96-21113. Florida Gas Transmission Company; Notice of Request Under Blanket Authorization  

  • [Federal Register Volume 61, Number 162 (Tuesday, August 20, 1996)]
    [Notices]
    [Pages 43048-43049]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-21113]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    Federal Energy Regulatory Commission
    [Docket No. CP96-702-000]
    
    
    Florida Gas Transmission Company; Notice of Request Under Blanket 
    Authorization
    
    August 14, 1996.
        Take notice that on August 9, 1996, Florida Gas Transmission 
    Company (FGT), 1400 Smith Street, P.O. Box 1188, Houston, Texas 77251-
    1188, filed in Docket No. CP96-702-000 a request pursuant to Sections 
    157.205 and 157.212 of the Commission's Regulations under the Natural 
    Gas Act (18 CFR 157.205, 157.212) for authorization to construct, own, 
    and operate a new delivery point in Indian River County, Florida for 
    City Gas Company of Florida (CGC) under FGT's blanket certificate 
    issued in Docket No. CP82-553-000 pursuant to Section 7 of the Natural 
    Gas Act, all as more fully set forth in the request that is on file 
    with the Commission and open to public inspection.
        FGT proposes to construct the delivery point adjacent to FGT's 20-
    inch and 26-inch mainlines and will include connection to the existing 
    taps, a rotary meter, approximately 100 feet of 4-inch line, and any 
    related appurtenant facilities necessary for FGT to deliver up to 144 
    MMBtu per hour to CGC.
        Any person or the Commission's staff may, within 45 days after 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Rules of Practice and Procedure (18 CFR 
    385.214) a motion to intervene or notice of intervention and pursuant 
    to Section 157.205 of the Regulations under the Natural Gas Act (18 CFR 
    157.205) a protest to the request. If no protest is filed within the 
    time allowed therefor, the proposed activity shall be deemed to be 
    authorized effective the day after the time allowed for filing a 
    protest. If a protest is filed and not withdrawn
    
    [[Page 43049]]
    
    within 30 days after the time allowed for filing a protest, the instant 
    request shall be treated as an application for authorization pursuant 
    to Section 7 of the Natural Gas Act.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 96-21113 Filed 8-19-96; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
08/20/1996
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
96-21113
Pages:
43048-43049 (2 pages)
Docket Numbers:
Docket No. CP96-702-000