98-22412. Use of PRA in Plant-Specific Reactor Regulatory Activities: Final Regulatory Guide and Standard Review Plan Section; Availability  

  • [Federal Register Volume 63, Number 161 (Thursday, August 20, 1998)]
    [Notices]
    [Pages 44659-44662]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-22412]
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    
    Use of PRA in Plant-Specific Reactor Regulatory Activities: Final 
    Regulatory Guide and Standard Review Plan Section; Availability
    
        The Nuclear Regulatory Commission has issued a new guide in its 
    Regulatory Guide Series, along with its conforming section of the 
    Standard Review Plan. Regulatory Guide 1.174, ``An Approach for Using 
    Probabilistic Risk Assessment in Risk-Informed Decisions on Plant-
    Specific Changes to the Licensing Basis,'' describes a method 
    acceptable to the NRC staff for assessing the nature and impact of 
    changes to a plant's licensing basis when the licensee chooses to 
    support these changes with risk information. The accompanying Standard 
    Review Plan Chapter 19, ``Use of Probabilistic Risk Assessment in 
    Plant-Specific, Risk-Informed Decisionmaking: General Guidance,'' 
    conforms to the guide to provide guidance to the NRC staff in reviewing 
    such changes.
        In June 1997, the Nuclear Regulatory Commission issued for public 
    comment a series of draft regulatory guides and Standard Review Plan 
    sections and a draft NUREG document addressing the use of PRA in 
    support of risk-informed regulatory activities. The preparation of 
    these documents followed from the Commission's Policy Statement of 
    August 16, 1995, on the use of PRA methods in nuclear regulatory 
    activities (60 FR 42622). The draft guidance documents were being 
    developed to provide acceptable approaches for using probabilistic risk 
    assessment (PRA) information in support of plant-specific changes to 
    plant licensing bases. The use of such PRA information and guidance by 
    power reactor licensees is voluntary, and alternative approaches may be 
    proposed.
        The Commission conducted a workshop on August 11-13, 1997, during 
    the comment period, to provide an overview of the draft documents, to 
    answer questions regarding their intended application, and to solicit 
    comments and suggestions. Comments received from the workshop have been 
    considered in preparing this final general regulatory guide (1.174) and 
    its accompanying Standard Review Plan (Chapter 19) for risk-informed 
    applications. Comments received from the workshop on application-
    specific guidance documents for technical specifications, inservice 
    testing, and graded quality assurance are currently being considered. 
    These guidance documents will be issued at a later date.
        Comments and suggestions in connection with items for inclusion in 
    guides currently being developed or improvements in all published 
    guides are encouraged at any time. Written comments may be submitted to 
    the Rules and Directives Branch, Division of Administrative Services, 
    Office of Administration, U.S. Nuclear Regulatory Commission, 
    Washington, DC 20555.
        Single copies of regulatory guides, both active and draft, and 
    draft NUREG documents may be obtained free of charge by writing the 
    Reproduction and Distribution Services Section, OCIO, USNRC, 
    Washington, DC 20555-0001; or by fax to (301) 415-2289; or by email to 
    [email protected] Active guides may also be purchased from the National 
    Technical Information Service on a standing order basis. Details on 
    this service may be obtained by writing NTIS, 5285 Port Royal Road, 
    Springfield, VA 22161. Copies of active and draft guides and the 
    Standard Review Plan are available for inspection or copying for a fee 
    from the NRC Public Document Room at 2120 L Street NW., Washington, DC; 
    the PDR's mailing address is Mail Stop LL-6, Washington, DC 20555; 
    telephone (202) 634-3273; fax (202) 634-3343. Regulatory guides are not 
    copyrighted, and Commission approval is not required to reproduce them.
    
    I. Background
    
        On August 16, 1995, the Commission published in the Federal 
    Register a final policy statement on the Use of Probabilistic Risk 
    Assessment Methods in Nuclear Regulatory Activities (60 FR 42622). The 
    policy statement included the following policy regarding NRC's expanded 
    use of PRA:
        1. The use of PRA technology should be increased in all regulatory 
    matters to the extent supported by the state-of-the-art in PRA methods 
    and data and in a manner that complements the NRC's deterministic 
    approach and supports the NRC's traditional defense-in-depth 
    philosophy.
        2. PRA and associated analyses (e.g., sensitivity studies, 
    uncertainty analyses, and importance measures) should be used in 
    regulatory matters, where practical within the bounds of the state-of-
    the-art, to reduce unnecessary conservatism associated with current 
    regulatory requirements, regulatory guides, license commitments, and 
    staff practices. Where appropriate, PRA should be used to support 
    proposals for additional regulatory requirements in accordance with 10 
    CFR 50.109 (Backfit Rule). Appropriate procedures for including PRA in 
    the process for changing regulatory requirements should be developed 
    and followed. It is, of course, understood that the intent of this 
    policy is that existing rules and regulations shall be complied with 
    unless these rules and regulations are revised.
        3. PRA evaluations in support of regulatory decisions should be as 
    realistic as practicable and appropriate supporting data should be 
    publicly available for review.
        4. The Commission's safety goals for nuclear power plants and 
    subsidiary numerical objectives are to be used with appropriate 
    consideration of uncertainties in making regulatory judgments on the 
    need for proposing and backfitting new generic requirements on nuclear 
    power plant licensees.
        It was the Commission's intent that implementation of this policy 
    statement would improve the regulatory process in three areas:
        1. Enhancement of safety decision making by the use of PRA 
    insights.
        2. More efficient use of agency resources, and
        3. Reduction in unnecessary burdens on licensees.
    
    [[Page 44660]]
    
        In parallel with the development of Commission policy on uses of 
    risk assessment methods, the NRC developed an agency-wide 
    implementation plan for applying PRA insights within the regulatory 
    process (SECY-95-079). This implementation plan included tasks to 
    develop a series of regulatory guides and standard review plans (SRPs) 
    on general guidance, inservice inspection (ISI), inservice testing 
    (IST), technical specifications (TS), and graded quality assurance 
    (GQA).
        The general regulatory guide, Regulatory Guide 1.174, and its 
    accompanying SRP section, Chapter 19, are intended to help implement 
    the Commission's August 1995 policy on the use of risk information in 
    the regulatory process. These two general documents are the first in 
    the series of risk-informed guidance documents. Together, they provide 
    the basic framework for an approach acceptable to the NRC staff for use 
    by power reactor licensees in preparing proposals for plant-specific 
    changes to their licensing bases using risk information. Alternative 
    approaches may be proposed. Application-specific guidance documents for 
    risk-informed technical specifications, inservice testing, and graded 
    quality assurance are currently being revised to address the public 
    comments that were received; these documents are scheduled to be issued 
    later in 1998. Guidance for inservice inspection is also being 
    developed on a later schedule.
    
    II. Public Comment Summary and Resolution
    
        The public comments on the draft regulatory guidance documents on 
    risk-informed applications were due by September 30, 1997. In addition 
    to comments received at the workshop, the NRC staff received 
    approximately 40 sets of written comments. Some of the more extensive 
    comments were provided by the Nuclear Energy Institute (NEI), in a 
    letter dated September 29, 1997, which provided comments on behalf of 
    the nuclear industry. In its letter, NEI commended the NRC staff for 
    its efforts in developing the draft documents, stating that the 
    industry recognized the significance of the drafts in articulating a 
    framework for the use of risk information in regulatory decisionmaking 
    and that the documents represent a milestone in the evolution of the 
    regulatory process. In addition, the NEI letter expressed concern 
    regarding four policy issues; NEI believes the resolution of these 
    issues is essential to the continued viability and the expansion of 
    risk-informed regulation. The issues cited by NEI were overall cost 
    benefit, use of numerical acceptance guidelines, treatment of 
    uncertainty, and PRA attributes and quality considerations. Each of 
    these areas highlighted by NEI will be addressed in the following 
    discussion of the principal issues.
        Comment letters were also received from the Electric Power Research 
    Institute (EPRI), the American Society of Mechanical Engineers (ASME), 
    the owners groups for the four reactor vendors (General Electric, 
    Westinghouse, Combustion Engineering, and Babcock and Wilcox), one 
    vendor (Westinghouse), 18 electric utilities, one national laboratory 
    (Oak Ridge), five technical organizations, five other private industry 
    organizations or individuals, and two anonymous commenters. The 
    following discussion addresses the resolution of the principal issues 
    raised by the commenters. A more complete discussion of the comments 
    received overall is given in the attachment to a memorandum from Mr. 
    Mark A. Cunningham (Chief, Probabilistic Risk Analysis Branch, Division 
    of Systems Technology, Office of Nuclear Regulatory Research) to Mr. M. 
    Wayne Hodges (Director, Division of Systems Technology, Office of 
    Nuclear Regulatory Research) dated January 7, 1998, which is available 
    in the NRC's Public Document Room. The discussion in the attachment 
    covers the resolution of the NRC's specific requests for comments 
    included in the Federal Register notice for the workshop (62 FR 34321), 
    other issues raised by the commenters, and the principal issues 
    discussed in this announcement.
    
    Principal Issues
    
    1. Use of 10-4 Per Reactor-Year Core Damage Frequency as an 
    Acceptance Guideline
    
        Issue: Comments were received indicating that the use of 
    10-4 per reactor-year core damage frequency 
    (10-4/RY CDF) as an acceptance guideline was overly 
    conservative, that the Commission's Safety Goal Policy quantitative 
    health objectives (QHOs) would be more appropriate for use as goals, 
    and that it was not clear how closely staff reviewers would hold 
    applications to this numerical criteria.
        Resolution: Revised Section 2.2.4, ``Acceptance Guidelines,'' of 
    Regulatory Guide 1.174 addresses the use of 10-4/RY CDF as a 
    guideline in evaluating the acceptability of risk-informed 
    applications. The use of 10-4/RY CDF as a subsidiary goal is 
    consistent with past Commission guidance. The guidelines for assessing 
    risk, contained in the regulatory guide and SRP, are based upon the 
    QHOs in the Commission's Safety Goal Policy and upon previous 
    Commission guidance related to implementation of the Safety Goal Policy 
    and regulatory analysis guidelines (Revision 2 of NUREG/BR-0058, 
    ``Regulatory Analysis Guidelines of the U.S. Nuclear Regulatory 
    Commission,'' USNRC, November 1995). Specifically, the guideline value 
    of 10-4/RY for CDF is based upon a June 15, 1990, memorandum 
    from the Commission to the NRC staff on implementation of the Safety 
    Goal Policy, which established a 10-5/RY CDF as a benchmark 
    objective for accident prevention. The guideline value on CDF 
    of 10-5/RY is based upon the guidance in the Commission's 
    regulatory analysis guidelines, which establish 10-5/RY 
    CDF as a cutoff below which the significance of safety issues 
    is not large enough to warrant backfit analysis, assuming a reasonable 
    accident mitigation capability.
        Accident mitigation capability is addressed via guidelines on large 
    early release frequency (LERF). The guideline value of 10-5/
    RY for LERF contained in Regulatory Guide 1.174 is based upon risk 
    analysis results presented in NUREG-1150 (``Severe Accident Risks: An 
    Assessment for Five U.S. Nuclear Power Plants,'' Vol. 3, USNRC, January 
    1991), which calculated offsite health risks for five nuclear power 
    plants and compared them to the Safety Goal QHOs. Analyses for all five 
    plants calculated health risks well below the QHOs. However, if the 
    results of this analysis were adjusted so that the offsite health risks 
    just met the early fatality QHO (the most limiting QHO), with allowance 
    for the unanalyzed modes of operation (shutdown), and in some cases 
    external events, a corresponding LERF value of 10-5/RY would 
    result for those plants whose calculated offsite health risks are 
    closest to the QHOs.
        Site-to-site variations in LERF were judged to be not a large 
    factor (this was also confirmed in a study reported by the Advisory 
    Committee for Reactor Safeguards in a September 19, 1997, letter to 
    Chairman Jackson), and thus a single value for all plants is used. The 
    guideline value of 10-6/RY for ``LERF is based upon the 
    regulatory analysis guidelines that, when used in conjunction with the 
    CDF guidelines discussed above, establish a cutoff below 
    which the significance of safety issue is not large enough to warrant 
    backfit analysis.
        Figures 3 and 4 of Section 2.2.4 in Regulatory Guide 1.174 
    illustrate acceptance guidelines for CDF and
    
    [[Page 44661]]
    
    LERF and indicate that for each of these metrics, three regions have 
    been identified for use in screening the acceptability of proposed 
    changes in licensing bases. Region III, shown in the figures and 
    discussed in the text of Regulatory Guide 1.174, has been identified as 
    representing a sufficiently low CDF or LERF increase that, in general, 
    program changes associated with this region may be permitted without a 
    detailed assessment of the baseline CDF/LERF. As discussed in 
    Regulatory Guide 1.174, if there are indications that the baseline CDF 
    or LERF is above the guideline values, additional evaluation would be 
    needed even though the calculated changes in CDF or LERF were small and 
    in Region III. In Section 2.2.5, ``Comparison of PRA Results with the 
    Acceptance Guidelines,'' it is stated that the acceptance guidelines 
    (lines separating the regions) are not to be interpreted in an overly 
    prescriptive manner and that they are intended to provide an 
    indication, in numerical terms, of what is considered acceptable. 
    Graduated shading has been added to the guideline figures to indicate 
    regions in which proposed changes will be subject to gradually more 
    intensive NRC technical and management review. Regarding the use of the 
    QHOs, it is stated that the use of the QHOs in lieu of LERF in support 
    of risk-informed applications is an acceptable approach provided that 
    appropriate consideration is given to the methods and assumptions used 
    in the analysis and in the treatment of uncertainties. Also, in Section 
    2.2.6, ``Integrated Decisionmaking,'' it is noted that Level 3 PRA 
    information can be submitted and will be considered in support of those 
    cases in which increased NRC management attention is needed during the 
    review (e.g., when the calculated CDF/LERF changes and baseline values 
    are close to the acceptance guidelines).
    
    2. Definition of Risk Neutral
    
        Issue: A number of comments were received indicating a need for a 
    definition of risk neutral applications, and indicating that increased 
    NRC management and technical review should not be required for risk 
    increases below some threshold.
        Resolution: See responses to Issues Number 1 and 3 addressing very 
    small increases in risk.
    
    3. Allowance for Very Small Increases in Risk
    
        Issue: Comments stated that facilities with CDFs greater than 
    10-4/RY should be allowed small risk increases and that the 
    level of effort and information required in submittals was excessive 
    for small risk increases.
        Resolution: Section 2.2.4, ``Acceptance Guidelines,'' addresses the 
    treatment of small increases in risk using the metrics of CDF and LERF. 
    As noted in the discussion for Issue Number 1, this section has been 
    revised and now includes a special category of application in which the 
    estimated level of CDF/LERF increase associated with the application is 
    sufficiently low that, in general, program changes associated with this 
    region may be permitted without a detailed assessment of the baseline 
    CDF/LERF. This category is displayed in Figures 3 and 4 of Section 
    2.2.4.
    
    4. Treatment of Uncertainties
    
        Issue: Comments stated that the inclusion of uncertainty could lead 
    to confusion regarding the decision criteria and that the use of PRA 
    inherently takes care of uncertainty.
        Resolution: Several approaches were reconsidered for the treatment 
    of uncertainties, and it was concluded that the approach described in 
    Draft Regulatory Guide DG-1061 appeared to be the most practical and 
    useful approach at this time, although the text needed to be clarified. 
    Uncertainty is addressed in Section 2.2.5, ``Comparison of PRA Results 
    with the Acceptance Guidelines,'' in Regulatory Guide 1.174. In this 
    section, it is noted that it is important, when interpreting the 
    results of a PRA, to develop an understanding of the impact of a 
    specific assumption or choice of model on the prediction. PRA only 
    inherently takes care of those uncertainties modeled in the analysis. 
    Others must be qualitatively or quantitatively addressed. The impact of 
    using alternative assumptions and models may be reasonably evaluated 
    using appropriate sensitivity studies. The major sources of uncertainty 
    should be understood, but it is not necessary, in all cases, to perform 
    elaborate uncertainty evaluations (e.g, propagation of uncertainty 
    distributions).
    
    5. Quality of PRA
    
        Issue: Numerous comments were received indicating concern that the 
    PRA standards included in Draft NUREG-1602, ``The Use of PRA in Risk-
    Informed Applications'' (USNRC, June 1997), were unnecessarily high for 
    many risk-informed applications. The comments also indicated that the 
    requirements for PRA quality were not clear and that graded levels of 
    PRA quality should be provided for different applications.
        Resolution: The issue of PRA quality is addressed in the revised 
    Section 2.2.3, ``Scope, Level of Detail, and Quality of the PRA,'' of 
    Regulatory Guide 1.174. In this section it is stated that PRA quality 
    should be commensurate with the application for which it is intended 
    and with the role that PRA results would play in the integrated 
    decision process. A PRA used in a risk-informed application should be 
    performed in a manner that is consistent with accepted practices, and 
    it should be commensurate with the scope and level of detail, which are 
    also discussed in Section 2.2.3 of Regulatory Guide 1.174. The NRC has 
    not developed its own formal standard nor endorsed an industry standard 
    for PRA quality, but it supports such a standard and expects that one 
    will be available in the future. Draft NUREG-1602 was cited in Draft 
    Regulatory Guide DG-1061 as a potential reference for PRA methods that 
    could be used to support regulatory decisionmaking. There were a number 
    of comments indicating that the ``PRA standard'' represented by Draft 
    NUREG-1602 was excessive for many risk-informed applications that did 
    not require sophisticated or state-of-the-art methods. While Draft 
    NUREG-1602 was not intended to be used universally as a PRA standard, 
    it is acknowledged that it would be more useful to have a standard that 
    addresses the differing needs for PRA scope and detail depending on the 
    application. Accordingly, Draft NUREG-1602 is no longer referenced in 
    Regulatory Guide 1.174, and a separate discussion on PRA quality has 
    been added, including the use of peer reviews or PRA cross comparisons. 
    PRA peer review activities such as those presently being done under 
    various industry PRA certification programs are examples. Peer review, 
    PRA certification, or cross comparison do not replace a staff review in 
    its entirety, and licensees need to justify why the PRA is adequate for 
    the proposed application. In the interim, until a consensus PRA 
    standard is available, the NRC staff will evaluate PRAs submitted in 
    support of specific applications using the guidelines given in Chapter 
    19 of the Standard Review Plan.
    
    6. Low Safety Significant Components Monitoring Needs
    
        Issue: Comments indicated that the draft guidance placed too much 
    importance on monitoring low safety significant components (LSSCs). The 
    comments also indicated that monitoring performed under the Maintenance 
    Rule should be acceptable for risk-informed programs.
    
    [[Page 44662]]
    
        Resolution: Section 2.3, ``Element 3: Define Implementation and 
    Monitoring Program,'' has been revised to clarify the need for 
    monitoring LSSCs. While details for monitoring LSSCs will be provided 
    in the application-specific guidance documents, the following principal 
    needs should be satisfied for all applications. Monitoring programs 
    should be proposed that are capable of adequately tracking the 
    performance of equipment that, when degraded, could alter the 
    conclusions that were key to supporting the acceptance of the program. 
    It follows that monitoring programs should be structured such that SSCs 
    are monitored commensurate with their safety significance. Monitoring 
    that is performed as a part of the Maintenance Rule implementation can 
    be used when the monitoring performed under the Maintenance Rule is 
    sufficient for the SSCs affected by the risk-informed application.
    
    7. Shutdown and Temporary Plant Condition
    
        Issue: Several commenters noted that the guidelines proposed did 
    not distinguish between power operation and shutdown and did not 
    address temporary plant conditions. Separate guidelines for these 
    conditions were suggested.
        Resolution: In response to these comments, Section 2.2.4 of 
    Regulatory Guide 1.174 has been expanded to address the shutdown 
    condition. Specific guidance for temporary plant conditions has not 
    been added, but will be considered in a future update of the guide.
    
    8. Documentation Needs
    
        Issue: Many commenters stated that the requirements in the drafts 
    for documentation were excessive and unmanageable, particularly for 
    proposals involving small changes in risk. It was also suggested that 
    certain items of documentation should not be required to be submitted 
    for the staff's initial review, provided that more complete 
    documentation was maintained at the utility for review as necessary.
        Resolution: In response to the comments received, Section 3 of 
    Regulatory Guide 1.174 has been reevaluated to determine whether all 
    items listed in the draft were necessary. As a result, a number of 
    documentation items, particularly with regard to the PRA, have been 
    removed in the final regulatory guide, and the SRP has been revised to 
    be consistent.
    
    9. Overall Cost Benefit
    
        Issue: This issue was highlighted by NEI in its comment letter and 
    was also included in a number of other comment letters. A concern was 
    expressed that the resources required by licensees to prepare proposals 
    and to subsequently implement NRC-approved risk-informed changes to the 
    CLB would be too high considering the benefit in terms of burden 
    reduction.
        Resolution: The question of how cost beneficial it would be for 
    utilities to prepare proposals for risk-informed changes to their 
    licensing bases and to implement such programs after review and 
    approval by the NRC will only be fully answered after the industry and 
    the NRC gain further experience in these types of programs. Certainly, 
    the pilot plant program proposals, which are currently being reviewed 
    for application to technical specifications, graded quality assurance, 
    and inservice testing and inspection, will provide useful insights into 
    the potential cost savings of these programs. While it is not the NRC's 
    responsibility to ensure that such risk-informed programs are cost 
    beneficial, it is believed that such programs can enhance safety by 
    better focusing utility and NRC resources on the most important safety 
    areas in reactors; this philosophy is consistent with the Commission's 
    Policy Statement on the use of PRA methods in nuclear regulatory 
    activities. During the preparation of this final regulatory guide and 
    standard review plan section, attention was paid to areas in which 
    needs for utility resources could be reduced, thus the cost beneficial 
    aspects of the risk-informed process were improved while still 
    maintaining an appropriate level of safety. Examples in Regulatory 
    Guide 1.174 are Section 2.2.3, ``Scope, Level of Detail, and Quality of 
    the PRA,'' which states that the level of detail required to support an 
    application can vary depending on the application, and not all 
    applications require an expensive, detailed PRA; Section 2.2.4, 
    ``Acceptance Guidelines,'' identifies a special category of risk-
    informed proposal as having a sufficiently low estimated risk increase 
    that, generally, the proposal would be considered without a detailed 
    assessment of baseline CDF/LERF (i.e., Region III of Figures 3 and 4 in 
    Regulatory Guide 1.174); and in Section 3, ``Documentation,'' where 
    some of the items that were identified in the draft guide and SRP as 
    being needed in program submittals have been removed since they were 
    not believed necessary.
    
    (5 U.S.C. 552(a))
    
        Dated at Rockville, MD, this 31st day of July 1998.
    
        For the Nuclear Regulatory Commission.
    Ashok C. Thadani,
    Director, Office of Nuclear Regulatory Research.
    [FR Doc. 98-22412 Filed 8-19-98; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
08/20/1998
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
98-22412
Pages:
44659-44662 (4 pages)
PDF File:
98-22412.pdf