2014-19861. ANR Pipeline Company; Notice of Intent To Prepare an Environmental Assessment for the Proposed Sulphur Springs Compression Project and Request for Comments on Environmental Issues  

  • Start Preamble August 15, 2014.

    The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the Sulphur Springs Compression Project involving construction and operation of facilities by ANR Pipeline Company (ANR) in Henry County, Indiana. The Commission will use this EA in its decision-making process to determine whether the project is in the public convenience and necessity.

    This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies on the project. Your input will help the Commission staff determine what issues they need to evaluate in the EA. Please note that the scoping period will close on September 15, 2014.

    This notice is being sent to the Commission's current environmental mailing list for this project. State and local government representatives should notify their constituents of this proposed project and encourage them to comment on their areas of concern.

    ANR provided landowners with a fact sheet prepared by the FERC entitled “An Interstate Natural Gas Facility On My Land? What Do I Need To Know?” This fact sheet addresses a number of typically-asked questions, including the use of eminent domain and how to participate in the Commission's proceedings. It is also available for viewing on the FERC Web site (www.ferc.gov).

    Summary of the Proposed Project

    ANR proposes to construct and operate one new compressor unit and appurtenant facilities at its existing Sulphur Springs Compressor Station in Henry County, Indiana. The Sulphur Springs Compression Project would provide about 133.6 million standard cubic feet of natural gas per day to ANR's wholly owned portion of the Lebanon Lateral which connects the Glen Karn meter facilities in Darke County, Ohio to the Sulphur Springs Compressor Station.Start Printed Page 49509

    According to ANR, its project would increase reverse flow capability on its system and provide greater reliability, flexibility, and security to existing shippers.

    The Sulphur Springs Compression Project consists of the following facilities:

    • An approximately 10,915 horsepower Solar Taurus 70 turbine with C65 compressor;
    • exhaust silencer, air inlet filtration, and lube oil cooling equipment;
    • two high pressure gas coolers;
    • high-pressure gas filter/separator;
    • associated piping, valves, fittings, regulators, cables, conduits, overhead cable trays, cathodic protection devices, parking areas, and access road;
    • compressor building to house the new turbine;
    • control building;
    • natural gas-fired boiler; and
    • aboveground storage tanks.

    The general location of the project facilities is shown in appendix 1.[1]

    Land Requirements for Construction

    Construction of the proposed aboveground facilities would disturb about 24.3 acres of open and industrial/commercial land owned by ANR. Of this total, approximately 1.1 acres would be permanently impacted to accommodate the new facilities. Remaining disturbed areas would be revegetated or otherwise returned to pre-existing conditions.

    The EA Process

    The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from an action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires us [2] to discover and address concerns the public may have about proposals. This process is referred to as “scoping.” The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this notice, the Commission requests public comments on the scope of the issues to address in the EA. We will consider all filed comments during the preparation of the EA.

    In the EA we will discuss impacts that could occur as a result of the construction and operation of the proposed project under these general headings:

    • Geology and soils;
    • land use;
    • water use and quality;
    • vegetation and wildlife;
    • air quality and noise;
    • public safety; and
    • cumulative impacts.

    We will also evaluate reasonable alternatives to the proposed project or portions of the project, and make recommendations on how to lessen or avoid impacts on the various resource areas.

    The EA will present our independent analysis of the issues. The EA will be available in the public record through eLibrary. Depending on the comments received during the scoping process, we may also publish and distribute the EA to the public for an allotted comment period. We will consider all comments on the EA before making our recommendations to the Commission. To ensure we have the opportunity to consider and address your comments, please carefully follow the instructions in the Public Participation section beginning on page 4.

    With this notice, we are asking agencies with jurisdiction by law and/or special expertise with respect to the environmental issues of this project to formally cooperate with us in the preparation of the EA.[3] Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice.

    Public Participation

    You can make a difference by providing us with your specific comments or concerns about the project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. The more specific your comments, the more useful they will be. To ensure that your comments are timely and properly recorded, please send your comments so that the Commission receives them in Washington, DC on or before September 15, 2014.

    For your convenience, there are three methods which you can use to submit your comments to the Commission. In all instances please reference the project docket number (CP14-514-000) with your submission. The Commission encourages electronic filing of comments and has expert staff available to assist you at (202) 502-8258 or efiling@ferc.gov.

    (1) You can file your comments electronically using the eComment feature on the Commission's Web site (www.ferc.gov) under the link to Documents and Filings. This is an easy method for interested persons to submit brief, text-only comments on a project;

    (2) You can file your comments electronically using the eFiling feature on the Commission's Web site (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on “eRegister.” You must select the type of filing you are making. If you are filing a comment on a particular project, please select “Comment on a Filing”; or

    (3) You can file a paper copy of your comments by mailing them to the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 20426.

    Environmental Mailing List

    The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission's regulations) who own homes within certain distances of aboveground facilities and anyone who submits comments on the project. We will update the environmental mailing list as the analysis proceeds to ensure that we send the information related to this environmental review to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project.

    If we publish and distribute the EA, copies will be sent to the environmental mailing list for public review and comment. If you would prefer to receive a paper copy of the document instead of the CD version or would like to remove your name from the mailing list, please return the attached Information Request (appendix 2).

    Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want to become an “intervenor” which is an official party to the Commission's Start Printed Page 49510proceeding. Intervenors play a more formal role in the process and are able to file briefs, appear at hearings, and be heard by the courts if they choose to appeal the Commission's final ruling. An intervenor formally participates in the proceeding by filing a request to intervene. Instructions for becoming an intervenor are in the User's Guide under the “e-filing” link on the Commission's Web site.

    Additional Information

    Additional information about the project is available from the Commission's Office of External Affairs, at (866) 208-FERC, or on the FERC Web site at www.ferc.gov using the “eLibrary” link. Click on the eLibrary link, click on “General Search” and enter the docket number, excluding the last three digits in the Docket Number field (i.e., CP14-514). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, contact (202) 502-8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings.

    In addition, the Commission now offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/​docs-filing/​esubscription.asp.

    Finally, public meetings or site visits will be posted on the Commission's calendar located at www.ferc.gov/​EventCalendar/​EventsList.aspx along with other related information.

    Start Signature

    Kimberly D. Bose,

    Secretary.

    End Signature End Preamble

    Footnotes

    1.  The appendices referenced in this notice will not appear in the Federal Register. Copies of appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called “eLibrary” or from the Commission's Public Reference Room, 888 First Street NE., Washington, DC 20426, or call (202) 502-8371. For instructions on connecting to eLibrary, refer to the last page of this notice.

    Back to Citation

    2.  “We,” “us,” and “our” refer to the environmental staff of the Commission's Office of Energy Projects.

    Back to Citation

    3.  The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, Part 1501.6.

    Back to Citation

    [FR Doc. 2014-19861 Filed 8-20-14; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Published:
08/21/2014
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2014-19861
Pages:
49508-49510 (3 pages)
Docket Numbers:
Docket No. CP14-514-000
EOCitation:
of 2014-08-15
PDF File: