99-21984. San Diego Gas & Electric Company, et al.; Electric Rate and Corporate Regulation Filings  

  • [Federal Register Volume 64, Number 164 (Wednesday, August 25, 1999)]
    [Notices]
    [Pages 46369-46374]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-21984]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    [Docket No. ER97-2364-003, et al.]
    
    
    San Diego Gas & Electric Company, et al.; Electric Rate and 
    Corporate Regulation Filings
    
    August 18, 1999.
        Take notice that the following filings have been made with the 
    Commission:
    
    1. San Diego Gas & Electric Company
    
    [Docket No. ER97-2364-003
    
        Take notice that on August 9, 1999, San Diego Gas & Electric 
    Company (SDG&E), tendered for filing a refund report in compliance with 
    the Commission order, dated March 12, 1999, approving its settlement 
    transmission rates.
        Copies of this filing have been served upon all parties in Docket 
    ER98-2364-000, including the California Public Utilities Commission, 
    the California Independent System Operator, California Independent 
    System Operator-registered Scheduling Coordinators, Pacific Gas and 
    Electric Company, and Southern California Edison Company.
        Comment date: August 30, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    2. Southern Indiana Gas & Electric
    
    [Docket No. ER99-3573-000]
    
        Take notice that on July 15, 1999, Southern Indiana Gas & Electric 
    Company (SIGECO), tendered for filing two (2) Service Agreements for 
    market based rate power sales under its Market Based Rate Tariff with 
    DTE Energy Trading, Inc., and East Kentucky Power Cooperative, Inc.
        Copies of the filing were served upon each of the parties to the 
    Service Agreements.
        Comment date: August 30, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    3. MidAmerican Energy Company
    
    [Docket No. ER99-3887-000]
    
        Take notice that on August 10, 1999, MidAmerican Energy Company 
    tendered for filing changes to its open access transmission tariff 
    filed on July 30, 1999.
        Comment date: August 30, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    4. Northeast Utilities Service Company
    
    [Docket No. ER99-4028-000]
    
        Take notice that August 9, 1999, Northeast Utilities Service 
    Company (NUSCO), tendered for filing a Service Agreement to provide 
    Network Integration Transmission Service to the New Hampshire Electric 
    Co-op under the NU System Companies' Open Access Transmission Service 
    Tariff No. 9.
        NUSCO states that a copy of this filing has been mailed to the New 
    Hampshire Electric Co-op.
        NUSCO requests that the Service Agreement become effective August 
    1, 1999.
    
    [[Page 46370]]
    
        Comment date: August 30, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    5. Central Hudson Gas & Electric Corporation; Consolidated Edison 
    Company of New York, Inc.; Long Island Lighting Company; New York 
    State Electric & Gas Corporation; Niagara Mohawk Power Corporation; 
    Orange & Rockland Utilities, Inc.; Rochester Gas & Electric Corp.; 
    Power Authority of the State of New York; and New York Power Pool
    
    [Docket Nos. ER97-1523-012, OA97-470-011, and ER97-4234-009]
    
        Take notice that on August 10, 1999, the New York Independent 
    System Operator, Inc. (NYISO), tendered a detailed proposal for an 
    installed capacity auction. The NYISO requests an effective date of 
    September 15, 1999.
        A copy of this filing was served upon all persons on the 
    Commission's official service lists in Docket Nos. ER97-1523-000, OA97-
    470-000 and ER97-4234-000 (not consolidated), and the respective 
    electric utility regulatory agencies in New York, New Jersey and 
    Pennsylvania.
        Comment date: August 30, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    6. Consolidated Edison Company of New York, Inc. and Orange and 
    Rockland Utilities, Inc.
    
    [Docket No. ER98-4510-002]
    
        Take notice that on August 9, 1999, Consolidated Edison Company of 
    New York, Inc. (Con Edison) and Orange and Rockland Utilities, Inc., 
    and its jurisdictional subsidiaries (O&R), tendered for filing revised 
    tariff sheets amending the Consolidated Edison Operating Companies FERC 
    Electric Tariff Original Volume No. 1 (Joint OATT).
        The proposed tariff sheets were filed in compliance with the 
    requirement of the January 27, 1999, order in this proceeding (86 FERC 
    61,063) that Con Edison and O&R establish rates to apply under the 
    Joint OATT in the event that the New York Independent System Operator 
    (NY ISO) was not operational by the date of the Con Edison and O&R 
    merger.
        The revised tariff sheets would become effective on October 8, 1999 
    if the NY ISO is not operational by that date.
        Comment date: August 30, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    7. California Independent System Operator Corporation
    
    [Docket No. ER99-1971-003]
    
        Take notice that on August 11, 1999, the California Independent 
    System Operator Corporation (ISO), tendered for filing a Notice to 
    Market Participants, dated August 10, 1999, which specifies that the 
    software required to implement the following elements of Amendment No. 
    14 to the ISO Tariff will be uploaded to production for Day-Ahead 
    scheduling on Tuesday, August 17, 1999 for Operating Day Wednesday, 
    August 18, 1999: Metered Demand, Use Of Replacement Reserves, Rational 
    Buyer, Regulation Up and Regulation Down, and Effective Price for 
    Uninstructed Deviations.
        The ISO states that this filing has been served on all parties 
    listed on the official service list in the above-referenced docket.
        Comment date: August 31, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    8. North American Electric Reliability Council
    
    [Docket No. ER99-2997-001]
    
        Take notice that on August 9, 1999, the North American Electric 
    Reliability Council tendered for filing a compliance filing in this 
    docket.
        Comment date: August 30, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    9. Consolidated Edison Energy, Inc.
    
    [Docket No. ER99-3248-001]
    
        Take notice that on August 9, 1999, Consolidated Edison Energy 
    Massachusetts, Inc. (CEEMI), tendered for filing its compliance filing 
    with respect to Consolidated Edison Energy Massachusetts FERC Electric 
    Tariff No. 1, Market Based Rates Tariff.
        CEEMI states that a copy of this filing has been served by mail 
    upon The New York State Public Service Commission.
        Comment date: August 30, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    10. Power Management Co., LLC
    
    [Docket No. ER99-3275-000]
    
        Take notice that on August 11, 1999, Power Management Co., LLC, 
    tendered for filing an amendment to its July 16, 1999, Petition for 
    Acceptance of Initial Rate Schedule, Waiver and Blanket Authority filed 
    with the Commission in the above-referenced docket.
        Comment date: August 31, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    11. Tucson Electric Power Company
    
    [Docket No. ER99-4029-000]
    
        Take notice that on August 9, 1999, Tucson Electric Power Company 
    (Tucson), tendered for filing an Umbrella Service Agreement between 
    Tucson and Ajo Improvement Company for short-term power sales under 
    Tucson's Market-Based Power Sales Tariff, FERC Electric Tariff Original 
    Volume No. 3.
        Comment date: August 30, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    12. Delmarva Power & Light Company
    
    [Docket No. ER99-4041-000]
    
        Take notice that on August 10, 1999, Delmarva Power & Light Company 
    (Delmarva), tendered for filing an executed umbrella service agreement 
    with Central Vermont Public Service Corporation (CVPS) under Delmarva's 
    market rate sales tariff.
        Delmarva requests an effective date of August 10, 1999.
        Comment date: August 30, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    13. Golden Spread Electric Cooperative, Inc.
    
    [Docket No. ER99-4042-000]
    
        Take notice that on August 10, 1999, Golden Spread Electric 
    Cooperative, Inc. (Golden Spread), tendered for filing proposed changes 
    to its FERC Rate Schedule Nos. 23-33. The purpose of the rate change is 
    to implement a Load Reduction Rider to its existing Rate Schedules 
    between itself and its Member Cooperatives.
        Copies of this filing were served upon Golden Spread's eleven 
    Member Cooperatives and the Public Utility Commission of Texas.
        Comment date: August 30, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    14. ISO New England, Inc.
    
    [Docket No. ER99-4043-000]
    
        Take notice that on August 10, 1999, ISO New England Inc. (the 
    ISO), tendered an Amendment to the ISO Tariff regarding Working Capital 
    Allocation.
        Copies of said filing have been served upon the Participants in the 
    New England Power Pool, non-Participant transmission customers and to 
    the New England State Governors and Regulatory Commissions.
        Comment date: August 30, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    [[Page 46371]]
    
    15. New England Power Pool
    
    [Docket No. ER99-4030-000]
    
        Take notice that on August 9, 1999, the New England Power Pool 
    (NEPOOL), Participants Committee submitted revisions to Market Rule 15. 
    This filing extends the effectiveness of Market Rule 15 and makes 
    limited changes to this NEPOOL Market Rule.
        NEPOOL has requested that Market Rule 15, as revised, be allowed to 
    become effective as of August 1, 1999.
        The NEPOOL Participants Committee states that copies of these 
    materials were sent to the New England state governors and regulatory 
    commissions and the Participants in the New England Power Pool.
        Comment date: August 30, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    16. Baltimore Gas and Electric Company
    
    [Docket No. ER99-4031-000]
    
        Take notice that on August 9, 1999, Baltimore Gas and Electric 
    Company (BGE), tendered for filing a Service Agreement with Citizens 
    Power Sales, under BGE's FERC Electric Tariff Original Volume No. 3 
    (Tariff). Under the tendered Service Agreement, BGE agrees to provide 
    services pursuant to the provisions of the Tariff.
        BGE requests an effective date of February 18, 1999, for the 
    Service Agreements. BGE states that a copy of the filing was served 
    upon the Public Service Commission of Maryland.
        Comment date: August 30, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    17. The Detroit Edison Company
    
    [Docket No. ER99-4035-000]
    
        Take notice that on August 10, 1999, Detroit Edison Company 
    (Detroit Edison), tendered for filing a Service Agreement for wholesale 
    power sales transactions under Detroit Edison's Wholesale Power Sales 
    Tariff (WPS-2), FERC Electric Tariff No. 3 (the WPS-2 Tariff) between 
    Detroit Edison and Minnesota Power, Inc., dated as of July 22, 1999.
        Comment date: August 30, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    18. Allegheny Power Service Corporation, on behalf of West Penn 
    Power Company (Allegheny Energy)
    
    [Docket Nos. ER99-3492-000; ER99-3568-000; ER99-3581-000; ER99-3582-
    000; ER99-3583-000; ER99-3584-000; ER99-3646-000; ER99-3671-000; ER99-
    3675-000; ER99-3715-000; ER99-3716-000; ER99-3717-000; and ER99-3718-
    000]
    
        Take notice that on August 9, 1999, Allegheny Power Service 
    Corporation on behalf of West Penn Power Company (Allegheny Energy), 
    tendered for filing a request to withdraw Amendments to Supplements to 
    Market Rate and Standard Generation Service Tariffs filed on behalf of 
    West Penn Power Company (Allegheny Energy) in the above-referenced 
    dockets.
        Copies of the filing have been provided to the Public Utilities 
    Commission of Ohio, the Pennsylvania Public Utility Commission, the 
    Maryland Public Service Commission, the Virginia State Corporation 
    Commission, the West Virginia Public Service Commission, and all 
    parties of record.
        Comment date: August 30, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    19. Allegheny Power Service Corporation, on behalf of Monongahela 
    Power Company, The Potomac Edison Company and West Penn Power 
    Company (Allegheny Power)
    
    [Docket No. ER99-4033-000]
    
        Take notice that on August 9, 1999, Allegheny Power Service 
    Corporation on behalf of Monongahela Power Company, The Potomac Edison 
    Company and West Penn Power Company (Allegheny Power), tendered for 
    filing Supplement No. 31 to add two (2) new Customers to the Market 
    Rate Tariff under which Allegheny Power offers generation services.
        Allegheny Power requests a waiver of notice requirements to make 
    service available as of August 6, 1999, to Cargill-Alliant, LLC and 
    Citizens Power Sales.
        Copies of the filing have been provided to the Public Utilities 
    Commission of Ohio, the Pennsylvania Public Utility Commission, the 
    Maryland Public Service Commission, the Virginia State Corporation 
    Commission, the West Virginia Public Service Commission, and all 
    parties of record.
        Comment date: August 30, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    20. New York State Electric & Gas Corporation
    
    [Docket No. ER99-4036-000]
    
        Take notice that on August 10, 1999, New York State Electric & Gas 
    Corporation (NYSEG), tendered for filing pursuant to part 35 of the 
    Federal Energy Regulatory Commission's rules of practice and procedure, 
    18 CFR 35, service agreements (the Service Agreements) under which 
    NYSEG may provide capacity and/or energy to TransAlta Energy Marketing 
    (U.S.) Inc. (TransAlta), Huntley Power LLC (Huntley), Arthur Kill Power 
    LLC (Arthur Kill), Astoria Gas Turbine Power LLC (Astoria), Dunkirk 
    Power LLC (Dunkirk), and NRG Power Marketing, Inc. (NRG) in accordance 
    with NYSEG's FERC Electric Tariff, Original Volume No. 3.
        NYSEG has requested waiver of the notice requirements so that the 
    Service Agreements with TransAlta, Huntley, Arthur Kill, Astoria, 
    Dunkirk, and NRG become effective as of August 11, 1999.
        NYSEG has served copies of the filing upon the New York State 
    Public Service Commission, TransAlta, Huntley, Arthur Kill, Astoria, 
    Dunkirk, and NRG.
        Comment date: August 30, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    21. Avista Corporation
    
    [Docket No. ER99-4038-000]
    
        Take notice that on August 10, 1999, Avista Corporation tendered 
    for filing, with the Federal Energy Regulatory Commission pursuant to 
    18 CFR Section 35.13, an executed Mutual Netting Agreement allowing for 
    arrangements of amounts which become due and owing to one Party to be 
    set off against amounts which are due and owing to the other Party with 
    City of Santa Clara, d/b/a Silicon Valley Power.
        Avista Corporation requests waiver of the prior notice requirement 
    and requests an effective date of July 1, 1999.
        Comment date: August 30, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    22. Southern California Edison Company
    
    [Docket No. ER99-4039-000]
    
        Take notice that on August 10, 1999, Southern California Edison 
    Company (SCE), tendered for filing Amendment No. 1 to the Edison-
    Anaheim Interconnection Agreement (Amendment) between SCE and the City 
    of Anaheim, California. The Amendment reflects a change in ownership 
    and responsibility for metering facilities at the Lewis
    
    [[Page 46372]]
    
    Substation from SCE to the City of Anaheim.
        Copies of this filing were served upon the Public Utilities 
    Commission of the State of California, the California Independent 
    System Operator Corporation, and the City of Anaheim.
        Comment date: August 30, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    23. Cleco Utility Group, Inc.
    
    [Docket No. ER99-4040-000]
    
        Take notice that on August 10, 1999, Cleco Utility Group, Inc. 
    (Cleco), tendered for filing a service agreement under which Cleco will 
    make market based power sales under its MR-1 tariff with the City of 
    Gueydan, Louisiana.
        Cleco states that a copy of the filing has been served on the City 
    of Gueydan.
        Comment date: August 30, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    24. Sandia Resources Corporation
    
    [Docket No. ER99-4044-000]
    
        Take notice that on August 10, 1999, Sandia Resources Corporation 
    (Sandia) petitioned the Commission for acceptance of Sandia Rate 
    Schedule FERC No. 1, the granting of certain blanket approvals, 
    including the authority to sell electricity at market-based rates; and 
    the waiver of certain Commission Regulations.
        Sandia intends to engage in wholesale electric power and energy 
    purchases and sales as a marketer. Sandia is not in the business of 
    generating or transmitting electric power. Sandia has no affiliates.
        Comment date: August 30, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    25. Public Service Company of New Mexico
    
    [Docket No. ER99-4046-000]
    
        Take notice that on August 11, 1999, Public Service Company of New 
    Mexico (PNM), tendered for filing Amendment Number Two to the Wholesale 
    Power Purchase Agreement between PNM and Navajo Tribal Utility 
    Authority (NTUA), dated July 13, 1999. The purpose of the Amendment is 
    to conform the Agreement with PNM's Settlement Rates for mandatory 
    ancillary services accepted for filing by the Commission by Letter 
    Order dated April 6, 1999.
        PNM requests waiver of the Commission's notice requirements in 
    order that the Amendment be effective retroactive to August 1, 1998.
        Copies of this filing have been provided to NTUA, PNM Transmission 
    Development and Contracts, PNM Wholesale Power Marketing, and the New 
    Mexico Public Regulation Commission. PNM's filing is available for 
    inspection at its offices in Albuquerque, New Mexico.
        Comment date: August 31, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    26. Ameren Services Company
    
    [Docket No. ER99-4048-000]
    
        Take notice that on August 11, 1999, Ameren Services Company (ASC), 
    tendered for filing a Service Agreement for Non-Firm Point-to-Point 
    Transmission Service between ASC and Illinova Energy Partners, Inc. 
    (IEP). ASC asserts that the purpose of the Agreement is to permit ASC 
    to provide transmission service to IEP pursuant to Ameren's Open Access 
    Transmission Tariff filed in Docket No. ER96-677-004.
        Comment date: August 31, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    27. Ameren Services Company
    
    [Docket No. ER99-4049-000]
    
        Take notice that on August 11, 1999, Ameren Services Company (ASC), 
    tendered for filing a Service Agreement for Firm Point-to-Point 
    Transmission Services between ASC and Illinova Energy Partners, Inc. 
    (IEP). ASC asserts that the purpose of the Agreement is to permit ASC 
    to provide transmission service to IEP pursuant to Ameren's Open Access 
    Transmission Tariff filed in Docket No. ER 96-677-004.
        Comment date: August 31, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    28. Idaho Power Company
    
    [Docket No. ER99-4051-000]
    
        Take notice that on August 11, 1999, Idaho Power Company (IPC), 
    tendered for filing with the Federal Energy Regulatory Commission 
    Service Agreements for Non-Firm Point-to-Point Transmission Service and 
    Firm Point-to-Point Transmission Service between Idaho Power Company 
    and TXU Energy Trading Company.
        Comment date: August 31, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    29. Ameren Services Company
    
    [Docket No. ER99-4052-000]
    
        Take notice that on August 11, 1999, Ameren Services Company 
    (Ameren), tendered for filing Service Agreements for Market Based Rate 
    Power Sales between Ameren and The Detroit Edison Company and Southern 
    Minnesota Municipal Power Agency (the parties). Ameren asserts that the 
    purpose of the Agreements is to permit Ameren to make sales of capacity 
    and energy at market based rates to the parties pursuant to Ameren's 
    Market Based Rate Power Sales Tariff filed in Docket No. ER98-3285-000.
        Comment date: August 31, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    30. Southern Indiana Gas and Electric Company, Indiana Energy, Inc. 
    and Vectren Corporation
    
    [Docket No. EC99-106-000]
    
        Take notice that on August 13, 1999, Southern Indiana Gas and 
    Electric Company (SIGECO), Indiana Energy, Inc. (Indiana Energy) and 
    Vectren Corporation (Vectren) submitted for filing, pursuant to section 
    203 of the Federal Power Act and Part 33 of the Commission's 
    regulations, an application for approval of the merger of SIGECO's 
    parent, SIGCORP, Inc. with Indiana Energy and into Vectren.
        A copy of the filing has been served upon the regulatory agency of 
    the affected state, the Indiana Utility Regulatory Commission.
        Comment date: October 13, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    31. COSI Astoria, Inc.
    
    [Docket No. EG99-211-000]
    
        Take notice that on August 9, 1999, COSI Astoria, Inc. (Applicant), 
    with its principal office at 111 Market Place, Suite 200, Baltimore, 
    Maryland 21202, filed with the Federal Energy Regulatory Commission 
    (Commission) an application for determination of exempt wholesale 
    generator status pursuant to part 365 of the Commission's regulations.
        The Facilities consist of three generating stations located in New 
    York City with a combined total summer net capacity of 1,855 MW. 
    Electric energy produced by the Facilities is sold exclusively at 
    wholesale.
        Comment date: September 8, 1999, in accordance with Standard 
    Paragraph E at the end of this notice. The Commission will limit its 
    consideration of comments to those that concern the adequacy or 
    accuracy of the application.
    
    32. North American Energy Services Company
    
    [Docket No. EG99-213-000]
    
        Take notice that on August 12, 1999, North American Energy Services 
    Company, a Washington corporation (Applicant), with its principal 
    executive office at Bellevue, Washington, filed with the Federal Energy 
    Regulatory
    
    [[Page 46373]]
    
    Commission an application for determination of exempt wholesale 
    generator status pursuant to part 365 of the Commission's regulations 
    (the Application).
        Applicant has entered into an agreement with Wartsila NSD 
    Operations, Inc. (Wartsila), a Maryland corporation, under which 
    Applicant assumes Wartsila's obligations to IGC/ERI Pam-Am Thermal 
    Generating Limited (Pan-Am), a stock company organized and existing 
    pursuant to the laws of the Cayman Islands, to operate and maintain an 
    electric power generating facility located at or near Chorrera, Panama 
    (the Project) pursuant to an agreement for operation and maintenance 
    services between Wartsila and Pan-Am. Project facilities include a 96 
    megawatt fuel oil-fired power generating station, supporting facilities 
    located at the Site and necessary transmission facilities; all of which 
    will be an eligible facility.
        Comment date: September 8, 1999, in accordance with Standard 
    Paragraph E at the end of this notice. The Commission will limit its 
    consideration of comments to those that concern the adequacy or 
    accuracy of the application.
    
    33. California Independent System Operator Corporation
    
    [Docket Nos. ER98-3594-002]
    
        Take notice that on August 13, 1999, the California Independent 
    System Operator Corporation (ISO), tendered for filing a compliance 
    filing in the above-referenced docket which included a number of 
    revisions to the ISO Tariff. The ISO states that this filing was 
    submitted to comply with the Commission's August 2, 1999 Order, 88 FERC 
    para. 61,156 (1999), in the above-referenced docket.
        The ISO states that this filing has been served on all parties 
    listed on the official service list in the above-referenced docket.
        Comment date: September 2, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    34. PG Energy PowerPlus; PG&E Energy Services Corporation; West 
    Georgia Generating Company L.P.
    
    [Docket No. ER98-1953-002; Docket No. ER98-1953-003; Docket No. ER95-
    1614-020; Docket No. ER97-1686-007]
    
        Take notice that on August 13, 1999, the above-mentioned power 
    marketers filed quarterly reports with the Commission in the above-
    mentioned proceedings for information only. These filings are available 
    for public inspection and copying in the Public Reference Room or on 
    the web at www.ferc.fed.us/online/rims.htm for viewing and downloading 
    (call 202-208-2222 for assistance).
    
    35. Southern Energy California, L.L.C.; UGI Power Supply, Inc.
    
    [Docket No. ER99-1841-001; Docket No. ER96-2715-012; Docket No. ER96-
    2715-013]
    
        Take notice that on August 12, 1999, the above-mentioned power 
    marketers filed quarterly reports with the Commission in the above-
    mentioned proceedings for information only. These filings are available 
    for public inspection and copying in the Public Reference Room or on 
    the web at www.ferc.fed.us/online/rims.htm for viewing and downloading 
    (call 202-208-2222 for assistance).
    
    36. Ameren Services Company
    
    [Docket No. ER99-4047-000]
    
        Take notice that on August 11, 1999, Ameren Services Company (ASC), 
    tendered for filing an Interconnection Agreement ASC and Trigen-St. 
    Louis Energy Corporation (Trigen). ASC asserts that the purpose of the 
    Agreement is to establish Trigen's interconnection with Ameren's 
    transmission system.
        Comment date: August 31, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    37. International Energy Consultants, Inc.
    
    [Docket No. ER99-3130-000]
    
        Take notice that on August 13, 1999, International Energy 
    Consultants, Inc. filed an amendment to their petition that was filed 
    on June 2, 1999.
        Comment date: September 2, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    38. West Georgia Generating Company, L.P.
    
    [Docket No. ER99-4065-000]
    
        Take notice that on August 13, 1999, the above-mentioned affiliated 
    power producer filed its quarterly report for the quarter ending June 
    30, 1999.
        Comment date: September 2, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    39. Arizona Public Service Company; Southern Energy Delta, L.L.C.; 
    Southern Energy Potrero, L.L.C.
    
    [Docket No. ER99-4066-000; Docket No. ER99-4075-000; Docket No. ER99-
    4076-000]
    
        Take notice that on August 12, 1999, the above-mentioned affiliated 
    power producers and/or public utilities filed their quarterly reports 
    for the quarter ending June 30, 1999.
        Comment date: September 1, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    40. California Independent System Operator Corporation
    
    [Docket Nos. ER99-3301-001]
    
        Take notice that on August 13, 1999, the California Independent 
    System Operator Corporation (ISO), tendered for filing a compliance 
    filing in the above-referenced docket which included a revision to the 
    ISO Tariff. The ISO states that this filing was submitted to comply 
    with the Commission's July 30, 1999 Order, 88 FERC para. 61,146 (1999), 
    in the above-referenced docket.
        The ISO states that this filing has been served on all parties 
    listed on the official service list in the above-referenced docket.
        Comment date: September 1, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    41. Northeast Utilities Service Company
    
    [Docket No. OA97-237-009]
    
        Take notice that on August 13, 1999, Northeast Utilities Service 
    Company (NUSCO), tendered for filing a refund report in compliance with 
    the Commission's order in Northeast Utilities Service Company, 88 FERC 
    para.  61,006 (1999).
        Comment date: September 13, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    42. Carville Energy LLC
    
    [Docket No. QF98-83-001]
    
        Take notice that on August 12, 1999, Carville Energy LLC located at 
    Edens Corporate Center, 650 Dundee Road, Suite 350, Northbrook, IL 
    60062 filed with the Federal Energy Regulatory Commission an 
    application for certification of a facility as a qualifying 
    cogeneration facility pursuant to 292.207(b) of the Commission's 
    regulations. No determination has been made that the submittal 
    constitutes a complete filing.
        The facility located at the Carville Energy Center is a gas turbine 
    combined cycle cogeneration facility that uses natural gas as its fuel 
    source. The facility includes two combustion turbine generators, each 
    with a rated capacity of approximately 160,000 kW at ISO conditions, 
    two heat recovery steam generators, and two condensing steam turbine 
    generators, each rated at approximately 85,000 kW. The facility will be 
    located in Iberville Parish, Louisiana.
        The Facility will interconnect directly and with the transmission 
    system of Entergy, located in New Orleans, Louisiana, and will sell its 
    useful output at wholesale to various qualified buyers which may 
    include Entergy. Entergy
    
    [[Page 46374]]
    
    will provide back-up and maintenance power to the Facility.
        Comment date: September 13, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    Standard Paragraph
    
        E. Any person desiring to be heard or to protest such filing should 
    file a motion to intervene or protest with the Federal Energy 
    Regulatory Commission, 888 First Street, NE, Washington, DC 20426, in 
    accordance with rules 211 and 214 of the Commission's rules of practice 
    and procedure (18 CFR 385.211 and 385.214). All such motions or 
    protests should be filed on or before the comment date. Protests will 
    be considered by the Commission in determining the appropriate action 
    to be taken, but will not serve to make protestants parties to the 
    proceeding. Any person wishing to become a party must file a motion to 
    intervene. Copies of these filings are on file with the Commission and 
    are available for public inspection. This filing may also be viewed on 
    the Internet at http://www.ferc.fed.us/online/rims.htm (call 202-208-
    2222 for assistance).
    Linwood A. Watson, Jr.,
    Acting Secretary.
    [FR Doc. 99-21984 Filed 8-24-99; 8:45 am]
    BILLING CODE 6717-01-P
    
    
    

Document Information

Published:
08/25/1999
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
99-21984
Dates:
August 30, 1999, in accordance with Standard Paragraph E at the end of this notice.
Pages:
46369-46374 (6 pages)
Docket Numbers:
Docket No. ER97-2364-003, et al.
PDF File:
99-21984.pdf