98-22471. Red Hills Power Project  

  • [Federal Register Volume 63, Number 162 (Friday, August 21, 1998)]
    [Notices]
    [Pages 44944-44947]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-22471]
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    TENNESSEE VALLEY AUTHORITY
    
    
    Red Hills Power Project
    
    AGENCY: Tennessee Valley Authority.
    
    ACTION: Issuance of record of decision.
    
    -----------------------------------------------------------------------
    
    SUMMARY: This notice is provided in accordance with the Council on 
    Environmental Quality's regulations (40 CFR parts 1500 to 1508) and 
    TVA's procedures implementing the National Environmental Policy Act. 
    TVA has decided to adopt the preferred alternative identified in its 
    Final Environmental Impact Statement (EIS) on the Proposed Purchase of 
    Electricity Generated by the Red Hills Power Project (RHPP). The Final 
    EIS was made available to the public on July 3, 1998. A notice of 
    Availability of the Final EIS was published in the Federal Register on 
    July 10, 1998. Under the preferred alternative, TVA would commit to 
    purchase all of the electricity generated by the Red Hills Power 
    Project in Choctaw County, Mississippi. This would result in the 
    construction and operation of a 440-megawatt (MW) lignite-fueled 
    generation facility by Choctaw Generation Limited
    
    [[Page 44945]]
    
    Partnership and an adjacent surface lignite mine by Mississippi Lignite 
    Mining Company. TVA would also construct a transmission line connecting 
    the generation facility to the TVA power distribution system; this 
    transmission line would be constructed within Corridor A (the preferred 
    alternative corridor).
    
    FOR FURTHER INFORMATION CONTACT: Charles P. Nicholson, NEPA Specialist, 
    Environmental Management, Tennessee Valley Authority, 400 West Summit 
    Hill Drive, WT 8C, Knoxville, Tennessee 37902-1499; telephone (423) 
    632-3582 or e-mail cpnicholson@tva.gov.
    
    SUPPLEMENTARY INFORMATION: In December 1995, TVA issued its ``Energy 
    Vision 2020 Integrated Resource Plan and Final EIS.'' This document 
    projected demands for electricity in the TVA power service area through 
    the year 2020 and evaluated different ways of meeting these projected 
    increases. Under the load forecast adopted by TVA, the demand for 
    electricity was projected to exceed TVA's 1996 generating capacity of 
    28,000 MW by 6,250 MW in 2005. TVA plans to meet this demand through a 
    combination of supply-side options, customer service options, and 
    environmental control options. One of the supply-side options is 
    purchasing power from independent power producers. An independent power 
    producer, Tractebel Power, Inc., parent company of Choctaw Generation 
    Limited Partnership, and Phillips Coal Company, parent company (along 
    with The North American Coal Company) of Mississippi Lignite Mining 
    Company, joint venture partners in the RHPP, submitted a proposal to 
    TVA for the sale of the total electric power output from the RHPP.
        TVA provided public notice of its intent to prepare an 
    Environmental Impact Statement on its proposed purchase of power from 
    the RHPP on October 16, 1996. A public meeting on the proposal was held 
    on November 15, 1996. TVA released its draft EIS on February 13, 1998, 
    and held a public meeting to receive comments on the document on March 
    12, 1998. Comments were received from two federal and four state 
    agencies, two corporations, one university institute, seven 
    representatives of local governments or development corporations, and 
    seven individuals. After considering all comments, TVA revised the EIS 
    appropriately. The Final EIS was distributed to commenting agencies and 
    the public on July 2, 1998.
    
    Alternatives Considered
    
        Alternative methods of meeting TVA's future electrical generation 
    capacity requirements were evaluated in ``Energy Vision 2020.'' One of 
    the selected methods was the purchase of power from independent power 
    producers such as Tractebel. Tiering from ``Energy Vision 2020,'' the 
    RHPP Final EIS evaluates a No Action Alternative and an Action 
    Alternative.
        Under the No Action Alternative, TVA would not purchase the 
    electricity generated by the RHPP. TVA would also not construct a 
    transmission line connecting the generation facility to the TVA power 
    distribution system. The environmental impacts associated with TVA's 
    purchase of this electrical power would not occur, and TVA would 
    consider other options for meeting its future electrical demands. This 
    would not necessarily preclude eventual development of the generation 
    facility and/or mine, with the electricity sold to another purchaser.
        Under the Action Alternative, TVA would commit to purchasing the 
    electricity generated by the RHPP and would construct a transmission 
    line connecting the generation facility to the TVA power distribution 
    system. The generation facility would be built near the town of 
    Ackerman, Choctaw County, Mississippi. It would use two circulating 
    fluidized bed boilers with limestone injection, feeding a single steam 
    turbine with a net output of 440 MW of electricity. The facility would 
    consume about 3 million tons per year of lignite from the adjacent 
    lignite mine. To control sulfur emissions, the lignite would be burned 
    with about 235,000 tons per year of limestone from existing quarries in 
    central Mississippi. Other air emissions would be controlled by use of 
    the circulating fluidized bed boilers, combustion controls, and a 
    fabric filter baghouse. The facility would also be capable of cofiring 
    up to 245,000 tons per year of wood waste. Both limestone and wood 
    waste would be transported to the facility by truck. The generation 
    facility would produce about 677,000 tons per year of ash, which would 
    be trucked from the facility to an adjacent ash management unit.
        The generation facility would use a wet mechanical draft cooling 
    tower system. With the anticipated maximum reuse of cooling water, a 
    continuous source of about 6.33 million gallons per day of blowdown 
    makeup water would be required. This would be supplied by three nearby 
    wells pumping water from the Massive Sands of the Tuscaloosa Aquifer 
    System at depths of about 3,000 feet. Blowdown from the cooling tower 
    would be processed for removal of silica and other dissolved solids and 
    recycled to the cooling system. Reject water from the silica removal 
    process would be used to wet the ash to control dust. There would be no 
    discharges of wastewater from generation facility systems.
        The lignite mine would be located between the generation facility 
    and the Natchez Trace Parkway. Mine development would begin in late 
    1998, and consist of construction of access roads, mine support 
    facilities, a lignite handling facility, temporary stream diversions, a 
    stormwater runoff control pond, and sedimentation control ponds. 
    Overburden removal would begin in 1999 and actual lignite mining 
    operations would begin in 2000, concurrent with the completion of the 
    generation facility.
        Mining would begin near the generation facility, progress towards 
    the northwest, and disturb about 110 acres per year. Over the 30-year 
    life of the mine, about 4,700 acres would be disturbed, 1,400 acres by 
    mine development activities and 3,300 by lignite removal operations. 
    Lignite would be mined from six seams. Overburden would be removed by a 
    combination of electric or diesel-powered shovels, trucks, dozers, and 
    a dragline. Lignite would be loaded by front-end loaders and hydraulic 
    backhoes, and transported from the mine pit to the lignite handling 
    facility by high capacity dump trucks. The lignite would be crushed at 
    the lignite handling facility and transported by conveyor to the 
    generation facility.
        Reclamation would be concurrent with mining. Following removal of 
    the final lignite seam, the mine pit would be filled with overburden 
    spoil from the adjacent active mine pit. Spoil would be regraded to 
    approximate the original contours and drainage patterns. A topsoil 
    substitute consisting of selected, oxidized overburden materials would 
    then be spread over the graded mine spoil. Soil amendments would be 
    added as necessary. A cover crop would be planted or mulch spread over 
    the area being reclaimed. The plant species used in establishing the 
    permanent vegetative cover would vary with the postmining land use, 
    which would be dependent on premining land use and surface landowner 
    preferences. Most of the mined areas would likely be reclaimed as 
    commercial forest planted with loblolly pine.
        Two potential routes for the transmission line connecting the 
    generation facility to the TVA power distribution system were 
    evaluated, Corridor A and Corridor B. Corridor A
    
    [[Page 44946]]
    
    is 10.3 miles long. About 5.4 miles of Corridor A would parallel an 
    existing transmission line; the remainder would be on new right-of-way. 
    Corridor B is 10.9 miles long and all on new right-of-way. The cleared 
    right-of-way for each corridor would vary from 100 to 175 ft wide. The 
    transmission line would be a double-circuit, 161-kV line using steel 
    double pole structures with horizontal cross arms. TVA would also 
    expand the switchyard facilities at its Sturgis substation to 
    accommodate the new line.
        Choctaw County and the state of Mississippi plan to develop the Red 
    Hills EcoPlex industrial park near the generation facility. Targeted 
    industries would use steam and other generation facility byproducts. 
    Initial EcoPlex development would occupy about 500 acres and, when 
    fully occupied, about 1,000 acres would be developed. The Final EIS 
    describes cumulative impacts of EcoPlex development and operation, 
    which are not TVA actions.
    
    Decision
    
        TVA has decided to purchase the electricity generated by the RHPP, 
    and to construct the associated transmission line within Corridor A. 
    Purchasing power from the RHPP will help TVA meet the demand for 
    electricity in its service area and maintain reliable service to its 
    customers. TVA's actions were identified as both the Action Alternative 
    and the Preferred Alternative in the Final EIS.
    
    Environmentally Preferable Alternative
    
        Because the No Action Alternative would make the construction and 
    operation of the generation facility, lignite mine, and transmission 
    line less likely, it could be characterized as the environmentally 
    preferable alternative. It would not, however, accomplish TVA's goal of 
    securing additional electrical generation capacity, and would not 
    provide the significant local socioeconomic benefits forecast under the 
    Action Alternative. TVA would have to choose another source of 
    electrical generation capacity. Other potential sources, described in 
    ``Energy Vision 2020,'' would result in their own impacts which would 
    likely be equal to or less than those resulting from the Action 
    Alternative. However, none of these other generation alternatives would 
    produce the local socioeconomic benefits that would result from the 
    RHPP.
    
    Environmental Consequences and Commitments
    
        TVA, Choctaw Generation Limited Partnership, and Mississippi 
    Lignite Mining Company have adopted many mitigation measures to avoid 
    or minimize environmental harm. TVA has adopted the following 
    mitigation measures pertaining to its construction and operation of the 
    transmission line:
         All construction and maintenance activities will utilize 
    applicable Best Management Practices. Construction activities will also 
    adhere to the Right-of-Way Clearing Specifications and Environmental 
    Quality Protection Specifications for Transmission Line Construction 
    listed in Appendix B-2 of the Final EIS. These list requirements for 
    protecting sensitive areas, water and air quality, reducing noise, and 
    disposing of wastes.
         Wetlands will be avoided to the extent practicable. 
    Identified wetlands, streams, and drainage ways will not be modified so 
    as to alter their natural hydrological patterns during transmission 
    line clearing, construction, and maintenance. Hydric soils will not be 
    disturbed or modified in any way that would alter their hydrological 
    properties.
         Initial right-of-way clearing within forested wetlands 
    will be accomplished using accepted silvicultural practices for timber/
    vegetation harvesting within wetlands.
         Within streams, riparian zones, and wetlands, trees will 
    be above ground level and stumps will not be uprooted or removed.
         Transmission line maintenance using mechanical means in 
    areas surrounding or adjacent to identified wetlands will only be 
    conducted during seasonal dry periods, usually late summer or early 
    fall, and will be accomplished without the use of heavy equipment.
         Potential impacts to the two historic properties will be 
    minimized by maintaining existing trees between the churches and the 
    transmission line, and by placing transmission line poles in locations 
    where they will not be visible from the properties.
         Any herbicide applications would be by licensed personnel 
    and use EPA-registered herbicides.
        Many mitigation measures are required as conditions of permits 
    issued by the Mississippi Department of Environmental Quality (MDEQ) 
    and the U.S. Army Corps of Engineers. These include the following:
         Air emissions will comply with limits set in the PSD 
    permit to be issued by MDEQ.
         During all construction activities and mine operations, 
    open burning will only be conducted in accordance with applicable 
    regulations and Mississippi Forestry Commission guidelines. Fugitive 
    dust will also be controlled as necessary.
         Best Management Practices for silt control will be 
    utilized during all construction activities and during mine operations. 
    These practices include use of filter fabric fences, hay bale dikes, 
    sedimentation ponds and revegetation.
         Discharges to surface waters will comply with limits set 
    in NPDES permits to be issued by MDEQ. Stormwater will be managed in 
    accordance with Storm Water Pollution Prevention plans and accidental 
    spills will be managed in accordance with Spill Prevention Control and 
    Countermeasure plans.
         Well operations will comply with MDEQ water supply permit 
    limitations. Alternative water supplies will be provided to residents 
    whose supplies are disrupted by project operations.
         Streams impacted by mining will be restored to their 
    premining locations and approximate drainage patterns. Streambanks will 
    be revegetated and approximate premining drainage patterns will be 
    restored.
         Special handling techniques will be used for unoxidized 
    mine overburden containing acid-or toxic-forming materials. Anoxic 
    limestone drains or other techniques will be used to neutralize acidic 
    seeps if they appear following mine reclamation.
         Liquid fuels, oils, and other chemicals will be stored in 
    curbed or diked areas. Pollution Prevention Plans will be implemented.
         The generation facility and mine will register with EPA as 
    Conditionally Exempt Small Quantity Generators or Small Quantity 
    Generators. Hazardous wastes will be managed in accordance with 
    applicable RCRA regulations.
         The ash management facility will be built and operated in 
    accordance with conditions of the MDEQ Special/Industrial Solid Waste 
    Permit.
         Wetlands eliminated by mining activities will be mitigated 
    to a minimum mitigation ratio of 2:1 in compliance with U.S. Corps of 
    Engineers permit requirements. Wetland mitigation for the generation 
    facility will consist of creation of 8.8 acres of wetlands and purchase 
    and preservation of 19 acres of forested wetlands, which also meets 
    Corps requirements. All wetland mitigation for mining activities will 
    occur on the mine site or elsewhere in affected watersheds. Only native 
    plant species will be used in creating or restoring wetlands. All 
    wetland mitigation projects will include multi-year monitoring plans 
    and success determination criteria.
    
    [[Page 44947]]
    
         Backfilling and grading of mined areas will be 
    contemporaneous with mining.
         Mined areas will be reclaimed to have a soil productivity 
    at least as high as existed before mining.
         Native plant species, in combination with approved 
    introduced species, will be used in establishing permanent vegetative 
    cover during mine reclamation. The survival of permanent plantings will 
    be monitored for at least five years and additional plantings made as 
    necessary to meet reclamation requirements.
         Hardwood trees will be planted in buffer strips at least 
    50 feet wide on each side of reclaimed streams. Mast and fruit-bearing 
    trees and shrubs will be planted in clumps throughout the reclaimed 
    mine area.
         Except for the populations of swamp hickory and pin oak, 
    the populations of state-listed plants within the mine area will be 
    either avoided or transplanted to protected areas.
         The cactus community and spring-head seepage area located 
    near the northwest corner of the mine will either be avoided or 
    mitigated by transplantation or other means.
         Mining impacts to historic and archaeological resources 
    will be mitigated in accordance with the June, 1998 Memorandum of 
    Understanding among the Mississippi Lignite Mining Company, MDEQ, 
    Mississippi State Historic Preservation Officer, and the Advisory 
    Council on Historic Preservation. No mining will occur within 100 feet 
    of the Tullos Cemetery.
         Road closure and relocation plans will be approved by the 
    Choctaw County Board of Supervisors. All public roads will be rebuilt 
    to meet or exceed existing standards in their original locations or 
    more suitable, approved locations. Access by surface landowners to 
    lands not being mined will be maintained throughout mine operations.
        Following are additional mitigation measures which Choctaw 
    Generation Limited Partnership and Mississippi Lignite Mining Company 
    have committed to carrying out, as described in an agreement with TVA:
         No mining construction activities, such as construction of 
    sedimentation ponds, will occur within 500 feet of National Park 
    Service lands, and no lignite removal will occur within 2,000 feet of 
    the Natchez Trace Parkway centerline or within 1,000 feet of the 
    property line around the Little Mountain Overlook.
         Tree buffers will be maintained or planted around the edge 
    of the generation facility site.
         Lighting techniques designed to reduce impacts to the 
    darkness of the night sky will be used by the generation facility and 
    mine. Replacement ``dark sky'' lighting equipment will be provided by 
    the generation facility for existing commercial facilities at the 
    entrance to the Jeff Busby developed area.
         Choctaw Generation Limited Partnership and Mississippi 
    Lignite Mining Company will instruct their vendors that the vendors' 
    trucks are not to use the Natchez Trace Parkway when delivering 
    materials and supplies to the RHPP. Employees will be discouraged from 
    commuting on the Parkway.
         Project facilities and operations will be designed to 
    minimize noise levels. Mississippi Lignite Mining Company and the 
    National Park Service will cooperatively monitor noise at Little 
    Mountain Overlook using the L90 noise metric.
         Generation facility and mine employees will receive fire 
    and safety training. Mine employees will receive emergency medical 
    training. Emergency services will be coordinated with local providers.
    
        Dated: August 10, 1998.
    William J. Museler,
    Executive Vice President, Transmission/Power Supply Group.
    [FR Doc. 98-22471 Filed 8-20-98; 8:45 am]
    BILLING CODE 8120-08-P
    
    
    

Document Information

Published:
08/21/1998
Department:
Tennessee Valley Authority
Entry Type:
Notice
Action:
Issuance of record of decision.
Document Number:
98-22471
Pages:
44944-44947 (4 pages)
PDF File:
98-22471.pdf