DEPARTMENT OF ENERGY
Draft Environmental Impact Statement for the Proposed JEA
Circulating Fluidized Bed Combustor Project at Jacksonville, Florida
AGENCY: Department of Energy.
ACTION: Notice of Availability.
-----------------------------------------------------------------------
SUMMARY: The Department of Energy (DOE) announces the availability for
public review and comment of the Draft Environmental Impact Statement
(EIS) for the JEA Circulating Fluidized Bed Combustor Project (DOE/EIS-
0289), at Jacksonville, Florida. The Draft EIS was prepared pursuant to
the National Environmental Policy Act (NEPA) of 1969, as amended (42
U.S.C. 4321 et seq.), Council on Environmental Quality NEPA regulations
(40 CFR parts 1500-1508), and the DOE NEPA regulations (10 CFR part
1021). The Draft EIS analyzes the environmental impacts that could
result from a proposal under DOE's Clean Coal Technology Program to
construct and operate a nearly 300 megawatt-electric, coal-and
petroleum coke-fired, circulating fluidized bed combustor and boiler to
repower an existing steam turbine at JEA's Northside Generating
Station. DOE's proposed action is to provide cost-shared funding of
approximately $73.1 million (about 24 percent of the estimated total
cost of $309 million) for construction of the combustor and boiler and
for a 24-month period of demonstration testing of the technology.
The proposed project would demonstrate technology that is capable
of cost-effectively reducing nitrogen oxide, sulfur dioxide, and
particulate emissions, while producing power more efficiently and at
less cost than conventional coal combustion technologies. Information
and experience developed from this project could provide the basis for
demonstrating the potential of utility scale, circulating fluidized bed
technology as a practical alternative to conventional coal-fired power
plant technologies.
DATES: DOE invites the public to comment on the Draft JEA EIS. Comments
should be submitted by October 15, 1999 (see ADDRESSES section for more
details) to ensure
[[Page 46364]]
consideration. DOE will consider comments submitted after October 15,
1999, to the extent practicable. A public hearing on the Draft JEA EIS
will be held as follows: Florida Community College at Jacksonville,
North Campus, Thursday, September 16, 1999, Times: 12 pm to 3 pm
(Information Session) and 6 pm to 9 pm (Public Hearing).
The hearing will provide an opportunity for information exchange
and discussion among DOE and the public, as well as opportunities for
the public to present oral or written comments.
ADDRESSES: Comments may be submitted by mail, fax, telephone, or
electronically to: Ms. Lisa Hollingsworth, NEPA Document Manager, U.S.
Department of Energy, Federal Energy Technology Center, P.O. Box 880,
Morgantown, WV 26507-0880, Telephone: 304-285-4992; Fax 304-285-4403,
leave a message at 1-800-276-9851, lisa.hollingsworth@fetc.doe.gov.
Requests for copies of the Draft JEA EIS or other information
regarding this environmental analysis should be addressed to Ms.
Hollingsworth at the address above. The Draft EIS will be available
under the DOE NEPA Analysis link from the DOE NEPA Web Site at http://
tis.eh.doe.gov/nepa/.
FOR FURTHER INFORMATION CONTACT: For further information on the
proposed project or the environmental impact statement, please contact
Ms. Hollingsworth as directed above. For general information on the
Department's NEPA process, please contact Ms. Carol M. Borgstrom,
Director, Office of NEPA Policy and Assistance, EH-42, U.S. Department
of Energy, 1000 Independence Avenue, SW, Washington, DC 20585. Ms.
Borgstrom may be contacted by calling 202-586-4600 or by leaving a
message at 1-800-472-2756.
SUPPLEMENTARY INFORMATION:
Background
On November 13, 1997, the Department published a Notice of Intent
(62 FR 60889) to prepare an environmental impact statement for the
proposed JEA Circulating Fluidized Bed Combustor Project, in Duval
County, Jacksonville, Florida. The purpose of the Notice of Intent was
to inform the public of the proposed scope of the EIS, to solicit
public input, and to announce a public scoping meeting that was held on
December 3, 1997, in Jacksonville, FL. The Notice invited comments and
suggestions on the proposed scope of the environmental impact
statement, including environmental issues and alternatives, and invited
public participation in the NEPA process. Comments and feedback
received during the public scoping process were used in preparing the
Draft EIS. The scoping period closed on December 31, 1997.
Alternatives Considered
The Draft EIS evaluates a proposed action and a no-action
alternative. DOE's proposed action is to provide JEA with cost-shared
funding of approximately $73.1 million (24 percent of the estimated
total cost of $309 million) for the construction and operation of a
combustor and boiler to repower a steam turbine and generator that have
been out of service since 1983 at JEA's Northside Generating Station.
In analyzing the proposed action (the preferred alternative), the Draft
EIS also evaluates JEA's plans to repower a second, currently
operating, steam turbine without cost-shared funding from DOE.
In addition to analyzing the environmental impacts of the proposed
action, the Draft EIS analyzes the potential impacts of a No-Action
Alternative. Under the No-Action Alternative, the Draft EIS analyzes
three scenarios that JEA could pursue in the absence of DOE funding.
The scenarios considered are: (1) JEA would construct the proposed
project without DOE funding; (2) JEA would construct a new gas-fired
combined cycle facility at Northside Generating Station or another
location; and (3) JEA would purchase electricity from other utilities
to meet JEA's projected demand. The Draft EIS compares the
environmental impacts that could be expected to occur from repowering
the two steam turbines with new circulating fluidized bed combustors
under the proposed action with the impacts that would be likely from
each of the three scenarios under the No-Action Alternative.
The Draft EIS focuses on impacts from construction and operation of
the proposed project on: Human health, air quality, surface water,
groundwater, ecological resources, socioeconomic resources,
environmental justice, noise, and traffic. In addition, impacts on land
use, floodplains, wetlands, waste management, and cultural resources
are considered.
Availability of the Draft EIS
DOE has distributed copies of the Draft EIS to appropriate Members
of Congress, State and local government officials in Florida, Federal
agencies, and other interested parties. Copies of the document may be
obtained by contacting DOE as provided in the section of this notice
entitled, ADDRESSES. Copies of the Draft EIS are also available for
inspection at the locations identified below:
(1) U.S. Department of Energy, Freedom of Information Reading Room, 1E-
190, Forrestal Building, 1000 Independence Avenue, SW, Washington, DC
20585.
(2) U.S. Department of Energy, Federal Energy Technology Center, 3610
Collins Ferry Road, Morgantown, WV 26507-0880.
(3) U.S. Department of Energy, Federal Energy Technology Center, 626
Cochrans Mill Road, Pittsburgh, PA 15236-0940.
(4) Highlands Branch Library, 1826 Dunn Avenue, Jacksonville, FL 32218.
After the public comment period ends on October 15, 1999, DOE will
consider all comments received, revise the Draft EIS as appropriate,
and issue a Final EIS. DOE will consider the Final EIS, along with
other information, such as economic and technical factors, in deciding
whether or not to provide funding for the construction and operation of
the proposed coal-fired, circulating fluidized bed combustor and
boiler.
Issued in Washington, DC, this 19th day of August 1999.
Robert S. Kripowicz,
Principal Deputy Assistant Secretary for Fossil Energy.
[FR Doc. 99-22007 Filed 8-24-99; 8:45 am]