    August 22, 1996.
        Take notice that the following hydroelectric application has been 
    filed with the Commission and is available for public inspection:
        a. Type of Application: Declaration of Intention.
        b. Docket No.: DI96-11-000.
        c. Date Filed: 7/19/96.
        d. Applicant: U.S. Forest Service (Ketchikan, AK).
        e. Name of Project: Swan Lake-Lake Tyee Intertie.
        f. Location: Between Swan Lake hydroelectric project switchyard (P-
    3015) and the Lake Tyee hydroelectric project switchyard (P-2911), 
    Ketchikan and Stikine areas, AK.
        g. Filed Pursuant to: Section 23(b) of the Federal Power Act, 16 
    U.S.C. 817(b).
        h. Applicant Contact: Bill Angelus, EIS Coordinator, Ketchikan 
    Ranger District, Tongass National Forest, 3031 Tongass Avenue, 
    Ketchikan, AK 99901, (907) 225-2148.
        i. FERC Contact: Diane M. Murray, (202) 219-2682.
        j. Comment Date: September 27, 1996.
        k. Description of Project: The proposed transmission line would 
    consist of: (1) A 138 kV electric transmission line that would intertie 
    the electrical systems of Ketchikan Public Utilities.
        When a Declaration of Intention is filed with the Federal Energy 
    Regulatory Commission, the Federal Power Act requires the Commission to 
    investigate and determine if the interests of interstate or foreign 
    commerce would be affected by the project. The Commission also 
    determines whether or not the project: (1) Would be located on a 
    navigable waterway; (2) would occupy or affect public lands or 
    reservations of the United States; (3) would utilize surplus water or 
    water power from a government dam; or (4) if applicable, has involved 
    or would involve any construction subsequent to 1935 that may have 
    increased or would increase the project's head or generating capacity, 
    or have otherwise significantly modified the project's pre-1935 design 
    or operation
        l. Purpose of Project: The proposed transmission line would allow 
    the City of Ketchikan to meet its energy needs by accessing surplus 
    energy at the Lake Tyee project.
        m. This notice also consists of the following standard paragraphs: 
    B, C1, and D2.
        B. Comments, Protests, or Motions to Intervene--Anyone may submit 
    comments, a protest, or a motion to intervene in accordance with the 
    requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
    .214. In determining the appropriate action to take, the Commission 
    will consider all protests or other comments filed, but only those who 
    file a motion to intervene in accordance with the Commission's Rules 
    may become a party to the proceeding. Any comments, protests, or 
    motions to intervene must be received on or before the specified 
    comment date for the particular application.
        C1. Filing and Service of Responsive Documents--Any filings must 
    bear in all capital letters and title ``COMMENTS'', ``RECOMMENDATIONS 
    FOR TERMS AND CONDITIONS'', ``PROTEST'', or ``MOTION TO INTERVENE'', as 
    applicable, and the Project Number of the particular application to 
    which the filing refers. Any of the above-named documents must be filed 
    by providing the original and the number of copies provided by the 
    Commission's regulations to: The Secretary, Federal Energy Regulatory 
    Commission, 888 First Street, NE., Washington, DC 20426. A copy of any 
    motion to intervene must also be served upon each representative of the 
    Applicant specified in the particular application.
        D2. Agency Comments--Federal, state, and local agencies are invited 
    to file comments on the described application. A copy of the 
    application may be obtained by agencies directly from the Applicant. If 
    an agency does not file comments within the time specified for filing 
    comments, it will be presumed to have no comments. One copy of an 
    agency's comments must also be sent to the Applicant's representatives.
    Linwood A. Watson, Jr.,
    Acting Secretary.
    [FR Doc. 96-21895 Filed 8-27-96; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Effective Date:
9/27/1996
Published:
08/28/1996
Department:
Energy Department
Entry Type:
Notice
Document Number:
96-21895
Dates:
September 27, 1996.
Pages:
44307-44307 (1 pages)
PDF File:
96-21895.pdf