSIVs, and the associated control and drain 
    valves. This LCO is 0.71 standard cubic meters (25 standard cubic feet) 
    per hour. During testing at Perry in 1992, the leakages through the 
    MSIVs were approximately 12 times allowable. Due to a history of poor 
    performance and multiple main steam line valve leakage, a detailed 
    analysis of the 1992 MSIV leakage was performed. The analysis is 
    required obtaining detailed information from the licensee; a number of 
    calculations, reviews, and subsequent reanalyses; and multiple meetings 
    among the staff to determine the impact on safety.
        MSIVs are designed to close and limit the release of radioactivity 
    to the environment in the unlikely event of an accident. When the Perry 
    facility was issued an operating license, there was reasonable 
    assurance that the MSIVs would operate as intended, and the potential 
    off-site doses resulting from postulated accidents, which includes 
    assumptions regarding fuel damage and fission product release, would be 
    below the guideline values for release to the general public. Because 
    of the excessive leakage, the NRS staff, using conservative 
    assumptions, calculated the potential off-site doses to the general 
    public that might result from a postulated loss-of-coolant accident. 
    Using the very conservative licensing basis calculational 
    methodologies, the calculated dose exceeded the guidelines for release 
    to the general public. A more realistic calculation using the new 
    approach presented in draft NUREG-1465, ``Accident Source Terms for 
    Light-Water Nuclear Power Plants'' (U.S. Nuclear Regulatory Commission, 
    NUREG-1465, ``Accident Source Terms for Light-Water Nuclear Power 
    Plants,'' Draft Report for Comment, June 1992) showed that the 
    potential off-site doses would not exceed the limits for release to the 
    general public; however, additional measures would be needed to 
    minimize exposure of control room personnel.
        Cause or Causes--The licenses determined the reason for the 
    excessive MSIV leakage during the 1992 tests to be excessive friction 
    from oxide buildup, which caused end-of-stroke angular misalignment 
    resulting in non-360-degree seat contact (Licensee Event Report 50-440/
    92-006-01, ``Local Leak Rate Test Results Exceed Allowable Primary 
    Containment Leakage for Main Steam Lines A, B, and D,'' August 14, 
    1992). The reason for the difficulty of the Perry MSIVs to meet test 
    leakage limits is design geometry. The MSIVs are ``Y'' pattern valves 
    with the valve stem at 45 degrees to the piping axis. To seat properly, 
    translational motion of the poppet at the moment of impact must change 
    from the direction of the stem to a direction parallel to the axis of 
    the pipe. Seating is made more difficult because of the large size of 
    the valves (66 centimeters [26 inches] diameter) and the weights 
    involved (4500 kilograms [10,000 pounds]).
    
    Actions Taken to Prevent Recurrence
    
        Licensee--In the early 1980s, Atwood & Morrill, suppliers of the 
    MSIVs, and the BWR Owners Group recognized the need for better 
    maintenance and for modification of the MSIVs. Modifications included 
    improved poppet nose guides to overcome eccentricity during seating and 
    poppet anti-rotation devices. During the 1992 refueling outage, these 
    modifications were installed by the licensee on the six (out of eight) 
    MSIVs which have had leakage problems (Licensee Event Report 50-440/92-
    006-01, ``Local Leak Rate Test Results Exceed Allowable Primary 
    Containment Leakage for Main Steam Lines A, B, and D,'' August 14, 
    1992). Based on leakage tests performed in 1993 and 1994, the 
    modifications were successful in significantly reducing MSIV leakage.
        NRC--NRC is closely monitoring the licensee's program and progress 
    in reducing the leak rate through the MSIVs.
    * * * * *
    
    Other NRC Licensees (Industrial Radiographers, Medical Institutions, 
    Industrial Users, etc.)
    
    94-2  Medical Brachytherapy Misadministration at Hospital Metropolitano 
    in Rio Piedras, Puerto Rico
    
        One of the AO reporting guidelines notes that a therapeutic 
    exposure to any part of the body not scheduled to receive radiation can 
    be considered an abnormal occurrence.
        Date and Place--December 11, 1993; Hospital Metropolitano; Rio 
    Piedras, Puerto Rico.
        Nature and Probable Consequences--On December 9, 1993, at 5:20 
    p.m., a patient began a gynecological low-dose-rate brachytherapy 
    treatment. The patient was prescribed a treatment of 3000 centigray 
    (cGy) (3000 rad) by a 48-hours exposure to approximately 2.3 
    gigabecquerel (61.3 millicurie [mCi]) of cesium-137 (Cs-137).
        On December 11, 1993, at approximately 7:30 a.m. (about 10 hours 
    before the end of the prescribed treatment), the patient intervened 
    with the procedure by removing the implant containing three Cs-137 
    sources of approximately 730 megabecquerel (20.4 mCi) each, and placed 
    it next to her thigh. Shortly after removing the implant, the patient 
    showed the device to the floor nurse. The nurse recognized the implant 
    and understood the need for concern. She did not take the device from 
    the patient but reported the situation to her supervisor. The patient 
    apparently returned the device next to her thigh beneath the bed linen.
        At the time of being informed, the nursing supervisor was 
    experiencing difficulty with another patient, and was involved in shift 
    turnover. Due to these distractions, the supervisor failed to realize 
    the urgent nature of the situation and did not make required 
    notifications.
        On several occasions that morning, other licensee personnel entered 
    the patient's room without realizing that the radioactive source was 
    exposed because it was covered by bed linen; the patient did not notify 
    any additional staff members that she had removed the implant. 
    Approximately 2\1/2\ hours after the estimated time of the source 
    removal, the attending physician attempted to perform a routine check 
    of the implant and discovered that it had been removed and placed next 
    to the patient's thigh.
        After properly accounting for and storing the sources, the 
    physician examined and interviewed the patient. Based on discussions 
    with the patient and review of the exposure received, the attending 
    physician terminated the treatment. This decision was based on the 
    physician's determination that the treatment received was clinically 
    adequate and his concern that the patient was a threat to herself and 
    others.
        The actual dose delivered to the intended treatment site was 
    calculated to be 2270 cGy (2270 rad). The written directive was revised 
    to reflect the lower dose delivered. The licensee's evaluation of the 
    incident indicated that assuming the implant remained in the same 
    location for three hours, the maximum dose to the skin of the patient's 
    thigh (the wrong treatment site) was 572 cGy (572 rad). The licensee 
    reported that no adverse effects to the patient are expected.
        The patient was notified verbally at the time the misadministration 
    was discovered and then notified in writing on January 13, 1994.
    
    Cause or Causes
    
        The initial cause of the misadministration was the patient's 
    removal of the implant which was compounded by the failure of the two 
    nurses to follow emergency procedures. The nurses' failure to respond 
    to the emergency resulted in approximately 2\1/2\ hours of unnecessary 
    exposure.
    
    Actions Taken to Prevent Recurrence
    
        Licensee--The licensee determined that the nursing supervisor's 
    failure to make the required notifications was due to the lack of 
    familiarity with established radiation safety procedures to which he/
    she had been trained. The licensee's investigation of the event 
    revealed that the lack of familiarity with radiation safety procedures 
    was caused by the infrequent handling of patients undergoing therapy 
    with licensed materials (Letter from Hospital Metropolitano, to Hector 
    Bermudez, Senior Inspector, NMI Section, NRC Region II, Forwarding a 
    Misadministration Report dated December 29, 1993, and an Addendum to 
    the Misadministration Report dated January 11, 1994, Docket No. 030-
    11155, Licensee No. 52-16033-01). The licensee held a Radiation Safety 
    Committee meeting in which the incident and corrective actions to 
    prevent recurrence were discussed.
        The licensee decided to dedicate one floor of the hospital for all 
    therapies involving NRC-licensed materials. This will provide 
    additional controls to allow the licensee to better ensure that nurses 
    assigned to the floor are kept current and familiar with operating and 
    emergency procedures. The licensee is also evaluating the need to 
    increase patient awareness regarding non-intervention of procedures.
        The licensee is revising its procedures for responding to 
    radiological emergencies involving patients undergoing 
    radiopharmaceutical or sealed source therapy. As a minimum, the 
    procedures will define what is a radiological emergency and will 
    provide examples of situations which must be considered radiological 
    emergencies or which could result in misadministrations. The licensee 
    also committed to developing and implementing a retraining program 
    based on the revised emergency procedures for all hospital employees 
    who may be involved in handling patients receiving radiation therapy.
        NRC--A special inspection was conducted on December 15 and 17, 
    1993, to review the circumstances surrounding the misadministration and 
    the licensee's Quality Management program. A Confirmatory Action Letter 
    (CAL) was issued to the licensee on December 30, 1993 (Letter from J. 
    Philip Stohr, Director, Division of Radiation Safety and Safeguards, 
    NRC Region II, to Hospital Metropolitano, Attn: Mr. Victor Marrero, 
    Administrator, forwarding a Confirmatory Action Letter, CAL No. 2-93-
    14, Docket No. 030-11155, License No. 52-16033-01, dated December 30, 
    1993). The CAL confirmed that the licensee would revise its emergency 
    procedures and implement a training program, based on new procedures, 
    for all licensee employees who may handle patients undergoing radiation 
    therapy. An NRC medical consultant has been retained to perform a 
    clinical assessment of this misadministration. The medical consultant's 
    report is expected to be available in time to discuss his findings in 
    the second quarter AO Report. As of the issuance of this report, NRC is 
    pursuing escalated enforcement action against the licensee.
    * * * * *
    
    94-3  Teletherapy Misadministration at Triangle Radiation Oncology 
    Associates in Pittsburgh, Pennsylvania
    
        One of the AO reporting guidelines notes that a therapeutic 
    misadministration that affects two or more patients at the same 
    facility, regardless of any health effects, can be considered an 
    abnormal occurrence.
        Date and Place--December 20, 1993; Triangle Radiation Oncology 
    Associates; Pittsburgh, Pennsylvania.
        Nature and Probable Consequences--On December 20, 1993, Triangle 
    Radiation Oncology Associates in Beaver, Pennsylvania, notified NRC of 
    two potential teletherapy misadministrations that occurred between 
    December 13 and 17, 1993, at the licensee's Pittsburgh, Pennsylvania, 
    facility. The potential misadministrations were identified during a 
    review of patient records on December 17, 1993, when the licensee 
    observed calculation errors involving the depth of the dose given to 
    each of the two patients.
        Both cases involved breast treatments where the original treatment 
    plan prescribed 28 treatments of 180 centigray (cGy) (180 rad) from a 
    cobalt-60 teletherapy source (using 2 parallel opposed fields) for a 
    total absorbed dose of 5040 cGy (5040 rad). The primary breast 
    treatments were concluded on December 10, 1993. The physician wrote 
    separate written directives for each patient to receive an additional 
    1000 cGy (1000 rad) to the scar in 5 treatments of 200 cGy (200 rad) 
    per day. One of the written directives indicated that the absorbed dose 
    was to be delivered at dmax, the maximum extension of the 
    teletherapy unit, which, as stated by the physicist, is typically a 
    depth of 0.5 centimeter (cm) (0.2 inch). The other written directive 
    did not indicate a depth; however, the physician stated that the 
    intended depth was dmax.
        As described above, such a treatment plan would typically have been 
    calculated by the teletherapy technologist at the Pittsburgh facility 
    and communicated by telephone to the teletherapy physicist at the 
    Beaver facility to be checked. However, this procedure changed when the 
    computer at the Pittsburgh facility was taken out of service on 
    December 1, 1993.
        On December 9, 1993, the teletherapy technologist hand wrote a 
    paraphrased request of the written directive for the two breast-
    treatment patients needing scar booster dose calculations. Rather than 
    writing dmax, the technologist stated the tumor dose at a depth of 
    5 cm (2 inch) and sent the request, via facsimile transmission, to the 
    teletherapy physicist at the Beaver facility. Hand calculations were 
    performed for 200 cGy (200 rad) treatments at a 5 cm (2 inch) depth, 
    checked by a certified physicist, and sent back to the technologist, 
    via facsimile transmission, on December 9, 1993.
        The patients were treated from December 13 to 17, 1993, and 
    received doses of 1300 and 1320 cGy (1300 and 1320 rad) respectively, 
    rather than the 1000 cGy (1000 rad) intended. This resulted in 
    misadministrations of 30 and 32 percent greater than the intended dose. 
    The licensee's physician stated that no adverse clinical effects are 
    expected as a result of the overexposures.
        After the initial report, the licensee told NRC in subsequent 
    telephone conversations that a recalculation of the dose averaged over 
    the entire tumor volume did not exceed 30 percent and, therefore, the 
    licensee no longer thought the definition of a misadministration 
    applied in this case.
        NRC performed a special inspection on December 28 and 29, 1993, to 
    review the potential misadministrations. Information gathered during 
    this inspection, including the calculations of the administered doses, 
    was given to an NRC scientific consultant to evaluate. The scientific 
    consultant, in his report to NRC, stated that ``the dose prescription 
    was to dmax (i.e., 0.5 cm [0.2 inch] depth on the central axis) 
    and a misadministration can only be judged by considering the dose 
    given to this point. * * * clearly in both cases a misadministration 
    has taken place.'' On March 25, 1994, the licensee was informed that 
    the doses to both patients were deemed to be misadministrations. The 
    licensee submitted its report of misadministrations in a letter dated 
    April 7, 1994.
        After receiving the scientific consultant's report, an NRC medical 
    consultant was retained to perform a clinical evaluation of the 
    patients. The medical consultant is still reviewing the potential 
    health effects to the patients. The consultant's report is expected to 
    be completed in time to update this writeup in the next AO report to 
    Congress.
        The referring physician was notified and determined that, based on 
    medical judgment, informing the patients of the misadministrations 
    would be harmful.
        Cause or Causes--The technologist incorrectly transposed the 
    treatment depth on the facsimile used to prepare the treatment plan. 
    The technologist failed to make reference to dmax and entered the 
    depth value incorrectly as 5.0 cm (2 inch) instead of the intended 0.5 
    cm (0.2 inch).
    
    Actions Taken to Prevent Recurrence
    
        Licensee--The licensee implemented a requirement for a stamp to be 
    placed on all written directives that prompts a clear documentation of 
    key treatment parameters such as site, method, daily dose, fractions, 
    total doses, depth of calculation, spinal blocks, other blocks, and 
    date. Previously, key parameters had been informally handwritten 
    directives on patients's treatment charts. The licensee also formalized 
    its requirement to include the written directive for all dosimetry 
    calculation requests from the Beaver facility, and revised its ``weekly 
    chart check'' procedure to increase chart reviews from once a week to 
    twice a week, as was the practice prior to December 1, 1993.
        NRC--NRC is reviewing the licensee's April 7, 1994, 
    misadministration report and the findings of the December 28 to 29, 
    1993, NRC inspection. Once the NRC medical consultant's report is 
    received, enforcement action will be considered.
    * * * * *
    
    94-4  Lost Reference Sources at Brooks Air Force Base in San Antonio, 
    Texas
    
        One of the AO reporting guidelines notes that any serious 
    deficiency in management or procedural controls in a major area can be 
    considered an abnormal occurrence.
        Date and Place--1993; Armstrong Laboratory, Brooks Air Force Base 
    (AFB); San Antonio, Texas.
        Nature and Probable Consequences--As prescribed by the licensees's 
    Compliance Accountability and Control Procedures, in 1993, the licensee 
    performed an audit of all licensed sources at Armstrong Laboratory. 
    During this audit, the licensee identified four missing strontium-90 
    (Sr-90) reference sources of approximately 14.8 megabecquerel (400 
    microcurie) each. The licensee conducted an extensive physical search 
    for the sources and reviewed all radioactive material permits issued to 
    other organizations at Brooks AFB. When the disposition of the Sr-90 
    sealed sources could not be determined, the licensee reported the loss 
    of the four sealed sources to NRC by telephone on September 22, 1993. 
    The licensee informed NRC that the United States Air Force (USAF) 
    Inspector General would review this incident. The licensee suspected 
    that the sources had been inadvertently discarded and transported to a 
    sanitary landfill.
        The licensee evaluated possible radiation exposure to members of 
    the general public and concluded that unless the sources were removed 
    from the container, the radiation levels from the sources would be near 
    background level. Furthermore, unless a deliberate effort was made to 
    open the source capsules, an individual handling the sources would 
    receive less exposure than allowed by regulatory limits for the general 
    public.
        Cause or Causes--During 1991, the timeframe during which the 
    sources were apparently lost, a number of individuals were responsible 
    for the radiation safety program at Brooks AFB. These individuals were 
    temporary or part-time Radiation Safety Officers (RSOs), and had 
    extensive, temporary duties at other sites.
        The results of the USAF Inspector General's investigation 
    determined that ``programmatic issues started to plague radiation 
    safety at Brooks AFB after the dismantling of the base/clinic program 
    and the inception of additional duty RSOs.'' The report explained that 
    in 1986, the radiation safety function and responsibility was 
    transferred to the base clinic at Brooks AFB. Almost simultaneously, a 
    Joint Military Medical Command (JMMC) was established and the base 
    clinic became a part of JMMC. JMMC was a medical command established to 
    service all branches of the Armed Forces in the San Antonio, Texas, 
    area. With this action, the radiation safety program was managed by an 
    organization that was not responsible to any management level at Brooks 
    AFB. Furthermore, the report stated that JMMC dismantled the clinic's 
    radiation safety program, and ``requested that all organizations 
    previously under the clinic's program establish and run their own 
    radiation safety program.'' Exacerbating the problem was the 
    appointment of the additional duty RSOs, who had ``limited to general 
    knowledge of radiation safety,'' and no directives or other guidance to 
    assist them. Additionally, ``the additional duty RSOs received little 
    management oversight after they had been appointed to the RSO 
    position.''
        The investigation concluded that from 1986 through 1991, there had 
    been a lack of commitment to management oversight, and a serious 
    disregard for radiation safety issues.
    
    Actions Taken to Prevent Recurrence
    
        Licensee--In 1991, Armstrong Laboratory was placed under a new Air 
    Force Command. The Command committed to increased management oversight 
    of the radiation safety programs. Additionally, physical inventory 
    procedures were revised.
        NRC--NRC conducted an inspection (Letter from Dwight D. 
    Chamberlain, Acting Director, Division of Radiation Safety and 
    Safeguards, NRC Region IV, to Lt. Colonel Joseph J. Donnelly, chief of 
    USAF Radioisotope Committee Secretariat, forwarding Inspection Report 
    No. 030-28641/93-10, Docket No. 030-28641, License No. 42-23539-01AF, 
    dated January 19, 1994) at Brooks AFB on December 21, 1993, to review 
    the circumstances associated with the loss of licensed material, after 
    receiving a written report from the licensee on December 10, 1993. NRC 
    also held an Enforcement Conference with the licensee on February 3, 
    1994, to review the findings of the inspection and to determine 
    enforcement action.
        On February 11, 1994, NRC issued a Notice of Violation (Letter from 
    L.J. Callan, Regional Administrator, NRC Region IV, to Department of 
    the Air Force, USAF Radioisotope Committee, forwarding Notice of 
    Violation, Docket No. 030-28641, License No. 42-23539-01AF, dated 
    February 11, 1994) for violations involving (1) a failure to secure 
    licensed material and (2) failure to include in one USAF permit a 
    requirement to conduct a periodic physical inventory of all licensed 
    materials.
        These violations were categorized as a Severity Level III and a 
    Severity Level IV, respectively (Severity Level I through V range from 
    the most significant to the least significant, respectively). No civil 
    penalty was assessed because of the Air Force's discovery of this 
    violation and the promptness and comprehensiveness of the corrective 
    actions. The licensee has responded in writing to the Notice of 
    Violation and no additional actions are required.
    * * * * *
    
    94-5  Medical Brachytherapy Misadministration at the University of 
    Cincinnati in Cincinnati, Ohio
    
        One of the AO reporting guidelines notes that a therapeutic 
    exposure to a part of the body not scheduled to receive radiation can 
    be considered an abnormal occurrence.
        Date and Place--January 7, 1994; University of Cincinnati; 
    Cincinnati, Ohio.
        Nature and Probable Consequences--On January 14, 1994, NRC was 
    notified by telephone of a misadministration involving a leaking 
    iodine-125 (I-125) brachytherapy implant seed. On January 7, 1994, 16 
    I-125 seeds, each ranging from 370 to 1110 megabecquerel (MBq) (10 to 
    30 millicurie [mCi]) activity, were implanted in the brain of a 30-
    year-old male patient. Following the explant procedure on January 14, 
    1994, the licensee identified radioactive contamination in the surgical 
    room and bathroom used by the patient. Personnel from the licensee's 
    radiation safety office identified the contamination to be I-125 and 
    confirmed that at least one seed was leaking. Further analysis by the 
    licensee determined that one seed was damaged during the implant 
    procedure by a surgical staple. The seed originally contained 758 MBq 
    (20.5 mCi) of I-125 and, based on an assay of the explanted source, the 
    licensee estimated that the loss was approximately 74 MBq (2.0 mCi).
        Thyroid monitoring of the patient's visitors and hospital employees 
    involved in the care of the patient was performed by the licensee. One 
    of the licensee's employees was determined to have received a committed 
    dose equivalent to the thyroid of 50 microsievert (Sv) (5 
    millirem [mrem]). In addition, a visitor was determined to have 
    received a committed dose equivalent to the thyroid of 540 Sv 
    (54 mrem), or a total effective dose equivalent of 160 Sv (1.6 
    mrem), which is less than the annual limit for members of the general 
    public of 1000 Sv (100 mrem).
        Through patient monitoring, the licensee estimates that 
    approximately 5 percent of the free I-125 was taken up in the patient's 
    thyroid. (In a normally functioning, unblocked thyroid, approximately 
    25 percent of the free iodine would be taken up in an individual's 
    thyroid.) The licensee estimates that the uptake would result in a 
    radiation dose to the thyroid of approximately 300 centigray (300 rad). 
    The licensee does not expect any adverse medical effects to the patient 
    as a result of the misadministration. An NRC medical consultant 
    concluded that the non-radioactive iodinated contrast agent used during 
    an imaging procedure performed on the patient prior to the implant 
    blocked the absorption of the I-125. He also concluded that exposure to 
    the radiation levels described has resulted in an increased probability 
    of developing thyroid tumor(s) in the future.
        The licensee notified the referring physician, the patient, and the 
    patient's family of the misadministration.
        Cause or Causes--The seed leaked after being inadvertently crushed 
    by a surgical staple used to secure the catheters during the implant 
    procedure.
    
    Actions Taken to Prevent Recurrence
    
        Licensee--For future procedures, the licensee plans to ensure that 
    the implanted seeds are located further down the catheter in order to 
    reduce the likelihood of seed damage from surgical staples. The 
    licensee also plans to examine each I-125 seed for leakage following 
    each explant procedure.
        NRC--NRC dispatched two inspectors on January 16, 1994, to monitor 
    the licensee's decontamination efforts and to obtain more details on 
    the misadministration. NRC also obtained the services of a medical 
    consultant to review the medical implications of the incident. A 
    followup NRC inspection (Letter from W.L. Axelson, Director, Division 
    of Radiation Safety and Safeguards, to Donald Harrison, M.D., Senior 
    Vice President and Provost for Health Affairs, University of 
    Cincinnati, forwarded Inspection Report No. 030-02764/94001, Docket No. 
    030-02764, License No. 34-06903-05, dated March 10, 1994) was conducted 
    from February 7 to 11, 1994. On March 16, 1994, NRC held a telephone 
    Enforcement Conference with the licensee to discuss the safety 
    inspections conducted in January and February 1994, at the University 
    of Cincinnati.
        A Notice of Violation was issued by NRC on March 25, 1994, which 
    imposed a fine of $5000 for a violation not associated with this 
    misadministration. In the Notice of Violation, NRC determined that the 
    inadvertent opening of the I-125 sealed source did not constitute a 
    violation of the University of Cincinnati's license.
    * * * * *
    
    94-6  Medical Brachytherapy Misadministration at Keesler Medical Center 
    at Keesler Air Force Base in Biloxi, Mississippi
    
        One of the AO reporting guidelines notes that a therapeutic 
    exposure to a part of the body scheduled to receive radiation such that 
    the actual dose received is greater than 1.5 5imes the prescribed dose 
    can be considered an abnormal occurrence.
        Date and Place--January 13, 1994; Keesler Medical Center, Keesler 
    Air Force Base; Biloxi, Mississippi.
        Nature and Probable Consequences--A patient was prescribed a lung 
    brachytherapy treatment delivered by an Omnitron 2000 high-dose-rate 
    (HDR) remote afterloader system. The prescribed tumor treatment plan 
    included 1000 centigray (cGy) (1000 rad) absorbed doses at 5 treatment 
    positions using a 144.3 gigabecquerel (3.9 curie) iridium-192 source 
    within a special needle. At the end of fifth and last treatment, the 
    source wire retracted 0.5 centimeter (cm) (0.2 inch) and stopped. 
    Alarms immediately alerted Keesler staff that the source remained 
    inside the patient's body. Licensee personnel followed emergency 
    procedures, entered the therapy room and removed the needle from the 
    patient. Once outside the patient's body, the radioactive source 
    retracted to the stored position.
        The licensee determined that the source remained stuck at 0.5 cm 
    (0.2 inches) above the fifth position for approximately 2\1/2\ minutes. 
    The treatment plan called for the delivery of 1000 centigray (cGy) 
    (1000 rad) at 1cm from each of the 5 treatment positions. As a result 
    of the additional 2\1/2\ minutes exposure, the last treatment position 
    received 1732 cGy (1732 rad) absorbed dose, or 73.2 percent over the 
    prescribed dose. The treatment plan also predicted an 800 cGy (800 rad) 
    absorbed dose at 0.5cm (0.2 inch) from each of the 5 treatment 
    positions. The point 0.5 cm (0.2 inch) above the last treatment 
    position, where the movement of the source stopped, received 
    approximately 1400 cGy (1400 rad), or 75 percent greater than the 
    absorbed dose stipulated in the prescribed treatment plan. The failure 
    of the source to retract resulted in a single overexposure, causing an 
    overall absorbed dose of 75 percent greater than that prescribed, for 
    all the tissue surrounding the position 0.5cm (0.2 inch) above the last 
    treatment site.
        The licensee reported that no adverse health effects to the patient 
    are expected. The patient was immediately notified of the 
    misadministration.
    
    Cause or Causes
    
        The patient had made a sudden move near the end of the treatment 
    causing the special needle to bend at the point where it extended 
    beyond the biopsy needle. The bend prevented the radioactive source 
    from retracting to the stored position, causing the misadministration.
    
    Actions Taken to Prevent Recurrence
    
        Licensee--The licensee immediately stopped the use of the HDR 
    device pending a complete check of the system by the manufacturer 
    (Letter from Omnitron International, Inc. to NRC Document control Desk, 
    forwarding a Report of HDR misadministration, Part 21- Reporting of 
    Defects and Noncompliance, Omnitron Report No. 102, dated January 19, 
    1994, Docket No. 030-26841, License No. 42-23539-01AF; and Letter from 
    Omnitron International, Inc. to John W. Lubinski, Mechanical Engineer, 
    Nuclear Material Safety and Safeguards, NRC Washington, D.C., 
    forwarding a report of Inspection of Source Wire, dated April 6, 1994, 
    Docket No. 030-26841, License No. 42-23539-01AF). The licensee also 
    evaluated the practice of extending special needles beyond biopsy 
    needles and the probability of patient movement causing damage, and 
    decided to discontinue this practice (Letter from Department of the 
    Army, HQ AFMOA/SGPR, Brooks AFB, TX to NRC Region IV, forwarding the 
    15-Day Report of Misadministration at Keesler AFB, MS, dated February 
    1, 1994, Docket 030-26841, License No. 42-23539-01AF; and Letter from 
    Department of the Army, HQ AFMOA/SGPR, Brooks AFB, TX to NRC Region IV, 
    responding to a NRC Confirmatory Action Letter (dated January 18, 
    1994), dated March 8, 1994, Docket 030-26841, License No. 42-23539-
    01AF).
        NRC--A special inspection was conducted from January 19 to 21, 
    1994, to review the circumstances surrounding the misadministration and 
    the licensee's Quality Management program. A representative of the U.S. 
    Food and Drug Administration (FDA) also participated in this 
    inspection. No violations of regulatory requirements were identified 
    during the inspection, but NRC initiated the following actions: (1) A 
    Confirmatory Action Letter (Letter from James L. Milhoan, Regional 
    Administrator, Region IV, to Department of the Army, USAF Radioisotope 
    Committee, HQ AFMOA/SGPR, Brooks AFB, TX, forwarding a Confirmatory 
    Action Letter, CAL No. 4-94-01, Docket No. 030-28641, License No. 42-
    23539-01AF, dated January 18, 1994) was issued to the licensee on 
    January 18, 1994, which prohibited the use of the HDR unit until 
    serviced by the manufacturer; (2) a medical consultant was contracted 
    to evaluate the clinical effects and to assess the events that led to 
    this misadministration; (3) the manufacturer was asked to analyze the 
    source wire involved in the misadministration for damage as a result of 
    the stresses experienced during this event; (4) Southwest Research 
    Institute was contracted to analyze the special needle for mechanical 
    failure; (5) a generic communication is being developed to notify other 
    HDR users of the results of the inspection and related research; and 
    (6) NRC is coordinating with FDA an evaluation of the generic 
    implications surrounding this event.
    * * * * *
    
    94-7  Medical Brachytherapy Misadministration at Alexandria Hospital in 
    Alexandria, Virginia
    
        One of the AO reporting guidelines notes that a therapeutic 
    exposure to a part of the body not scheduled to receive radiation can 
    be considered an abnormal occurrence.
        Date and Place--January 27, 1994; Alexandria Hospital; Alexandria, 
    Virginia.
        Nature and Probable Consequences--On January 27, 1994, a patient 
    was scheduled to receive a 500 centigray (cGy) (500 rad) brachytherapy 
    treatment to the trachea using a Nucletron high-dose-rate (HDR) remote 
    afterloader system. A single catheter was used for this endobronchial 
    treatment and the licensee performed a routine simulated treatment. 
    During this simulation, the oncologist established a 3 centimeter (cm) 
    (1.2 inch) tumor treatment site and added a 1 cm (0.4 inch) margin on 
    both ends of the tumor site.
        Normally, at this time the medial physicist and the dosimetrist 
    plot distances, measured in centimeters along the length of the 
    catheter shown in the simulation film, in order to program the HDR for 
    precise treatment at the prescribed treatment site. This step was not 
    performed and the procedure was initiated without the HDR being 
    properly programmed. The unprogrammed source was allowed to travel 
    beyond the treatment site into the left lung area where the catheter 
    ended. The treatment resulted in the prescribed 500 cGy (500 rad) 
    effective dose equivalent being delivered to the left lung instead of 
    the trachea target site. Prior to administering the dose, the treatment 
    plan and treatment console printout were reviewed by the dosimetrist, 
    the medical physicist, and the oncologist. All three individuals failed 
    to identify the failure to plot the treatment site. Immediately 
    following the treatment, the licensee's medical physicist realized that 
    the plotting and programming of the treatment site were not performed. 
    After discovery of the treatment error, the oncologist determined that 
    the patient should be treated again using the correct treatment 
    parameters.
        The licensee has advised NRC that no adverse effects to the patient 
    are anticipated as a result of this misadministration. The licensee has 
    informed the patient of the misadministration.
        Cause or Causes--The licensee's radiation therapy staff failed to 
    follow the licensee's normal protocol for treatment with the HDR remote 
    afterloader. The failure to administer the treatment as prescribed 
    resulted from performing the treatment planning and independent 
    verification in the vicinity of the HDR console, where there were a 
    number of distractions.
    
    Actions Taken to Prevent Recurrence
    
        Licensee--The licensee's corrective actions included immediate 
    retraining of all personnel involved in brachytherapy treatments and 
    the addition of a checklist for each step in the treatment process. The 
    licensee also added steps to its Quality Management program for HDR 
    brachytherapy. These steps now require the use of the treatment 
    planning computer with manual verification of the input parameter and 
    the use of the treatment parameter card generated by the planning 
    computer to program the HDR rather than programming the HDR treatment 
    parameters manually.
        NRC--NRC conducted a special inspection from February 2 to 4, 1994, 
    to review the circumstances associated with the misadministration, the 
    licensee's Quality Management program, and the licensee's immediate 
    corrective actions. In addition, on February 25, 1994, NRC employed a 
    medical consultant to provide an assessment of the potential clinical 
    effects of this misadministration and the events that led to it.
        The inspection report, medical consultant's assessment, and 
    enforcement actions for the misadministration are being completed.
    
        Dated at Rockville, MD this 15th day of August, 1994.
    
        For the Nuclear Regulatory Commission.
    John C. Hoyle,
    Acting Secretary of the Commission.
    [FR Doc. 94-20423 Filed 8-18-94; 8:45 am]
    BILLING CODE 7590-01-M