97-22523. Electric Overhead Distribution Lines; Specifications and Drawings for 24.9/14.4 kV Line Construction  

  • [Federal Register Volume 62, Number 165 (Tuesday, August 26, 1997)]
    [Proposed Rules]
    [Pages 45176-45177]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 97-22523]
    
    
    ========================================================================
    Proposed Rules
                                                    Federal Register
    ________________________________________________________________________
    
    This section of the FEDERAL REGISTER contains notices to the public of 
    the proposed issuance of rules and regulations. The purpose of these 
    notices is to give interested persons an opportunity to participate in 
    the rule making prior to the adoption of the final rules.
    
    ========================================================================
    
    
    Federal Register / Vol. 62, No. 165 / Tuesday, August 26, 1997 / 
    Proposed Rules
    
    [[Page 45176]]
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    DEPARTMENT OF AGRICULTURE
    
    Rural Utilities Service
    
    7 CFR Part 1728
    
    
    Electric Overhead Distribution Lines; Specifications and Drawings 
    for 24.9/14.4 kV Line Construction
    
    AGENCY: Rural Utilities Service, USDA.
    
    ACTION: Proposed rule.
    
    -----------------------------------------------------------------------
    
    SUMMARY: The Rural Utilities Service (RUS) proposes to revise its 
    bulletin of specifications and drawings for 24.9/14.4 kV overhead 
    distribution line construction. RUS proposes to separate the bulletin 
    into 19 sections. Each section would contain an index, construction 
    specifications and a group of similar drawings of construction 
    assemblies which perform a common function. RUS proposes to change the 
    drawing number on each drawing to conform to a new, functional format. 
    RUS also proposes certain additional technical changes to the 154 
    drawings so that construction assemblies would conform to current RUS 
    construction requirements and specifications which would make the 
    drawings more readable. Where applicable, the drawings would show 
    allowable loading limits and reference to new tables which would show 
    maximum line angles. Existing specifications, such as pole setting 
    depths, would not be modified, however, they would be moved to the 
    section that contains wood poles. RUS proposes to renumber and reformat 
    this bulletin in accordance with its new publications and directives 
    system.
    
    DATES: Written comments must be received by RUS by October 27, 1997.
    
    ADDRESSES: Submit written comments to Mr. George J. Bagnall, Director, 
    Electric Staff Division, Rural Utilities Service, U.S. Department of 
    Agriculture, 1400 Independence Avenue, SW., STOP 1569, Washington, DC 
    20250-1569. RUS requires a signed original and three copies of all 
    comments (7 CFR 1700.30(e)). Comments will be available for public 
    inspection during regular business hours (7 CFR 1.27(b)).
    
    FOR FURTHER INFORMATION CONTACT: Mr. James L. Bohlk, Electrical 
    Engineer, Distribution Branch, Electric Staff Division, Rural Utilities 
    Service, U.S. Department of Agriculture, 1400 Independence Avenue, SW., 
    STOP 1569, Washington, DC 20250-1569. Telephone: (202) 720-1967. Fax: 
    (202) 720-7491.
    
    SUPPLEMENTARY INFORMATION:
    
    Executive Order 12866
    
        This rule was waived from Office of Management and Budget (OMB) 
    review.
    
    Executive Order 12372
    
        This proposed rule is excluded from the scope of Executive Order 
    12372, Intergovernmental Consultation, which may require consultation 
    with State and local officials. A Notice of Final Rule entitled 
    Department Programs and Activities Excluded from Executive Order 12372 
    (50 FR 47034) exempts RUS loans and loan guarantees from coverage under 
    this order.
    
    Executive Order 12988
    
        This proposed rule has been reviewed under Executive Order 12988, 
    Civil Justice Reform. RUS has determined that this proposed rule meets 
    the applicable standards provided in Sec. 3. of the Executive Order.
    
    Regulatory Flexibility Act Certification
    
        The Administrator of RUS has determined that a rule relating to the 
    RUS electric loan program is not a rule as defined in the Regulatory 
    Flexibility Act (5 U.S.C. 601 et seq.), and therefore, the Regulatory 
    Flexibility Act does not apply to this proposed rule.
    
    Information Collection and Recordkeeping Requirements
    
        This proposed rule contains no reporting or recordkeeping 
    provisions requiring Office of Management and Budget (OMB) approval 
    under the Paperwork Reduction Act of 1995 (44 U.S.C. Chapter 35, as 
    amended).
    
    National Environmental Policy Act Certification
    
        The Administrator of RUS has determined that this rule will not 
    significantly affect the quality of the human environment as defined by 
    the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.). 
    Therefore, this action does not require an environmental impact 
    statement or assessment.
    
    Catalog of Federal Domestic Assistance
    
        This program described by this proposed rule is listed in the 
    Catalog of Federal Domestic Assistance Programs under No. 10.850, Rural 
    Electrification Loans and Loan Guarantees. This catalog is available on 
    a subscription basis from the Superintendent of Documents, U.S. 
    Government Printing Office, Washington, DC 20402-9325.
    
    Background
    
        Pursuant to the Rural Electrification Act of 1936 as amended (7 
    U.S.C. 901 et seq.), the Rural Utilities Service (RUS) proposes to 
    amend 7 CFR Chapter XVII, Part 1728, Electric Standards and 
    Specification for Materials and Construction, by revising RUS Bulletin 
    50-5 (D-803), Specification and Drawings for 14.4/24.9 kV Line 
    Construction, and renumbering it as RUS Bulletin 1728F-803. RUS 
    maintains a system of bulletins that contains construction standards 
    and specifications for materials and equipment. These standards and 
    specifications apply to system facilities constructed by RUS electric 
    and telecommunications borrowers in accordance with the RUS loan 
    contract, and contain standard construction units, material and 
    equipment units commonly used in RUS electric and telecommunication 
    borrowers' systems.
        RUS Bulletin 50-5 provides dimensioned drawings of standard 
    assembly units and specifications for the construction of 24.9/14.4 kV 
    overhead electric distribution lines. RUS proposes to change the 
    bulletin number from RUS Bulletin 50-5 to RUS Bulletin 1728F-803. The 
    change in the bulletin number and reformatting is necessary to conform 
    to RUS' new publications and directives system. This bulletin will be 
    incorporated by reference in 7 CFR part 1728.97. It may be purchased 
    from the Superintendent of Documents, U.S. Government Printing Office, 
    Washington, DC 20402-9325.
        The major proposed changes are described below.
        The proposed bulletin has been separated into 19 different sections 
    or categories. Each section generally contains construction 
    specifications
    
    [[Page 45177]]
    
    related to the category, an index of drawings in the section and 
    several similar construction drawings of assemblies which are designed 
    to perform a similar function. The proposed bulletin also contains an 
    overall index and general construction specifications. Also added to 
    the proposed bulletin are additional new tables displaying maximum line 
    angles and soil classifications.
        The drawing numbers on all the proposed modified drawings have been 
    slightly changed. The drawing number on each new and modified drawing 
    is in a new, uniform format based on the original RUS numbering scheme 
    and format in which each character in the number has a functional 
    meaning related to the contents of the drawings.
        Approximately 63 construction drawings in previous bulletin 50-5 
    have been deleted in the proposed bulletin. Each drawing was eliminated 
    for one or more of the following reasons:
        (a) There is a conflict in the permissible line angles between the 
    primary conductor supports and the neutral conductor supports;
        (b) The assembly contains material no longer listed in Information 
    Publication 202-1, ``List of Materials Acceptable for Use on Systems of 
    RUS Electrification Borrowers'';
        (c) The assembly or assemblies have been renumbered and reorganized 
    and included in the proposed bulletin as a new drawing;
        (d) The assembly design is no longer acceptable as a RUS 
    construction standard for mechanical strength or clearance reasons;
        (e) The drawing is redundant of another similar drawing and thus 
    not needed or useful;
        (f) The assembly design is no longer preferred or commonly used; 
    or,
        (g) The drawing contains construction instructions or details which 
    are no longer applicable to RUS construction standards.
        Corrections or modifications are being proposed to approximately 89 
    drawings of the bulletin. Each revised drawing contains one or more of 
    the following changes:
        (a) Each drawing was given a new, shorter, simpler and more uniform 
    drawing title or name;
        (b) The primary system voltage of ``24.9/14.4 kV'' and the number 
    of primary phases were drawn in a uniform place in the title block on 
    each drawing where this information is relevant;
        (c) The number (quantity) of locknuts is shown in the material list 
    of all the drawings that have these items;
        (d) The revised drawings specify that crossarms be generally 
    installed one foot, six inches from the top of the pole to utilize the 
    new predrilled hole arrangement in the new RUS standard pole drilling 
    guide;
        (e) The new drawings depict the use of three, more modern, 4\1/4\ 
    inch primary suspension insulators for primary conductors instead of 2-
    6 inch insulators as shown on the previous drawings;
        (f) New technical information, defined as ``design parameters'' 
    would be added to the title blocks on most of the drawings. These 
    design parameters include maximum line angels (referenced to the new 
    tables), maximum longitudinal, transverse or unbalanced loads, maximum 
    working load or maximum holding power. This new technical information 
    defines and usually limits the physical applications of the assembly 
    units shown on the drawings; and,
        (g) Several of the revised drawings contain new advisory notes, 
    technical information and references to other drawings.
        Approximately 87 new drawings are being proposed. Many of these 
    proposed new drawings are of construction assemblies from the previous 
    bulletin that have been modified as appropriate, renumbered and 
    reorganized. Other new drawings were added to exhibit one or more of 
    the following:
        (a) The application of post-type insulators;
        (b) Construction guides and design details;
        (c) New equipment and new design; and
        (d) Details of subassembly units.
        A few new drawings would be added to replace, with modifications as 
    required, needed drawings or assemblies which were deleted from the 
    previous bulletin for the reasons previously given.
    
    List of Subjects in 7 CFR Part 1728
    
        Electric power, Incorporation by reference, Loan programs--energy, 
    Rural areas.
    
        For reasons set out in the preamble, RUS proposes to amend 7 CFR 
    part 1728 as follows:
    
    PART 1728--ELECTRIC STANDARDS AND SPECIFICATIONS FOR MATERIALS AND 
    CONSTRUCTION
    
        1. The authority citation for part 1728 continues to read as 
    follows:
    
        Authority: 7 U.S.C. 901 et seq.; 7 U.S.C. 1921 et seq.; Pub L. 
    103-354, 108 Stat. 3178 (7 U.S.C. 6941 et seq.).
    
        2. Section 1728.97(b) is amended by removing the entry for Bulletin 
    50-5 and adding to the list of bulletins, in numerical order, the entry 
    for Bulletin 1728F-803, to read as follows:
    
    
    Sec. 1728.97  Incorporation by reference of electric standards and 
    specifications.
    
    * * * * *
        (b) List of Bulletins.
    * * * * *
        Bulletin 1728F-803, Specifications and Drawings for 24.9/14.4 kV 
    Line Construction ([Month and year of effective date of final rule])
    * * * * *
        Dated: August 18, 1997.
    Jill Long Thompson,
    Under Secretary, Rural Development.
    [FR Doc. 97-22523 Filed 8-25-97; 8:45 am]
    BILLING CODE 3410-15-P
    
    
    

Document Information

Published:
08/26/1997
Department:
Rural Utilities Service
Entry Type:
Proposed Rule
Action:
Proposed rule.
Document Number:
97-22523
Dates:
Written comments must be received by RUS by October 27, 1997.
Pages:
45176-45177 (2 pages)
PDF File:
97-22523.pdf
CFR: (1)
7 CFR 1728.97