95-21032. Duke Power Company, et al. (Catawba Nuclear Station, Unit No. 2); Exemption  

  • [Federal Register Volume 60, Number 164 (Thursday, August 24, 1995)]
    [Notices]
    [Pages 44089-44090]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 95-21032]
    
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    [Docket No. 50-414]
    
    
    Duke Power Company, et al. (Catawba Nuclear Station, Unit No. 2); 
    Exemption
    
    I
    
        The Duke Power Company, et al. (DPC or the licensee) is the holder 
    of Facility Operating License No. NPF-52, which authorizes operation of 
    the Catawba Nuclear Station, Unit No. 2 (the facility), at a steady-
    state reactor power level not in excess of 3411 megawatts thermal. The 
    facility is a pressurized water reactor located at the licensee's site 
    in York County, South Carolina. The license provides, among other 
    things, that the Catawba Nuclear Station is subject to all rules, 
    regulations, and Orders of the U.S. Nuclear Regulatory Commission (the 
    Commission or NRC) now or hereafter in effect.
    
    II
    
        Section III.D.1.(a) of Appendix J to 10 CFR Part 50 requires the 
    performance of three Type A containment integrated leakage rate tests 
    (ILRTs) at approximately equal intervals during each 10-year service 
    period of the primary containment. The third test of each set shall be 
    conducted when the plant is shut down for the 10-year inservice 
    inspection of the primary containment.
    
    III
    
        By letters dated May 18, 1995, and May 31, 1995, the licensee 
    requested temporary relief from the requirement to perform a set of 
    three Type A tests at approximately equal intervals during each 10-year 
    service period of the primary containment. The requested exemption 
    would permit a one-time interval extension of the third Type A test by 
    approximately 30 months (from the 1995 refueling outage, which begins 
    in October 1995, to the end-of-cycle 8 (EOC-8) refueling outage, 
    currently scheduled for March 1997) and would permit the third Type A 
    test of the second 10-year inservice inspection period to not 
    correspond with the end of the current inservice inspection interval.
        The licensee's request concluded that the proposed change, a one-
    time extension of the interval between the second and third ILRTs at 
    Catawba Unit 2, is justified for the following reasons.
        The previous testing history at Catawba Unit 2 provides substantial 
    justification for the proposed test interval extension. In each of the 
    two previous periodic ILRTs at Catawba Unit 2, the as-found leakage was 
    less than or equal to 48.7% of the allowable leakage, thereby 
    demonstrating that Catawba Unit 2 is a low-leakage containment. There 
    are no mechanisms which would adversely affect the structural integrity 
    of the containment, or that would be a factor in extending the test 
    interval by 30 months. However, as a preventative maintenance measure, 
    a containment civil inspection, currently required by Appendix J prior 
    to a Type A test, will be performed during EOC-7 in October 1995 to 
    verify that no structural degradation exists. Any additional risk 
    created by the longer interval between ILRTs is considered to be 
    negligible, primarily because Type B and C testing will continue 
    unchanged.
        Additionally, the licensee stated that its exemption request meets 
    the requirements of 10 CFR 50.12, paragraphs (a)(1) and (a)(2)(ii), for 
    the following reasons:
    
        In order to justify the granting of an exemption to the 
    requirements of 10 CFR Part 50, paragraph 50.12(a)(1) requires that 
    the licensee show that the proposed exemption will not pose an undue 
    risk to the public. That this proposed change will not pose an undue 
    risk is demonstrated by the analysis presented in draft NUREG-1493, 
    which concludes that an increase in the test interval to once every 
    20 years would ``lead to an imperceptible increase in risk.'' The 
    analyses in draft NUREG-1493 are considered to be specifically 
    applicable to Catawba because: (1) The requested exemption would 
    result in a one-time increase in the test interval to about 5 years, 
    not 20; (2) the population density around Catawba is less than that 
    used in the study (329 people per square mile, vs. 340 used in the 
    study); (3) no ILRT at Catawba has failed; 4) the core inventory 
    used in the study was represented by a 3412 Mwt PWR [pressurized 
    water reactor]. Catawba is a 3411 Mwt PWR. Other factors which lead 
    to the conclusion that the proposed change will not pose an undue 
    risk include the fact that local leak rate testing, which identifies 
    97% of leakage in excess of prescribed limits, will remain in place 
    at its current test frequency; the detailed, proceduralized 
    containment civil inspection which is normally performed in 
    conjunction with an ILRT will be performed in place of the scheduled 
    ILRT, to identify potential structural deteriorations; and the 
    historical leak-tightness of the containment structure, as evidenced 
    by two successive ILRTs in which the as-found leakage did not exceed 
    48.7% of the allowable leakage rate. A table which shows the leak 
    test history of Catawba Unit 2 follows this Attachment. 
    
    [[Page 44090]]
    
        A comparison was made between the risk analysis presented in 
    draft NUREG-1493 and a probabilistic risk assessment performed for 
    Catawba Nuclear Station. While the quantitative results of the NUREG 
    are not directly applicable to plants not used in the study, 
    conclusions similar to those presented in the NUREG can be made 
    concerning Catawba. NUREG-1493 indicates that reactor accident risks 
    are dominated by accident sequences that result in failure or bypass 
    of the containment. This conclusion is also valid for Catawba. 
    Considering only the Catawba accident sequences that do not result 
    in containment failure, containment leakage contributes 
    approximately 0.08 to 0.09 percent to off-site risk (whole-body 
    person-rem, thyroid nodules, and latent fatalities). NUREG-1493 
    indicated that containment leakage contributed from 0.02 to 0.10 
    percent to latent cancer risk. The comparison between the analysis 
    of NUREG-1493 and the Catawba PRA concludes that increases in 
    containment leakage at Catawba are expected to produce increases in 
    accident risk similar to the results in NUREG-1493.
        Special circumstances, as defined in 10 CFR 50.12(a)(2)(ii), are 
    considered to exist if ``application of the regulation * * * is not 
    necessary to achieve the underlying purpose of the rule.'' The 
    purposes of the rule, as stated in Section I of Appendix J, are to 
    ensure that: a) leakage through the primary reactor containment and 
    systems and components penetrating containment shall not exceed 
    allowable values, and b) periodic surveillance of reactor 
    containment penetrations and isolation valves is performed so that 
    proper maintenance and repairs are made. One of the significant 
    factors in assuring that the proposed exemption will not pose an 
    undue risk to the public, as noted above, is the local leak rate 
    testing (LLRT) which is performed. That the LLRT program at Catawba 
    provides an effective mechanism for maintaining containment 
    integrity is perhaps best demonstrated by the fact that the most 
    recent ILRT at Catawba Unit 2 was performed at the front end of the 
    refueling outage; before any repairs or adjustments were made to 
    valves or penetrations. Nevertheless, the as-found leakage did not 
    exceed 48.7% of the allowable leakage rate. The fact that no leakage 
    paths were identified by an ILRT, and that the ILRT met the 
    acceptance criteria with significant margin confirms the results of 
    the Type B and C testing.
        The frequency and scope of the Type B and C LLRT program are not 
    being changed by this exemption request. The LLRT program will 
    continue to effectively detect containment leakage resulting from 
    the degradation of active containment isolation components, as well 
    as containment penetrations. Administrative limits have been 
    established for each Type B or C component at a fraction of the 
    allowable leak rate, such that any leakage detected in excess of the 
    administrative limit will indicate a potential valve or penetration 
    degradation. In instances in which a component's leakage exceeds its 
    administrative limit, proceduralized controls in the test program 
    require that a work order be written to repair the component.
    
    IV
    
        Section III.D.1.(a) of Appendix J to 10 CFR Part 50 states that a 
    set of three Type A leakage rate tests shall be performed at 
    approximately equal intervals during each 10-year service period.
        The licensee proposes an exemption to this section which would 
    provide a one-time interval extension for the Type A test by 
    approximately 30 months. The Commission has determined that, pursuant 
    to 10 CFR 50.12(a)(1), this exemption is authorized by law, will not 
    present an undue risk to the public health and safety, and is 
    consistent with the common defense and security. The Commission further 
    determined, for the reasons discussed below, that special 
    circumstances, as provided in 10 CFR 50.12(a)(2)(ii), are present 
    justifying the exemption; namely, that application of the regulation in 
    the particular circumstances is not necessary to achieve the underlying 
    purpose of the rule. The underlying purpose of the requirement to 
    perform Type A containment leak rate tests at approximately equal 
    intervals during the 10-year service period, is to ensure that any 
    potential leakage pathways through the containment boundary are 
    identified within a time span that prevents significant degradation 
    from continuing or becoming unknown. The NRC staff has reviewed the 
    basis and supporting information provided by the licensee in the 
    exemption request. The NRC staff has noted that the licensee has a good 
    record of ensuring a leak-tight containment. All Type A tests have 
    passed with significant margin and the licensee has noted that the 
    results of the Type A testing have been confirmatory of the Type B and 
    C tests which will continue to be performed. The licensee has stated 
    that it will continue to perform the general containment civil 
    inspection although it is only required by Appendix J (Section V.A.) to 
    be performed in conjunction with Type A tests. The NRC staff considers 
    that these inspections, though limited in scope, provide an important 
    added level of confidence in the continued integrity of the containment 
    boundary.
        The NRC staff has also made use of a draft staff report, NUREG-
    1493, which provides the technical justification for the present 
    Appendix J rulemaking effort which also includes a 10-year test 
    interval for Type A tests. The integrated leakage rate test, or Type A 
    test, measures overall containment leakage. However, operating 
    experience with all types of containments used in this country 
    demonstrates that essentially all containment leakage can be detected 
    by local leakage rate tests (Type B and C). According to results given 
    in NUREG-1493, out of 180 ILRT reports covering 110 individual reactors 
    and approximately 770 years of operating history, only 5 ILRT failures 
    were found that local leakage rate testing could not detect. This is 3% 
    of all failures. This study agrees with previous NRC staff studies 
    which show that Type B and C testing can detect a very large percentage 
    of containment leaks. The Catawba Unit 2 experience has also been 
    consistent with this.
        The Nuclear Management and Resources Council (NUMARC), now the 
    Nuclear Energy Institute (NEI), collected and provided the NRC staff 
    with summaries of data to assist in the Appendix J rulemaking effort. 
    NUMARC collected results of 144 ILRTs from 33 units; 23 ILRTs exceeded 
    1.0La. Of these, only nine were not due to Type B or C leakage 
    penalties. The NEI data also added another perspective. The NEI data 
    show that in about one-third of the cases exceeding allowable leakage, 
    the as-found leakage was less than 2La; in one case the leakage 
    was found to be approximately 2La; in one case the as-found 
    leakage was less than 3La; one case approached 10La; and in 
    one case the leakage was found to be approximately 21La. For about 
    half of the failed ILRTs, the as-found leakage was not quantified. 
    These data show that, for those ILRTs for which the leakage was 
    quantified, the leakage values are small in comparison to the leakage 
    value at which the risk to the public starts to increase over the value 
    of risk corresponding to La (approximately 200La, as 
    discussed in NUREG-1493).
        Based on generic and plant-specific data, the NRC staff finds the 
    licensee's proposed one-time exemption to permit a schedular extension 
    of one cycle for the performance of the Appendix Type A test to be 
    acceptable.
        Pursuant to 10 CFR 51.32, the Commission has determined that 
    granting this exemption will not have a significant impact on the human 
    environment (60 FR 32567).
        This exemption is effective upon issuance and shall expire at the 
    completion of the 1997 refueling outage.
    
        Dated at Rockville, Maryland, this 17th day of August 1995
    
        For the Nuclear Regulatory Commission.
    Steven A. Varga,
    Director, Division of Reactor Projects--I/II, Office of Nuclear Reactor 
    Regulation.
    [FR Doc. 95-21032 Filed 8-23-95; 8:45 am]
    BILLING CODE 7590-01-P
    
    

Document Information

Published:
08/24/1995
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
95-21032
Pages:
44089-44090 (2 pages)
Docket Numbers:
Docket No. 50-414
PDF File:
95-21032.pdf