94-20486. Transcontinental Gas Pipe Line Corp.; Notice of Application  

  • [Federal Register Volume 59, Number 161 (Monday, August 22, 1994)]
    [Unknown Section]
    [Page 0]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 94-20486]
    
    
    [[Page Unknown]]
    
    [Federal Register: August 22, 1994]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Docket No. CP94-714-000]
    
     
    
    Transcontinental Gas Pipe Line Corp.; Notice of Application
    
    August 16, 1994.
        Take notice that on August 15, 1994, Transcontinental Gas Pipe Line 
    Corporation (Transco), P.O. Box 1396, Houston, Texas 77251-1396, filed 
    in Docket No. CP94-714-000 an application pursuant to Sections 7(c) and 
    7(b) of the Natural Gas Act for (1) a certificate of public convenience 
    and necessity authorizing certain river crossings, and (2) an order 
    permitting and approving the abandonment of existing facilities at the 
    same location, all as more fully set forth in the application which is 
    on file with the Commission and open to public inspection.
        Transco states that it has three pipelines which cross the Amite 
    River in Louisiana: (1) 30-inch diameter Main Line A, (2) 36-inch 
    diameter Main Line B and (3) 36-inch Maine Line C. Transco states that 
    all gas produced onshore and offshore Texas and Louisiana which flows 
    through Transco's system to Transco's markets in the deep south, 
    atlantic seaboard and eastern markets flows through the Amite River 
    crossing (with the exception of the gas attached to Transco's mainline 
    by way of the Southeast Louisiana Gathering System, which interconnects 
    with Transco's mainline at Compressor Station No. 65, located 
    approximately 11 miles north of the Amite River).
        Transco states that because of river scouring, bank washing and 
    channel meander/realignment, Main Line A is exposed. It is indicated 
    that Line A has been taken out of service because Transco is concerned 
    that a significant flood event could occur and rupture the line. It is 
    also indicated that Main Lines B and C are not yet exposed, but Transco 
    is concerned that they would become exposed because the river is 
    realigning in a southward direction.
        Transco states that it cannot perform these replacements pursuant 
    to Section 2.55(b) of the Commission's Regulations because of the 
    Commission's recent clarification of Section 2.55(b) in the order 
    issued on May 12, 1994, in Arkla Energy Resources Company, Docket No. 
    CP91-2069-000 (67 FERC 61,173), involving the issue of replacements 
    outside of existing right-of-way. Transco states that it is imperative 
    that it complete the new crossings in time to provide service during 
    the upcoming winter heating season.
        Transco states that it proposes to install approximately 2,700 feet 
    of new 36-inch diameter Main Line B by horizontal directional drilling 
    under the Amite River, at the location of its existing pipeline 
    crossing of the Amite River. Transco indicates that directionally 
    drilled pipeline are more secure than the older pipelines which were 
    installed by way of trenching the river bed. It is stated that 
    approximately 225 feet of 36-inch diameter pipe would be conventionally 
    installed from the entrance of the bore on the east side of the river 
    and tied in to existing Main Lines A and B by means of a new manifold. 
    It is also indicated that approximately 225 feet of 36-inch diameter 
    pipe would be conventionally installed from the exit of the bore on the 
    west bank of the river and tied into existing Main Lines A and B by 
    means of a new manifold.
        Transco states that it also proposes to install approximately 2,700 
    feet of new 36-inch diameter Main Line C by horizontal directional 
    drilling under the Amite River. It is indicated that approximately 225 
    feet of 36-inch diameter pipe will be conventionally installed from the 
    entrance of the bore on the east side of the river and tied into 
    existing Main Line Lines A, B, and C by means of the manifold mentioned 
    above. It is also stated that approximately 225 feet of 36-inch 
    diameter pipe would be conventionally installed from the exit of the 
    bore on the west side of the river and tied into Main Lines A, B, and C 
    by means of the manifold mentioned above.
        Transco states that proposed replacements would restore the long-
    term integrity of Transco's transmission system at the Amite River 
    crossings. It is stated that system capacity across the Amite River 
    after installation of the two new river crossings would be 2,361,000 
    Mcf per day compared with a current capacity of 2,369,000 Mcf per day. 
    Transco states that the three existing pipelines would be retired and 
    removed. Transco estimates the cost of installing both new lines at 
    approximately $6,000,000, to be financed initially through short-term 
    loans and funds on hand, with permanent financing to be undertaken at a 
    later date. Transco estimates the cost of the removal work at $280,000.
        Transco states that issuance of a certificate and construction 
    clearance by September 15, 1994, is justified for three reasons: (1) 
    The need for security of gas service during the upcoming winter heating 
    season, (2) historically, during the months of August and September, it 
    is expected that the Amite River floodplain would be dryer than at any 
    time of the year, and thus provide the most favorable conditions for 
    the contractor's equipment, and (3) the de minimis impact on the 
    environment of the crossing project.
        Any person desiring to be heard or to make any protest with 
    reference to said application should on or before August 31, 1994, file 
    with the Federal Energy Regulatory Commission Washington, DC 20426, a 
    motion to intervene or a protest in accordance with the requirements of 
    the Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
    385.211) and the Regulations under the Natural Gas Act (18 CFR 157.10). 
    All protests filed with the Commission will be considered by it in 
    determining the appropriate action to be taken but will not serve to 
    make the protestants parties to the proceeding. Any person wishing to 
    become a party to a proceeding or to participate as a party in any 
    hearing therein must file a motion to intervene in accordance with the 
    Commission's Rules.
        Take further notice that, pursuant to the authority contained in 
    and subject to the jurisdiction conferred upon the Federal Energy 
    Regulatory Commission by Sections 7 and 15 of the Natural Gas Act and 
    the Commission's Rules of Practice and Procedure, a hearing will be 
    held without further notice before the Commission or its designee on 
    this application if no motion to intervene is filed within the time 
    required herein, if the Commission on its own review of the matter 
    finds that a grant of the certificate and permission for abandonment 
    are required by the public convenience and necessity. If a motion for 
    leave to intervene is timely filed, or if the Commission on its own 
    motion believes that a formal hearing is required, further notice of 
    such hearing will be duly given.
        Under the procedure herein provided for, unless otherwise advised, 
    it will be unnecessary for Transco to appear or be represented at the 
    hearing.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 94-20486 Filed 8-19-94; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
08/22/1994
Department:
Energy Department
Entry Type:
Uncategorized Document
Document Number:
94-20486
Pages:
0-0 (1 pages)
Docket Numbers:
Federal Register: August 22, 1994, Docket No. CP94-714-000