2020-18163. Notice of Availability of a Draft Environmental Impact Statement (EIS) and Notice of Public Workshops and Hearings for the Proposed LaGuardia Access Improvement Project at LaGuardia Airport (LGA), New York City, Queens County, New York
-
Start Preamble
AGENCY:
Federal Aviation Administration (FAA), Department of Transportation (DOT).
ACTION:
Notice of Availability of a Draft Environmental Impact Statement and Notice of Public Workshops and Hearings.
SUMMARY:
The FAA is issuing this notice under the provisions of the National Environmental Policy Act (NEPA) of 1969, as amended, to announce the availability of the Draft Environmental Impact Statement (EIS) for the proposed LaGuardia Airport (LGA) Access Improvement Project and its connected actions (the Proposed Action). The Proposed Action would provide direct access between LGA and the Metropolitan Transportation Authority (MTA) Long Island Rail Road (LIRR) Mets-Willets Point Station and the New York City Transit (NYCT) 7 Line Mets-Willets Point Station. FAA is the lead federal agency in the preparation of the EIS, with cooperating agencies including U.S. Army Corps of Engineers, U.S. Environmental Protection Agency, New York State Department of Environmental Conservation, New York State Department of Transportation, and New York State Office of Parks, Recreation and Historic Preservation. The Draft EIS was prepared to disclose the potential environmental impacts resulting from the Proposed Action, including real property transactions under the New York State Eminent Domain Procedures Law. This notice announces the beginning of public comment period to solicit public comments on the Draft EIS. FAA plans to hold two public meetings and three public hearings concerning the Proposed Action and information contained in the Draft EIS.
DATES:
The public comment period on the Draft EIS starts on August 21, 2020 and ends on October 5, 2020. All comments must be received by no later than 5:00 p.m. Eastern Daylight Time, Monday, October 5, 2020.
As part of the EIS public participation process, FAA will hold two public workshops via Zoom where information will be presented and interested members of the public can participate in a moderated question and answer session on the Proposed Action and information contained in the Draft EIS with the FAA and the EIS Team:
- September 22, 2020 from 4:30 p.m. to 6:30 p.m.
- September 23, 2020 from 11:00 a.m. to 1:00 p.m.
FAA will also hold three public hearings via Zoom where interested members of the public can provide and listen to oral comments concerning the Proposed Action and information contained in the Draft EIS:
- September 22, 2020 from 7:00 p.m. to 9:00 p.m.
- September 23, 2020 from 2:00 p.m. to 4:00 p.m.
- September 24, 2020 from 5:00 p.m. to 7:00 p.m.
All speakers who register to give oral comments will be given up to 3 minutes to allow everyone the opportunity to provide oral comments, if they choose to do so. Written comments will also be accepted, as specified below.
Due to the ongoing public health emergency associated with COVID-19 Start Printed Page 51143and FAA's responsibility to protect the health and safety of the community, all workshops and hearings will be virtual. Registration and instructions for the public workshops and hearings is available on the project website at https://www.lgaaccesseis.com/. Translation services, including sign language interpretation, can be made available during the public workshops and hearings, if requested 10 calendar days before the sessions, via the online registration process.
ADDRESSES:
Oral comments on the Draft EIS may be presented at the public hearings or by leaving a voicemail at (855) LGA-EIS9 or (855) 542-3479. Written comments on the Draft EIS may be submitted via the following methods:
- Online on the project website at https://www.lgaaccesseis.com/formal-comment
- Email to comments@lgaaccesseis.com
- U.S. Mail to Mr. Andrew Brooks, Environmental Program Manager, Eastern Regional Office, AEA-610, Federal Aviation Administration, 1 Aviation Plaza, Jamaica, NY 11434
Comments on the Draft EIS will help FAA arrive at the best possible informed decision about the proposal. If you choose to include your name, address and telephone number, email, or other personal identifying information in your comment, be advised that your entire comment—including your personal identifying information—may be made publicly available at any time. While you can ask us in your comment to withhold your personal identifying information, FAA cannot guarantee that we will be able to do so.
Start Further InfoFOR FURTHER INFORMATION CONTACT:
Mr. Andrew Brooks, Environmental Program Manager, Eastern Regional Office, AEA-610, Federal Aviation Administration, 1 Aviation Plaza, Jamaica, NY 11434. Telephone: 718-553-2511.
End Further Info End Preamble Start Supplemental InformationSUPPLEMENTARY INFORMATION:
This notice continues the EIS process announced in the Notice of Intent To Prepare an Environmental Impact Statement (EIS) and Initiate Section 106 Consultation for the Proposed LaGuardia Access Improvement Project at LaGuardia Airport (LGA), New York City, Queens County, New York, 84 FR 19151, May 3, 2019, and follows meetings associated with the EIS announced in the Notice of Public Information Sessions on Alternatives Analysis for the Proposed LaGuardia Airport Access Improvement Project at LaGuardia Airport (LGA), New York City, Queens County, New York, 84 FR 66438, December 4, 2019.
This document was prepared in response to a proposal presented by the Port Authority of New York and New Jersey (Port Authority). The Port Authority operates LGA under a lease agreement with the City of New York. FAA must decide whether to approve, pursuant to 49 U.S.C. 47106 and 47107 relating to the eligibility of the Proposed Action for federal funding under the Airport Improvement Program (AIP) and/or under 49 U.S.C. 40117, as implemented by 14 CFR 158.25, to impose and use passenger facility charge (PFC) revenue collected for the Proposed Action to assist with construction of potentially eligible development items shown on the Airport Layout Plan (ALP). FAA approval of the eligibility for federal funding under AIP or to impose and use PFCs is a Federal action that must comply with NEPA requirements. FAA, as lead federal agency, invited the U.S. Army Corps of Engineers, U.S. Environmental Protection Agency, New York State Department of Environmental Conservation, New York State Department of Transportation, and New York State Office of Parks, Recreation and Historic Preservation to participate as cooperating agencies, which they have accepted, as described under 40 CFR 1501.6(a)(1).
The Draft EIS presents the purpose and need for the Proposed Action, analysis of reasonable alternatives, discussion of impacts for each reasonable alternative, and support appendices. Pursuant to 40 CFR 1502.14(d), the No Action Alternative is also assessed in the Draft EIS as the baseline for comparison purposes. The Proposed Action includes:
- construction of an above ground fixed guideway automated people mover (APM) system approximately 2.3 miles in length that extends from the future LGA Central Hall Building to the Metropolitan Transportation Authority (MTA) Long Island Rail Road (LIRR) Mets-Willets Point Station and the New York City Transit (NYCT) 7 Line Mets-Willets Point Station;
- construction of two on-Airport APM stations (Central Hall APM Station and East APM Station) and one off-Airport APM station at Willets Point (Willets Point APM Station) that provides connections to the Mets-Willets Point LIRR and NYCT 7 Line stations;
- construction of passenger walkway systems to connect the APM stations to the passenger terminals, parking garages, and ground transportation facilities;
- construction of a multi-level APM operations, maintenance, and storage facility (OMSF) that includes up to 1,000 parking spaces (500 for airport employees, 250 for MTA employees, 50 for APM employees, and 200 for replacement Citi Field parking);
- construction of three traction power substations: One located at the on-Airport East Station, another at-grade west of the proposed Willets Point Station just south of Roosevelt Avenue, and the third at the OMSF to provide power to the APM guideway;
- construction of a 27kV main substation located adjacent to the OMSF structure on MTA property;
- construction of utilities infrastructure, both new and modified, as needed, to support the Proposed Action, including a permanent stormwater outfall into Flushing Creek and a temporary stormwater outfall into Flushing Creek; and
- acquisition of temporary and permanent easements.
The Proposed Action also includes various connected actions, including: Utility relocation and demolition of certain existing facilities; a temporary MTA bus storage/parking facility; relocation of up to 200 Citi Field parking spaces; demolition and replacement of the Passerelle Bridge; temporary walkway to maintain access between the transit stations and Flushing Meadows-Corona Park; modifications to the MTA LIRR Mets-Willets Point Station, including service changes to the LIRR Port Washington Line; and the relocation of a boat lift, finger piers and connected timber floating dock, Marina office and boatyard facility, boat storage and parking, and operations shed, part of the World's Fair Marina.
FAA provides the following notices:
- Pursuant to 36 CFR 800.8(c) that it is using the NEPA process to notify the public of FAA's finding that the proposed undertaking would adversely affect properties listed or eligible for listing on the National Register of Historic Places and is seeking public comment on the measures proposed to avoid, minimize, or mitigate such effects disclosed in the Draft EIS. A Draft Memorandum of Agreement to resolve adverse effects to historic properties is included in Appendix K.11 of the Draft EIS.
- Pursuant to Section 4(f) of the DOT Act, FAA has prepared a Draft Section 4(f) Evaluation (see Appendix I of the Draft EIS). The Proposed Action would have a significant impact on Section 4(f) resources and is seeking public comments on impacts and proposed mitigation disclosed in Chapter 3.8 of the Draft EIS.
- Pursuant to DOT Order 5610.2(a), DOT Actions to Address Environmental Justice in Minority Populations and Start Printed Page 51144Low-Income Populations, the Proposed Action would have a significant impact on minority environmental justice populations and is seeking public comments on impacts and proposed mitigation disclosed in Chapter 3.14 of the Draft EIS.
- Pursuant to Executive Order 11990, Protection of Wetlands, that the Proposed Action would temporarily affect less than 1 acre of jurisdictional wetlands in Flushing Creek and less than 1 acre of temporary and permanent impact in Flushing Bay. Impacts to these aquatic resources are disclosed in Chapter 3.16 of the Draft EIS.
- Pursuant to Executive Order 11988, Floodplain Management that the Proposed Action would not result in a significant encroachment on floodplains. Impacts to floodplains are disclosed in Chapter 3.16 of the Draft EIS.
FAA encourages all interested parties to provide comments concerning the scope and content of the Draft EIS. Comments should be as specific as possible and address the analysis of potential environmental impacts and the adequacy of the assessment of the Proposed Action or merits of its alternatives and the mitigation being considered. Reviewers should organize their participation so that it is meaningful and makes the agency aware of the viewers' interests and concerns using quotations and other specific references to the Draft EIS and related documents. This commenting procedure is intended to ensure that substantive comments and concerns are available to FAA in a timely manner so that FAA has an opportunity to address them. Matters that could have been raised with specificity during the comment period on the Draft EIS may not be considered if they are raised for the first time later in the decision process.
Following the public comment period, FAA will prepare a Final EIS and Record of Decision pursuant to 40 CFR 1503.4(c) [Council of Environmental Quality regulations] and FAA Orders 1050.1F and 5050.4B. FAA and the US Army Corps of Engineers will prepare a joint Record of Decision pursuant to Executive Order 13807.
Start SignatureIssued in Jamaica, New York, August 14, 2020.
Evelyn Martinez,
Manager, New York Airport District Office, Airports Division, Eastern Region.
[FR Doc. 2020-18163 Filed 8-18-20; 8:45 am]
BILLING CODE 4910-13-P
Document Information
- Published:
- 08/19/2020
- Department:
- Federal Aviation Administration
- Entry Type:
- Notice
- Action:
- Notice of Availability of a Draft Environmental Impact Statement and Notice of Public Workshops and Hearings.
- Document Number:
- 2020-18163
- Dates:
- The public comment period on the Draft EIS starts on August 21, 2020 and ends on October 5, 2020. All comments must be received by no later than 5:00 p.m. Eastern Daylight Time, Monday, October 5, 2020.
- Pages:
- 51142-51144 (3 pages)
- PDF File:
- 2020-18163.pdf
- Supporting Documents:
- » Standard Instrument Approach Procedures, and Takeoff Minimums and Obstacle Departure Procedures; Miscellaneous Amendments
- » Standard Instrument Approach Procedures, and Takeoff Minimums and Obstacle Departure Procedures; Miscellaneous Amendments
- » Agency Information Collection Activities; Proposals, Submissions, and Approvals: Air Traffic Slots Management
- » Noise Compatibility Program: Westfield-Barnes Regional Airport, Westfield, MA
- » Agency Information Collection Activities; Proposals, Submissions, and Approvals: Extended Operations of Multi-Engine Airplanes
- » Surplus Property Releases: Greenville SCTAC Airport, Greenville, SC
- » Airport Property Releases: Abilene Regional Airport, Abilene, TX
- » Meetings: Ninety Eighth RTCA SC-159 Navigation Equipment Using the Global Positioning System Plenary
- » Agency Information Collection Activities; Proposals, Submissions, and Approvals: National Flight Data Center Web Portal
- » Consensus Standards: Light-Sport Aircraft