    DEPARTMENT OF ENERGY
    18 CFR Part 284
    
    [Docket No. RM93-4-008; Order No. 563-E]
    
    
    Standards for Electronic Bulletin Boards Required Under Part 284 
    of the Commission's Regulations
    
    Issued July 27, 1995.
    
    AGENCY: Federal Energy Regulatory Commission, DOE.
    
    ACTION: Final rule; order modifying capacity release data sets.
    
    -----------------------------------------------------------------------
    
    SUMMARY: The Federal Energy Regulatory Commission (Commission) is 
    issuing an order making changes to its capacity release data sets and 
    Electronic Data Interchange implementation guide in response to a 
    filing by the Electronic Bulletin Board Working Group. The Commission's 
    order revises its ``Standardized Data Sets and Communication 
    Protocols,'' available at the Commission's Public Reference and Files 
    Maintenance Branch.
    
    EFFECTIVE DATE: Pipelines must implement the new requirements by 
    October 25, 1995.
    
    ADDRESSES: Federal Energy Regulatory Commission, 825 North Capitol 
    Street NE., Washington, DC 20426.
    
    FOR FURTHER INFORMATION CONTACT:
    Michael Goldenberg, Office of the General Counsel, Federal Energy 
    Regulatory Commission, 825 North Capitol Street NE., Washington, DC 
    20426, (202) 208-2294
    Marvin Rosenberg, Office of Economic Policy, Federal Energy Regulatory 
    Commission, 825 North Capitol Street NE., Washington, D.C. 20426, (202) 
    208-1283
    Brooks Carter, Federal Energy Regulatory Commission, 825 North Capitol 
    Street NE., Washington, D.C. 20426, (202) 501-8145.
    
    SUPPLEMENTARY INFORMATION: In addition to publishing the full text of 
    this document in the Federal Register, the Commission also provides all 
    interested persons an opportunity to inspect or copy the contents of 
    this document during normal business hours in Room 3104, 941 North 
    Capitol Street NE., Washington D.C. 20426.
        The Commission Issuance Posting System (CIPS), an electronic 
    bulletin board service, provides access to the texts of formal 
    documents issued by the 
    
    [[Page 39253]]
    Commission. CIPS is available at no charge to the user and may be 
    accessed using a personal computer with a modem by dialing (202) 208-
    1397. To access CIPS, set your communications software to use 19200, 
    14400, 12000, 9600, 7200, 4800, 2400, or 1200 bps, full duplex, no 
    parity, 8 data bits, and 1 stop bit. The full text of this document 
    will be available on CIPS in ASCII and WordPerfect 5.1 format. The 
    complete text on diskette in WordPerfect format may also be purchased 
    from the Commission's copy contractor, La Dorn Systems Corporation, 
    also located in Room 3104, 941 North Capitol Street NE., Washington 
    D.C. 20426.
    Order Modifying Capacity Release Data Sets
    
        Before Commissioners: Elizabeth Anne Moler, Chair; Vicky A. 
    Bailey, James J. Hoecker, William L. Massey, and Donald F. Santa, 
    Jr.
    
        On June 29, 1995, the Electronic Bulletin Board (EBB) Working Group 
    submitted a consensus proposal to modify the capacity release data sets 
    adopted by the Commission in Order No. 563.1 The filing also 
    contained proposed revisions to the Electronic Data Interchange (EDI) 
    implementation guide relating to these changes. The approved data sets 
    and implementation guide are included in a document entitled 
    ``Standardized Data Sets and Communication Protocols,'' available at 
    the Commission's Public Reference and Files Maintenance Branch.
    
        \1\ Standards For Electronic Bulletin Boards Required Under Part 
    284 of the Commission's Regulations, Order No. 563, 59 FR 516 (Jan. 
    5, 1994), III FERC Stats. & Regs. Preambles para. 30,988 (Dec. 23, 
    1993), order on reh'g, Order No. 563-A, 59 FR 23624 (May 6, 1994), 
    III FERC Stats. & Regs. Preambles para. 30,994 (May 2, 1994), reh'g 
    denied, Order No. 563-B, 68 FERC para. 61,002 (1994).
    ---------------------------------------------------------------------------
    
        The Working Group requests that the changes become effective 90 
    days after a Commission order to provide sufficient implementation 
    time. The Working Group, through a filing made on May 11, 1995, also 
    provided notification that, by consensus agreement, it intends to 
    transfer future responsibility for maintenance of the capacity release 
    data sets and for the PI GRIDTM Common Code Database to the Gas 
    Industry Standards Board.
        Pursuant to the process adopted by the Commission to make 
    modifications to the data sets,2 public notice of the June 29, 
    1995 filing was issued on July 3, 1995, with comments due by July 12, 
    1995.
    
        \2\ Order No. 563-A, III FERC Stats. & Regs. Preambles at 
    31,036-37.
    ---------------------------------------------------------------------------
    
        Natural Gas Clearinghouse (NGC), a member of the Working Group, 
    filed a comment stating that the field entitled discount indicator 
    needs to be clarified. The discount indicator is a mandatory ``yes/no'' 
    field where:
    
        ``Y'' signifies that the rates associated with the capacity 
    being released include rates discounted by transporter which could 
    result in additional charges to the bidder if other than the Gas 
    transaction points used to describe the capacity are utilized, and 
    ``N'' or blank, signifies that no discounts apply.
    
        NGC states that this field was accepted at its behest to reflect 
    the Commission's decision in ANR,3 under which a replacement 
    shipper may be assessed charges in excess of its bid if it uses 
    alternate receipt or delivery points.
    
        \3\ ANR Pipeline Company, 66 FERC para. 61,340, at 62,130-32 
    (1994).
    ---------------------------------------------------------------------------
    
        NGC contends that, after the Working Group filed the data sets, an 
    ambiguity became apparent. It is concerned that parties that were not a 
    part of the Working Group process may interpret this provision to mean 
    that the field would be coded as ``yes'' whenever a shipper is 
    releasing capacity on which it pays discounted rates. NGC maintains 
    that it and the Working Group's intent was that the field be coded 
    ``yes'' only when the replacement shipper would be exposed to a higher 
    rate for the use of alternate points. NGC requests clarification of 
    this point and also recommends revision to the description of the field 
    to better reflect this intent.4
    
        \4\ Specifically, NGC recommends the field be reworded to state:
        ``Y'' signifies that the rates associated with the capacity 
    being released include rates discounted by transporter which that 
    could result in additional charges to the bidder if other than the 
    Gas transaction points used to describe the capacity are utilized, 
    and ``N'' or blank, signifies that no discounts such additional 
    charges could apply.
        NGC states the revised definition should be included in both the 
    ``description of field'' and the ``data type and explanation'' 
    columns.
    ---------------------------------------------------------------------------
    
        The Commission accepts the data sets and EDI implementation guide, 
    and will grant the clarification and accept the proposed language 
    revision requested by NGC. This clarification will help ensure that the 
    discount indicator field is coded in a consistent manner so that 
    replacement shippers can rely on the information provided.
        In El Paso 5 and ANR,6 the Commission explained that when 
    a replacement shipper obtains capacity that the pipeline sold to the 
    releasing shipper at a discount rate, the replacement shipper may be 
    subject to additional charges for using alternate receipt or delivery 
    points. 7 The replacement shipper is subject to additional charges 
    only when the releasing shipper includes a specific condition in the 
    release obligating the replacement shipper to pay the additional 
    charges resulting from its use of alternate points. Absent an express 
    condition, the replacement shipper pays the rate established by its bid 
    and the releasing shipper is required to pay the differential between 
    the discount rate and the maximum rate.
    
        \5\ El Paso Natural Gas Company, 62 FERC para. 61,311, at 62,991 
    (1993).
        \6\ ANR Pipeline Company, 66 FERC para. 61,340, at 62,130-32 
    (1994).
        \7\ In general, when the pipeline has sold capacity at a 
    discount, the pipeline is entitled to collect the maximum rate when 
    shippers change to alternate points (unless the pipeline has agreed 
    by contract that the discounted rate applies to all points).
    ---------------------------------------------------------------------------
    
        In line with this policy, the Commission clarifies that the 
    discount indicator is to be coded ``yes'' only when the replacement 
    shipper could be subject to additional charges for changing points. 
    This clarification will ensure that replacement shippers receive 
    consistent and correct information about their potential exposure to 
    additional charges. The language revision suggested by NGC provides a 
    better reflection of this intent than the version proposed by the 
    Working Group and, therefore, will be adopted.
        Pipelines will be required to implement the new fields within 90 
    days of the date of this order. The ``Standardized Data Sets and 
    Communication Protocols'' will be modified to include the new fields 
    and will be made available at the Commission's Public Reference and 
    Files Maintenance Branch.
    
    The Commission Orders
    
        (A) The data sets and implementation guide are accepted with the 
    revision discussed in the body of this order.
        (B) Pipelines must implement the requirements of this order within 
    90 days of the date of the order.
    
        By the Commission.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 95-18957 Filed 8-1-95; 8:45 am]
    BILLING CODE 6717-01-P
    
    

Document Information

Published:
08/02/1995
Department:
Energy Department
Entry Type:
Rule
Action:
Final rule; order modifying capacity release data sets.
Document Number:
95-18957
Dates:
Pipelines must implement the new requirements by October 25, 1995.
Pages:
39252-39253 (2 pages)
Docket Numbers:
Docket No. RM93-4-008, Order No. 563-E
PDF File:
95-18957.pdf
CFR: (1)
18 CFR 284