E9-20145. Port Dolphin Energy LLC, Port Dolphin Energy Liquefied Natural Gas Deepwater Port License Application; Final Environmental Impact Statement  

  • Start Preamble Start Printed Page 42358

    AGENCY:

    Maritime Administration, DOT.

    ACTION:

    Notice of availability; Correction.

    SUMMARY:

    The Coast Guard and the Maritime Administration (MARAD) announce the availability of material supplementing the Final Environmental Impact Statement (FEIS) for the Port Dolphin Energy Liquefied Natural Gas Deepwater Port license application. The supplementary material corrects errors in the FEIS.

    DATES:

    To allow sufficient time for public review and comment on this supplemental material we are extending the public comment period until September 11, 2009. All other scheduled dates remain unchanged. The Federal and State Agency and Governor comment periods also end September 11, 2009 and the MARAD Record of Decision is due by October 26, 2009.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Ray Martin, U.S. Coast Guard, telephone: 202-372-1449, e-mail: raymond.w.martin@uscg.mil or Chris Hanan, U.S. Maritime Administration, telephone: 202-366-1900, e-mail: Christopher.Hanan@dot.gov. If you have questions on viewing the docket, call Renee V. Wright, Program Manager, Docket Operations, telephone 202-493-0402.

    (Authority 49 CFR 1.66)

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    On July 13, 2009, the Coast Guard and MARAD notice of availability for the Port Dolphin Energy Liquefied Natural Gas Deepwater Port license application FEIS appeared in the Federal Register (74 FR 33509). Subsequently, we discovered several typographical errors and errors related to the analysis of sand resources in the Executive Summary and Sections 3, 4, and 6 of the FEIS. The most significant of these errors was a mathematical unit conversion error that resulted in the volumes of sand reported in the FEIS being nine times the actual estimated values.

    The corrections to the FEIS appear in this notice which, along with the FEIS itself, is available for viewing at the Federal Docket Management System Web site: http://www.regulations.gov under docket number USCG-2007-28532. You may also view these materials in person at Department of Transportation, Docket Management Facility, West Building, Ground Floor, Room W12-140, 1200 New Jersey Avenue, SE., Washington, DC 20590-0001 between 9 a.m. and 5 p.m., Monday through Friday, except Federal holidays. The Facility telephone number is 202-366-9329.

    The following corrections to the FEIS apply:

    Page ES-7, Table ES-1

    Delete: Table ES-1

    Replace with: the following table:

    Table ES-1—Comparison of Location and Pipeline Alternatives for Port Dolphin

    Project componentProposed site and pipeline alternativeSouthern site and pipeline alternativeOffshore interconnection with gulfstream pipeline
    Port Components
    Port C/O footprint22 acres30 acres (+36%)
    Pipeline Components
    Total pipeline length74.0 km (46 mi)80.4 km (50 mi) (+9%)28.8 km (18 mi) (−38%)
    Offshore length (from the piggable Y to the bulkhead)67.6 km (42 mi)74 km (46 mi) (+9.5%)N/A
    Offshore pipeline construction footprint (3,000-foot construction survey corridor)16,728 acres18,180 acres (+ 9%)6,545 acres (−39%)
    Offshore Gulfstream Pipeline crossingCrosses two times. HDD 1=1,335 feet, HDD 2=2,947 feetN/AN/A
    Permitted Sand Borrow Area IX0 cubic yards248,581 cubic yards0 cubic yards
    ROSS Areas5,374,463 cubic yards7,069,055 cubic yards0 cubic yards
    Offshore shipping channel crossingsnoneNonenone
    Nearshore Terra Ceia crossingnoneCrosses two times: 4.8 km (3.0 mi), and 1.1 km (0.7 mi)none
    Onshore pipeline length6.4 km (4 mi)6.4 km (4 mi)6.4 km (4 mi)
    Onshore pipeline C footprint (100-foot ROW)48.5 acres48.5 acres48.5 acres
    Onshore O footprint (30-foot ROW)14.5 acres14.5 acres14.5 acres
    Onshore wetland crossings C impacts10.71 acres10.71 acres10.71 acres
    Onshore wetland crossings O impacts1.19 acres1.19 acres1.19 acres
    Onshore Facility and Workspace Components
    Onshore landfall locationJust east of Gulfstream station at Port ManateeJust east of Gulfstream station at Port ManateeN/A
    Start Printed Page 42359
    Aboveground facilitiesInterconnection with GS and TECO—120 × 1,319 feet (3.4 acres) Valve station located on Port Manatee property—50 × 60 feet (0.07 acres)Interconnection with GS and TECO—120 × 1,319 feet (3.4 acres) Valve station located on Port Manatee property—50 × 60 feet (0.07 acres)Interconnection with GS offshore
    Onshore extra work spaces (located at the entrance and exit areas for HDD and boring activities)6 acres6 acres6 acres
    Staging areas, pipeyard, and contractor facilities would be located on Port Manatee (6 months)34 acres; includes a concrete batch plant, mattress facility and pipe lay-down areas34 acres; includes a concrete batch plant, mattress facility, and pipe lay-down areas34 acres; includes a concrete batch plant, mattress facility, and pipe lay-down areas
    Onshore access roadsNone (use existing roadways)None (use existing roadways)N/A
    Notes:
    C—Construction; O—Operation
    Length and acreage have been rounded to nearest whole number for NEPA planning purposes

    Page 3-77, Geological Resources

    Delete: The survey information provided by the Town of Longboat Key identified approximately 25 additional areas with potential as future sand borrow areas. These areas have not been fully investigated, and therefore cannot be confirmed to contain beach quality sand resources. These areas include a total of approximately 125,000 acres.

    Replace with: The survey information provided by the Town of Longboat Key identified approximately 25 additional areas with potential as future sand borrow areas. These areas have not been fully investigated, and therefore cannot be confirmed to contain beach quality sand resources. These areas include a total of approximately 128,000 acres.

    Page 4-157, Geological Resources

    Delete: The Proposed Pipeline Route passes through potential areas identified by Longboat Key, including the area identified in Federal waters as F-2, in their May 28, 2008, comments for a distance of 3.9 km (2.4 mi), and through the ROSS area for a distance of approximately 25.3 km (15.7 mi). These lengths were used to calculate the volumes in Table 4.4-1.

    Replace with: The Proposed Pipeline Route passes through potential areas identified by Longboat Key, including the area identified in Federal waters as F-2, in their May 29, 2008 and May 28, 2009 comments. Based on GIS mapping calculations, the Proposed pipeline would pass through potential areas identified by Longboat Key for a distance of 3.9 km (2.4 mi), and through the ROSS area for a distance of approximately 11.5 km (7.2 mi). These lengths were used to calculate the volumes in Table 4.4-1.

    Delete: Table 4.4-1

    Replace with: the following table:

    Table 4.4-1—Impacts on Potential Sand Borrow Areas

    Size of area (acres)Volume of area (cubic yards)Length of pipeline through impacted area (feet)Volume of impacted area (cubic yards)Percentage of potential volume impacted
    3.75-foot average depth9.5-foot average depth3.75-foot average depth9.5-foot average depth
    Borrow Area IX2641,597,2004,046,2400000.00
    High-Volume Sand Shoal4,50027,225,00068,970,0000000.00
    Longboat Key Potential Areas128,000774,400,0001,961,813,33312,858714,3231,809,6170.09
    ROSS Area538,0003,254,900,0008,245,746,66738,1872,121,4995,374,4630.07

    Delete: In 2006, Longboat Key used approximately 1,360,000 m3 (1,790,000 y3) of sand resources for their beach renourishment project. Assuming Longboat Key's next major beach renourishment project requires a similar amount of sand the proposed pipeline route would result in a loss of beach quality sand from the Longboat Key-identified potential sand resource areas equivalent to 2 to 5.5 beach renourishment projects. The loss of sand resulting from the proposed pipeline obstruction on ROSS-identified resources would result in the loss of 10.6 to 27.0 beach renourishment projects. No loss of beach quality sand within Borrow Area IX or the High Volume Sand Shoal is anticipated to occur.

    Replace with: In 2006, Longboat Key used approximately 1,360,000 m3 (1,790,000 y3) of sand resources for their beach renourishment project. Assuming Longboat Key's next major beach renourishment project requires a similar amount of sand, the proposed pipeline route would result in a loss of sand from the Longboat Key-identified potential sand resource areas equivalent to 0.4 to 1 beach renourishment projects. The loss of sand resulting from the proposed pipeline obstruction on ROSS-identified resources would result in the loss of 1.2 to 3 beach renourishment projects. No loss of beach-quality sand within Borrow Area IX or the High-Volume Sand Shoal is anticipated to occur.

    Page 4-160, Geological Resources

    Delete: Table 4.4-2

    Replace with: the following table:Start Printed Page 42360

    Table 4.4-2—Impacts on Potential Sand Borrow Areas along the Southern Site and Route Alternative

    Size of area (acres)Volume of area (cubic yards)Length of pipeline through impacted area (feet)Volume of impacted area (cubic yards)Percentage of potential volume impacted
    3.75-foot average depth9.5-foot average depth3.75-foot average depth9.5-foot average depth
    Borrow Area IX2641,597,2004,046,2401,76698,124248,5816.14
    High-Volume Sand Shoal4,50027,225,00068,970,00012,302683,4481,731,4022.51
    Longboat Key Potential Areas128,000774,400,0001,961,813,33324,0461,335,8893,384,2510.17
    ROSS Area538,0003,254,900,0008,245,746,66750,2272,790,4167,069,0550.09

    Page 4-161, Geological Resources

    Delete: Assuming Longboat Key's next major beach renourishment project requires a similar amount of sand the southern pipeline route would result in a loss of beach quality sand from Borrow Area IX equivalent to 0.5 to 1.2 renourishment projects. The loss of beach quality sand resulting from the proposed pipeline obstruction on ROSS-identified resources would result in sand loss equivalent to 14.0 to 35.5 beach renourishment projects.

    Replace with: Assuming Longboat Key's next major beach renourishment project requires a similar amount of sand, the southern pipeline route would result in a loss of beach-quality sand from Borrow Area IX equivalent to 0.05 to 0.14 beach renourishment projects. The loss of sand resulting from the proposed pipeline obstruction on ROSS-identified resources would result in sand loss equivalent to 1.6 to 3.9 beach renourishment projects.

    Page 4-170, Marine Areas and Land Use

    Delete: The total construction footprint for this alternative is estimated to be 9,323 acres, or 9 percent less than the proposed alternative. For impacts on sand resource areas, assuming a 400-m (1,312-foot) buffer centered on the pipeline, a total of 103 acres of the available area would be restricted for use in beach renourishment.

    Replace with: The total construction footprint for this alternative is estimated to be 9,323 acres, or 9 percent more than the proposed alternative. For impacts on sand resource areas see Table 4.4-2.

    Page 4-215, Socioeconomic Resources and Environmental Justice

    Delete: The sand resource locations and quantities of sand that would be inaccessible after construction of the pipeline are minimal and alternative resources exist nearby (see Section 4.1.1).

    Replace with: The sand resource locations and quantities of sand that would be inaccessible after construction of the pipeline are minimal and alternative resources exist nearby (see Figure 2.1-18).

    Page 4-243, BMPs, Mitigation and Minimization Measures, and Monitoring

    Delete: The Maritime Administration agrees that mitigation and monitoring of egg and fish mortality should be required to demonstrate impacts consistent with those analyzed in the EIS. Further details of this effort, including the duration of monitoring, would be developed in coordination with NOAA and USEPA as part of a detailed monitoring and mitigation plan being developed by the Maritime Administration. Onsite sampling for ichthyoplankton, lobster, and shrimp densities should include three years of data prior to the start of operations. If a license is issued, Port Dolphin Energy LLC would be required to conduct site-specific, year-round surveying to collect data on existing fish and invertebrate ichthyoplankton populations. Data collection shall begin as soon as the license is issued, and continue for a minimum of 3 years. Furthermore, one year of data collection must be completed prior to the start of operations, one of which must be completed prior to the start of operations.

    Replace with: The Maritime Administration agrees that mitigation and monitoring of egg and fish mortality should be required to demonstrate impacts consistent with those analyzed in the EIS. Further details of this effort would be developed in coordination with NOAA and USEPA as part of a detailed monitoring and mitigation plan being developed by the Maritime Administration. If a license is issued, Port Dolphin Energy LLC would be required to conduct site-specific, year-round surveying to collect data on existing fish and invertebrate ichthyoplankton populations. Data collection shall begin as soon as the license is issued, and continue for a minimum of three years. Furthermore, one year of data collection must be completed prior to the start of operations.

    Page 6-31, Geological Resources

    Delete: The proposed pipeline would pass through two potential sand sources identified by the Town of Longboat Key

    for a distance of approximately 2.26 km (1.4 mi). In addition, the proposed pipeline would pass through approximately 11.64 km (7.23 mi) of ROSS-identified potential sand source area. Based on analysis conducted in Sections 3.4.3 and 4.4.1, the proposed pipeline route including the 200-foot buffer on each side of the pipeline would restrict approximately 383 acres (155 hectares) for use in beach nourishment. This area comprises 0.06 percent of the 615,464 acres of the Long Boat Key, ROSS, High Volume Sand Shoal, and Borrow Area IX mapped potential sand resource areas.

    Replace with: The Proposed Pipeline Route passes through potential areas identified by Longboat Key, including the area identified in Federal waters as F-2, in their May 29, 2008 and May 28, 2009 comments. Based on GIS mapping calculations, the Proposed pipeline would pass through potential areas identified by Longboat Key for a distance of 3.9 km (2.4 mi), and through the ROSS area for a distance of approximately 11.5 km (7.2 mi). These lengths were used to calculate the volumes in Table 4.4-1.

    Start Signature

    Dated: August 18, 2009.

    By Order of the Maritime Administrator.

    Murray A. Bloom,

    Acting Secretary, Maritime Administration.

    End Signature End Supplemental Information

    [FR Doc. E9-20145 Filed 8-20-09; 8:45 am]

    BILLING CODE 4910-81-P

Document Information

Comments Received:
0 Comments
Published:
08/21/2009
Department:
Maritime Administration
Entry Type:
Notice
Action:
Notice of availability; Correction.
Document Number:
E9-20145
Dates:
To allow sufficient time for public review and comment on this supplemental material we are extending the public comment period until September 11, 2009. All other scheduled dates remain unchanged. The Federal and State Agency and Governor comment periods also end September 11, 2009 and the MARAD Record of Decision is due by October 26, 2009.
Pages:
42358-42360 (3 pages)
Docket Numbers:
USCG-2007-28532
PDF File:
e9-20145.pdf
Supporting Documents:
» Memorandum Of Agreement Between The State Of Florida, Department Of Environmental Protection And Fish And Wildlife Conservation Commission, And Port Dolphin Energy, LLC
» Port Dolphin Final Environmental Impact Statement (FEIS), Volume III, Appendices E - K, 11 of 11
» Port Dolphin Final Environmental Impact Statement (FEIS), Volume III, Appendices A - D, 10 of 11
» Port Dolphin Final Environmental Impact Statement (FEIS), Volume II, Appendix B - Part 6, 9 of 11
» Port Dolphin Final Environmental Impact Statement (FEIS), Volume II, Appendix B - Part 5, 8 of 11
» Port Dolphin Final Environmental Impact Statement (FEIS), Volume II, Appendix B - Part 4, 7 of 11
» Port Dolphin Final Environmental Impact Statement (FEIS), Volume II, Appendix B - Part 3, 6 of 11
» Port Dolphin Final Environmental Impact Statement (FEIS), Volume II, Appendix B - Part 2, 5 of 11
» Port Dolphin Final Environmental Impact Statement (FEIS), Volume II, Appendix B - Part 1, 4 of 11
» Port Dolphin Final Environmental Impact Statement (FEIS), Volume II, Appendix A - Part 2, 3 of 11