98-22527. Illinois Power Co., Clinton Power Station, Unit 1; Notice of Partial Denial of Amendment to Facility Operating License and Opportunity for Hearing  

  • [Federal Register Volume 63, Number 162 (Friday, August 21, 1998)]
    [Notices]
    [Page 44939]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-22527]
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket No. 50-461]
    
    
    Illinois Power Co., Clinton Power Station, Unit 1; Notice of 
    Partial Denial of Amendment to Facility Operating License and 
    Opportunity for Hearing
    
        The U.S. Nuclear Regulatory Commission (the Commission) has 
    partially denied a request by Illinois Power Company (the licensee) to 
    amend Facility Operating License NPF-62 issued to the licensee for 
    operation of the Clinton Power Station, Unit 1, located in DeWitt 
    County, Illinois. Notice of Consideration of Issuance of the amendment 
    was published in the Federal Register on December 20, 1995 (60 FR 
    65681).
        The purpose of the licensee's amendment request was to revise 
    Technical Specification (TS) 5.2.2.e, ``Unit Staff,'' by revising the 
    requirements for controls on the working hours of unit staff who 
    perform safety related functions and by removing the requirement for 
    monthly review of individual overtime.
        The proposed changes were denied in part. The licensee's request to 
    remove the monthly review of individual overtime requirement was denied 
    because this removal would result in working hours controls that would 
    not be sufficient to assure that adequate shift coverage is maintained 
    without routine heavy use of overtime.
        The NRC staff has concluded that part of the licensee's request 
    cannot be granted. The licensee was notified of the Commission's 
    partial denial of the proposed change by letter dated August 13, 1998.
        By September 21, 1998, the licensee may demand a hearing with 
    respect to the partial denial described above. Any person whose 
    interest may be affected by this proceeding may file a written petition 
    for leave to intervene. A request for hearing or petition for leave to 
    intervene must be filed with the Secretary of the Commission, U.S. 
    Nuclear Regulatory Commission, Washington, DC 20555, Attention: 
    Rulemakings and Adjudications Staff, or may be delivered to the 
    Commission's Public Document Room, the Gelman Building, 2120 L Street, 
    NW., Washington, DC, by the above date.
        A copy of any petition should also be sent to the Office of the 
    General Counsel, U.S. Nuclear Regulatory Commission, Washington, DC 
    20555, and to Leah Manning Stetzner, Vice President, General Counsel, 
    and Corporate Secretary, 500 South 27th Street, Decatur, IL 62525, 
    attorney for the licensee.
        For further details with respect to this action, see (1) the 
    application for amendment dated October 27, 1995, and (2) the 
    Commission's letter to the licensee dated August 13, 1998.
        These documents are available for public inspection at the 
    Commission's Public Document Room and at the local public document room 
    located at the Vespasian Warner Public Library, 120 West Johnson 
    Street, Clinton, IL 61727.
    
        Dated at Rockville, MD, this 13th day of August 1998.
    
        For the Nuclear Regulatory Commission.
    Jon B. Hopkins,
    Senior Project Manager, Project Directorate III-3, Division of Reactor 
    Projects--III/IV, Office of Nuclear Reactor Regulation.
    [FR Doc. 98-22527 Filed 8-20-98; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
08/21/1998
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
98-22527
Pages:
44939-44939 (1 pages)
Docket Numbers:
Docket No. 50-461
PDF File:
98-22527.pdf