2012-21207. Requirements for Maintenance of Inspections, Tests, Analyses, and Acceptance Criteria

  • Start Preamble

    AGENCY:

    Nuclear Regulatory Commission.

    ACTION:

    Final rule and regulatory guide, issuance.

    SUMMARY:

    The U.S. Nuclear Regulatory Commission (NRC or the Commission) is amending its regulations related to verification of nuclear power plant construction activities through inspections, tests, analyses, and acceptance criteria (ITAAC) under a combined license, and issuing a revision to Regulatory Guide (RG) 1.215, “Guidance for ITAAC Closure Under 10 CFR [Title 10 of the Code of Federal Regulations] Part 52.” The final rule contains new provisions that apply after a licensee has completed an ITAAC and submitted an ITAAC closure notification. The new provisions require licensees to report new information materially altering the basis for determining that inspections, tests, or analyses were performed as required, or that acceptance criteria are met, and to notify the NRC of the completion of all ITAAC activities. In addition, the NRC is including editorial corrections to existing language in the NRC's regulations to make that language consistent with language in the Atomic Energy Act of 1954, as amended (AEA). Regulatory Guide 1.215 describes a method that the staff of the NRC considers acceptable for use in satisfying the requirements for documenting the completion of ITAAC.

    DATES:

    The effective date is September 27, 2012.

    ADDRESSES:

    Please refer to Docket ID NRC-2010-0012 when contacting the NRC about the availability of information for this final rule. You can access information and comment submittals related to this final rule, which the NRC possesses and are publicly available, by any of the following methods:

    • Federal Rulemaking Web Site: Go to http://www.regulations.gov and search for Docket ID NRC-2010-0012.
    • NRC's Agencywide Documents Access and Management System (ADAMS): You may access publicly available documents online in the NRC Library at http://www.nrc.gov/​reading-rm/​adams.html. To begin the search, select “ADAMS Public Documents” and then select “Begin Web-based ADAMS Search.” For problems with ADAMS, please contact the NRC's Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. The ADAMS accession number for each document referenced in this document (if that document is available in ADAMS) is provided the first time that a document is referenced. In addition, for the convenience of the reader, the ADAMS accession numbers are provided in a table in the section of this document entitled, “Availability of Documents.”
    • NRC's PDR: You may examine and purchase copies of public documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852.
    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Mr. Earl R. Libby, Office of New Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-0522; email: Earl.Libby@nrc.gov.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    I. Background

    II. Comments on the Proposed Rule and Regulatory Guide

    A. Overview of Public Comments

    B. Comments on the Proposed Rule

    C. Comments on the Draft Regulatory Guide DG-1250/RG 1.215

    III. Discussion

    A. Licensee Programs That Maintain ITAAC Conclusions

    B. Additional ITAAC Notifications

    C. Conforming Changes to 10 CFR 2.340

    IV. Section-by-Section Analysis

    V. Availability of Regulatory Guidance

    VI. Availability of Documents

    VII. Plain Writing

    VIII. Agreement State Compatibility

    IX. Voluntary Consensus Standards

    X. Environmental Impact—Categorical Exclusion

    XI. Paperwork Reduction Act Statement

    XII. Regulatory Analysis

    XIII. Regulatory Flexibility Act Certification

    XIV. Backfitting and Issue Finality

    XV. Congressional Review Act

    I. Background

    The Commission first issued 10 CFR part 52, “Early Site Permits; Standard Design Certifications; and Combined Licenses for Nuclear Power Reactors” on April 18, 1989 (54 FR 15372). Section 52.99, “Inspection during construction,” was included to make it clear that the NRC's inspection carried out during construction under a combined license would be based on ITAAC proposed by the applicant, approved by the NRC staff, and incorporated in the combined license. At that time, the Commission made it clear that, although 10 CFR 52.99 envisioned a “sign-as-you-go” process in which the NRC staff would sign off on inspection units and notice of the staff's sign-off would be published in the Federal Register, the Commission itself would make no findings with respect to construction until construction was complete. (See 54 FR 15372; April 18, 1989; at 15383 (second column)).

    On August 28, 2007 (72 FR 49352), the Commission revised 10 CFR part 52 to enhance the NRC's regulatory effectiveness and efficiency in implementing its licensing and approval processes. In that revision, the NRC amended 10 CFR 52.99 to require licensees to notify the NRC that the prescribed inspections, tests, or analyses in the ITAAC have been completed and that the acceptance criteria have been met. The revision also requires that these notifications contain sufficient information to demonstrate that the prescribed inspections, tests, or analyses have been performed and that the prescribed acceptance criteria have been met. The statement of considerations for the 2007 rule indicated that this requirement would ensure that combined license applicants and holders were aware that it was the licensee's burden to demonstrate compliance with the ITAAC and that the notification of ITAAC completion will contain more information than just a simple statement that the licensee Start Printed Page 51881believes the ITAAC had been completed and the acceptance criteria met.

    Under Section 185b of the AEA and 10 CFR 52.97(b), a combined license for a nuclear power plant (a “facility”) must contain those ITAAC that are “necessary and sufficient to provide reasonable assurance that the facility has been constructed and will be operated in conformity with” the license, the AEA, and the NRC regulations. Following issuance of the combined license, Section 185b of the AEA and 10 CFR 52.99(e) require that the Commission “ensure that the prescribed inspections, tests, and analyses are performed.” Finally, before operation of the facility, Section 185b of the AEA and 10 CFR 52.103(g) require that the Commission find that the “prescribed acceptance criteria are met” (emphasis added). This Commission finding will not occur until construction is complete, near the scheduled date for initial fuel load.

    As currently required by 10 CFR 52.99(c)(1), the licensee must submit ITAAC closure notifications containing “sufficient information to demonstrate that the prescribed inspections, tests, and analyses have been performed and that the associated acceptance criteria have been met.” These notifications perform two functions. First, they alert the NRC to the licensee's completion of the ITAAC [1] and ensure that the NRC has sufficient information to complete all of the activities necessary for the Commission to determine whether all of the ITAAC acceptance criteria have been or will be met (the “will be met” finding is relevant to any hearing on ITAAC under 10 CFR 52.103) before initial operation. Second, they ensure that interested persons will have access to information on both completed and uncompleted ITAAC at a level of detail sufficient to address the AEA Section 189a(1)(B) threshold for requesting a hearing on acceptance criteria. See 72 FR 49352; August 28, 2007, at 49450 (second column).

    After completing the 2007 rulemaking, the NRC began developing guidance on the ITAAC closure process and the requirements under 10 CFR 52.99. In October 2009, the NRC issued regulatory guidance for the implementation of the revised 10 CFR 52.99 in RG 1.215, “Guidance for ITAAC Closure Under 10 CFR Part 52.” This RG endorsed guidance developed by the Nuclear Energy Institute (NEI) in NEI 08-01, “Industry Guideline for the ITAAC Closure Process Under 10 CFR part 52,” Revision 3, issued January 2009 (ADAMS Accession No. ML090270415).

    After considering information presented by industry representatives in a series of public meetings, the NRC realized that some additional implementation issues were left unaddressed by the various provisions in 10 CFR part 52. In particular, the NRC determined that the combined license holder should provide additional notifications to the NRC following the notification of ITAAC completion currently required by 10 CFR 52.99(c)(1). The NRC refers to the time after this ITAAC closure notification, but before the date the Commission makes the finding under 10 CFR 52.103(g), as the ITAAC maintenance period. Most recently, the NRC held two public meetings in March 2010 to discuss draft proposed rule text that it made available to the public in February 2010. The NRC considered feedback given from external stakeholders during those meetings in its development of this final rule. Finally, in March 2010, the NRC issued Inspection Procedure 40600, “Licensee Program for ITAAC Management,” which provides guidance to verify that licensees have implemented ITAAC maintenance programs to ensure that structures, systems, and components continue to meet the ITAAC acceptance criteria until the Commission makes the finding under 10 CFR 52.103(g) allowing operation.

    II. Comments on the Proposed Rule and Regulatory Guide

    A. Overview of Public Comments

    The NRC published a proposed rule on the Requirements for Maintenance of Inspections, Tests, Analyses and Acceptance Criteria in the Federal Register on May 13, 2011 (76 FR 27925). The period for submitting comments on the proposed ITAAC Maintenance rule closed on July 27, 2011. The associated draft regulatory guide for the proposed rule, RG 1.215 “Guidance for ITAAC Closure under 10 CFR Part 52” (DG-1250) was also published in the Federal Register on May 13, 2011 (76 FR 27924). The period for submitting comments on the draft guidance closed on July 25, 2011.

    Types of Comments

    The NRC received one public comment submission on the proposed rule containing 11 comments from one industry organization, NEI (ADAMS Accession No. ML11208C708). The NRC received one public comment submission, from NEI, containing 22 comments on the RG (ADAMS Accession No. ML11209C487). Comments on the proposed rule are discussed separately from the comments on the draft regulatory guide.

    B. Comments on the Proposed Rule

    There were two types of comments on the proposed rule:

    1. Comments that were general in nature to the proposed rule language.

    2. Comments that were specific in nature to the proposed rule supplementary information.

    The NEI submission contained two general comments on the proposed rule and nine specific comments on the proposed rule supplementary information. The NRC has carefully considered the public comments received during the comment period and is adopting a final rule that is substantially similar to the proposed rule with one change to § 52.99(e)(2). The NEI generally supported the approach and objective of the proposed rule and the associated regulatory guidance.

    Comment Identification Format

    All comments are identified uniquely by using the formation [Comment X, p. Y] where [Comment X] represents the sequential comment number and [p. Y] represents the comment submission page number.

    1. General Comments Regarding the Proposed Rule Language

    Comment: Section 52.99(e)(1) should be revised to state, “* * * the NRC staff's determination [deleted: of the successful completion of] [added: that] inspections, tests, and analyses contained in the license have been successfully completed [added: and, based solely thereon, that the prescribed acceptance criteria are met].” (Comment 1, p.1)

    NRC Response: The NRC does not agree with this comment. The change that NEI proposes is not within the scope of this rulemaking, as it does not address the issues of ITAAC maintenance (including public awareness of significant changes to the bases of licensee notifications under § 52.99). In addition, NEI proposed this change as part of a set of changes in their comment submission on the 2006 proposed part 52 rule (ML011100405). In the 2007 rulemaking revising part 52, the NRC declined to make the NEI-proposed change. See 72 FR 49352, 49385 (August 28, 2007). The NEI does not present any new arguments that would cause the NRC to change its 2007 position rejecting the NEI proposal. No Start Printed Page 51882changes to the final rule language were made as a result of this comment.

    Comment: The NRC should clarify in the final rule the relationship between paragraphs (c) and (g) of § 52.103, to account for the possibility of interim operation. (Comment 11, p.4)

    NRC Response: The NRC disagrees with the comment, because the relationship between §§ 52.103(c) and (g) is outside the scope of this rulemaking, and Section 189b(1)(B)(iii) of the AEA clearly provides the Commission with authority to allow interim operation during a pending hearing on acceptance criteria. The NRC may address the subject of interim operation at a later time. No change was made to the final rule language as a result of this comment.

    2. Specific Comments Regarding the Proposed Rule Supplementary Information

    The nine specific comments received on the proposed rule contained recommendations for changes to the supplementary information to correctly reflect common terminology between the rule supplementary information, the associated RG 1.215 and the industry guidance contained within Revision 4 of NEI 08-01 (ADAMS Accession No. ML102010051). These nine specific comments all addressed discussion in the statement of considerations (SOC) (the SUPPLEMENTARY INFORMATION section of the Federal Register notice of proposed rulemaking); therefore no changes to the final rule language were made as a result of these comments. The SOC for the final rule reflects the NRC consideration of these nine comments.

    Comment: The phrase “ITAAC closure package” should be replaced with the phrase “ITAAC completion package” in Section III. A, 3d bullet (76 FR 27927) so that the SOC uses terminology which is consistent with that in the associated draft regulatory guide and industry guidance. (Comment 2, p.2)

    NRC Response: The NRC agrees with the comment. The SOC for the final rule uses the phrase, “ITAAC completion package.”

    Comment: Delete the second sentence in Section III.B paragraph beginning “When making * * *” to maintain a consistent description of the content of 52.99(c)(1) notifications in the associated draft regulatory guide and industry guidance. (Comment 3, p.2)

    NRC Response: The NRC agrees with the comment. The SOC for the final rule deleted the sentence “The licensee's summary statement of the basis for resolving the issue which is the subject of the notification, a discussion of any action taken, and a list of the key licensee documents supporting the resolution and its implementation, would assist the NRC in making its independent evaluation of the issue” to agree with the RG 1.215 and the industry guidance contained within Revision 4 of NEI 08-01.

    Comment: Add the term “maintenance” to the list of permissible activities that may be in progress at the time of the 10 CFR 52.103(g) finding. (Comment 4, p.2)

    NRC Response: The NRC agrees with the comment, because it reflects the intent of the rule and the guidance. The SOC for the final rule added the term “maintenance” to the activities that are allowable during the time of the Commission's 10 CFR 52.103(g) finding if the programs credited with maintaining the validity of completed ITAAC guide those activities and the activities are not so significant as to exceed a threshold for reporting.

    Comment: Delete “The NRC understands that the nuclear power industry believes * * *” in Section III.B First paragraph under heading “ITAAC Closure Documentation” because the language is unnecessary. (Comment 5, p.2)

    NRC Response: The NRC agrees with the comment, because the language is unnecessary. The SOC for the final rule deleted the phrase “The NRC understands that the nuclear power industry believes * * *” from the sentence.

    Comment: Revise Section III.C for clarity by replacing the text that reads “In both cases, if the presiding officer's decision resolves the contention favorably * * *” with “In both cases, if the presiding officer finds that the contested acceptance criteria have been met * * *” (Comment 6, p.3)

    NRC Response: The NRC agrees that the sentence should be revised for clarity, but the SOC will use the phrase “have been or will be met” to reflect both types of possible presiding officer findings. The SOC for the final rule was changed to “In both cases, if the presiding officer finds that the contested acceptance criteria have been or will be met, this does not obviate the need for the Commission to make the required finding under Section 185b of the AEA and 10 CFR 52.103(g) that the acceptance criteria are met.” This change is consistent with similar language in Section IV of the supplementary information section.

    Comment: Add the phrase “* * * on contested acceptance criteria.” to clarify what decision by the presiding officer the paragraph is referencing. (Comment 7, p.3)

    NRC Response: The NRC agrees with the comment. The final rule SOC now reads as follows: “The phrase `otherwise able to make' conveys the NRC's determination that the Commission's process for supporting a Commission finding on uncontested acceptance criteria is unrelated to and unaffected by the timing of the presiding officer's initial decision on contested acceptance criteria.”

    Comment: Replace the term “must” with the term “should” to reflect that ITAAC Maintenance documentation and recordkeeping is an expectation and not a requirement. (Comment 8, p.3)

    NRC Response: The NRC agrees with the comment. The final rule SOC uses the term “should” to reflect expectations regarding documentation and recordkeeping in support of ITAAC post-closure notifications. However, as explained below, regulatory provisions such as 10 CFR part 50, “Domestic Licensing of Production and Utilization Facilities,” Appendix B, “Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants,” require the preparation and retention of records supporting the vast majority of ITAAC processes, including the activities supporting the notifications that are required by this final rule.

    Comment: The comment requested the addition of a sentence stating the NRC proposed no changes to Section IV, Subsection on § 52.99(d). (Comment 9, p.3)

    NRC Response: The NRC does not agree with this comment. The first sentence of § 52.99(d)(1) contains the following change. “In the event that an activity is subject to an ITAAC derived from a referenced standard design certification and the licensee has not demonstrated that the prescribed acceptance criteria [deleted: has been] [added: are] met, the licensee may take corrective actions to successfully complete that ITAAC or request an exemption from the standard design certification ITAAC, as applicable.” In addition, 52.99(d)(2) was also changed as follows: “In the event that an activity is subject to an ITAAC not derived from a referenced standard design certification and the licensee has not demonstrated that the prescribed acceptance criteria [deleted: has been] [added: are] met, the licensee may take corrective actions to successfully complete that ITAAC or request a license amendment under 10 CFR 52.98(f).”

    Comment: Delete the phrase “and detailed” when referring to licensee notifications required by § 52.99(c) for consistency with Section IV.B (Comment 10, p.4)Start Printed Page 51883

    NRC Response: The NRC agrees with this comment. In the final rule SOC the phrase “and detailed” was deleted. The sentence now reads, “In general, the NRC expects to make the paragraph (c) notifications available shortly after the NRC has received the notifications and concluded that they are complete.” The accompanying detail necessary for the ITAAC notifications under paragraph (c) is developed in regulatory guidance, RG 1.215. This change is consistent with the last paragraph in Section III.B of the SUPPLEMENTARY INFORMATION.

    C. Comments on the Draft Regulatory Guide DG-1250/RG 1.215

    The NRC published the draft regulatory guide for the proposed rule, RG 1.215, “Guidance for ITAAC Closure Under 10 CFR Part 52” (DG-1250) in the Federal Register on May 13, 2011 (76 FR 27924). The period for submitting comments on the draft guidance closed on July 25, 2011.

    The NRC received 1 public comment submission on the regulatory guide containing 25 comments from 1 industry organization, NEI (ADAMS Accession No. ML11209C487). The NRC's responses to the public comments are contained in “Response to Public Comments on Draft Regulatory Guide DG-1250 proposed Revision 1 of RG 1.215, `Guidance for ITAAC Closure Under 10 CFR Part 52'” (ADAMS Accession No. ML11284A006).

    III. Discussion

    The NRC is requiring the following new notifications with respect to ITAAC closure:

    • ITAAC post-closure notification, and
    • All ITAAC complete notification.

    In general, the reasons for these new notifications are analogous to the reasons presented in the 2007 rulemaking for the existing 10 CFR 52.99(c) notifications: (1) To ensure that the NRC has sufficient information, in light of new information developed or identified after the ITAAC closure notification under 10 CFR 52.99(c)(1), to complete all of the activities necessary for the NRC to make a determination on ITAAC; and (2) to ensure that interested persons have access to information on ITAAC at a level of detail sufficient to address the AEA Section 189a(1)(B) threshold for requesting a hearing. After evaluating the various means of ensuring that the Commission has sufficient information to make a determination on ITAAC, and that interested persons have access to sufficient ITAAC information, the NRC has provided a rule augmented by guidance. The details of timing and content of the new notifications are captured in guidance that was issued for public comment simultaneously with the proposed rule, as discussed in more detail in Section V, “Availability of Regulatory Guidance,” of this document. The NRC believes that this approach allows more flexibility to adjust the guidance based on lessons learned during early implementation of the ITAAC process under the first combined licenses. Based upon the NRC's experience with the overall NRC oversight and verification of ITAAC, the notification provisions of the rule, the ITAAC hearing process, and the process for making the 10 CFR 52.103(g) finding, the NRC may revise and supplement the final guidance on the timing and content of notifications. The NRC notes that it would not rely solely on the existence of this rulemaking as a primary basis for the 10 CFR 52.103(g) finding. Rather, the NRC would use a holistic review using results from the NRC's construction inspection program and ITAAC closure review process as primary factors supporting a conclusion that the acceptance criteria in the combined license are met.

    Each of the notification requirements in this rulemaking, and the bases for each of the requirements, are described in Section III.B, “Additional ITAAC Notifications,” of this document. The NRC also included several editorial changes to 10 CFR 52.99 in paragraphs (b), (c)(1), final (c)(3) (former (c)(2)), and (d)(1). In all of these cases, the NRC is replacing the phrase “acceptance criteria have been met” with the phrase “acceptance criteria are met” for consistency with the wording of the requirement in 10 CFR 52.103(g) on the Commission's ITAAC finding, which is derived directly from wording in the AEA. In addition, the NRC changed 10 CFR 52.99(d)(2) to replace the phrase “ITAAC has been met” with the phrase “prescribed acceptance criteria are met” for consistency with the wording in 10 CFR 52.99(d)(1).

    A. Licensee Programs That Maintain ITAAC Conclusions

    One essential element in ensuring the maintenance of successfully completed ITAAC involves the use of established licensee programs such as the Quality Assurance Program, Problem Identification and Resolution Program, Maintenance/Construction Program, and Design and Configuration Management Program. Each program credited with supporting the maintenance of completed ITAAC should contain attributes that maintain the validity of the ITAAC determination basis. These program attributes include the following:

    • Licensee screening of activities and events for impact on ITAAC;
    • Licensee determination of whether supplemental ITAAC notification is required; and
    • Licensee supplementation of the ITAAC completion package, as appropriate, to demonstrate that the acceptance criteria continue to be met.

    The NRC expects these programs to be fully implemented and effective before the licensee takes credit for them as an appropriate means of supporting ITAAC maintenance. These programs will be subject to NRC inspection.

    B. Additional ITAAC Notifications

    ITAAC Post-Closure Notification

    The first new notification is contained in 10 CFR 52.99(c)(2), “ITAAC post-closure notifications,” and would be required following the licensee's ITAAC closure notifications under 10 CFR 52.99(c)(1) until the Commission makes the finding under 10 CFR 52.103(g). This provision in 10 CFR 52.99(c)(2) would require the licensee to provide the NRC with timely notification of new information materially altering the basis for determining that either inspections, tests, or analyses were performed as required, or that acceptance criteria are met (referred to as the ITAAC determination basis).

    The licensee is responsible for maintaining the validity of the ITAAC conclusions after completion of the ITAAC. If the ITAAC determination basis is materially altered, the licensee is expected to notify the NRC. Through public workshops and stakeholder interaction, the NRC developed thresholds to identify when activities would materially alter the basis for determining that a prescribed inspection, test, or analysis was performed as required, or finding that a prescribed acceptance criterion is met. One obvious case is that a notification under paragraph (c)(2) is required to correct a material error or omission in the original ITAAC closure notification. The “materially altered determination” is further developed in RG 1.215 and in the industry guidance in NEI 08-01, Revision 4.

    Section 52.6, “Completeness and accuracy of information,” paragraph (a), requires that information provided to the Commission by a licensee be complete and accurate in all material respects. However, it might be the case that the original closure notification was complete and accurate when sent, but subsequent events materially alter the ITAAC determination basis. Also, a Start Printed Page 51884material error or omission might not be discovered until after the ITAAC closure notification is sent. It is possible that new information materially altering the ITAAC determination basis would not rise to the reporting threshold under 10 CFR 52.6(b). As required by 10 CFR 52.6(b), licensees must notify the Commission of information identified by the licensee as having, for the regulated activity, a significant implication for public health and safety or the common defense and security. Given the primary purpose of ITAAC—to verify that the plant has been constructed and will be operated in compliance with the approved design—the NRC believes that it cannot rely on the provisions in 10 CFR 52.6 for licensee reporting of new information materially altering the ITAAC determination basis. The reasons for this conclusion are as follows:

    1. Material errors and omissions in ITAAC closure notifications, relevant to the accuracy and completeness of the documented basis for the Commission's finding on ITAAC, may nonetheless be determined in isolation by a licensee as not having a significant implication for public health and safety or common defense and security.

    2. A Commission finding of compliance with acceptance criteria in the ITAAC at the time of the finding is required, under Section 185b of the AEA, in order for the combined license holder to commence operation.

    3. The addition of specific reporting requirements addressing information relevant and material to the ITAAC finding ensures that the NRC will get the necessary reports as a matter of regulatory requirement and allows the NRC to determine the timing and content of these reports so that they serve the regulatory needs of the NRC.

    Therefore, the NRC intends that these issues will be reported under 10 CFR 52.99(c)(2). In addition to the reporting of material errors and omissions, the NRC has identified other circumstances in which reporting under this provision would be required (i.e., reporting thresholds). These reporting thresholds are described in more detail in Section IV, “Section-by-Section Analysis,” of this document.

    When making the 10 CFR 52.103(g) finding, the NRC must have sufficient information to determine that the relevant acceptance criteria are met despite the new information prompting the notification under paragraph (c)(2). Apart from the NRC's use of the information, the NRC also believes that public availability of such information is necessary to ensure that interested persons will have sufficient information to review when preparing a request for a hearing under 10 CFR 52.103, comparable to the information provided under paragraph (c)(1), as described in the Statement of Considerations for the 2007 part 52 rulemaking. See August 28, 2007; 72 FR 49352, at 49384 (second and third columns). Accordingly, the NRC requires that after a licensee identifies new information materially altering the ITAAC determination basis, the licensee must then submit what is essentially a “resolution” notification to the NRC in the form of an ITAAC post-closure notification. The ITAAC post-closure notification, described in paragraph (c)(2), requires the licensee to submit a written notification of the resolution of the circumstances surrounding the identification of new information materially altering the ITAAC determination basis. The ITAAC post-closure notification must contain sufficient information demonstrating that, notwithstanding the information that prompted notification, the prescribed inspections, tests, and analyses have been performed as required and the prescribed acceptance criteria are met. The ITAAC post-closure notifications should explain the need for the notification, outline the resolution of the issue, and confirm that the ITAAC acceptance criteria continue to be met. The ITAAC post-closure notifications must include a level of detail similar to the level of information required in initial ITAAC closure notifications under 10 CFR 52.99(c)(1).

    Section 52.99(c)(2) states that licensees must make the notification “in a timely manner.” Further discussion of what the NRC considers “timely” can be found in the NRC guidance being issued simultaneously with this final rule, as discussed in more detail in Section V, “Availability of Regulatory Guidance,” of this document.

    The NRC provides that the notification be available for public review under paragraph (e)(2). This helps ensure public availability and accessibility of important information on ITAAC closure. Further explanation of the basis for the availability requirement is presented under the discussion on 10 CFR 52.99(e)(2) in Section IV, “Section-by-Section Analysis,” of this document.

    Events that affect completed ITAAC could involve activities that include, but are not limited to, maintenance and engineering programs, or design changes. The NRC expects that licensees will carry out these activities under established programs to maintain ITAAC conclusions and that no post-closure notification will be necessary in most instances. The NRC can have confidence that prior ITAAC conclusions are maintained, as long as the ITAAC determination basis established by the original ITAAC closure notification is not materially altered. If the ITAAC determination basis is not materially altered, then licensee activities will remain below the notification threshold of 10 CFR 52.99(c)(2). If the ITAAC determination basis is materially altered, then the licensee is required to notify the NRC under 10 CFR 52.99(c)(2).

    Although the NRC is requiring that licensees notify the NRC of information materially altering the ITAAC determination basis only after the licensee has evaluated and resolved the issue prompting the notification, the NRC encourages licensees to communicate with the NRC early in its evaluation process. The purpose of this early communication would be to alert the NRC staff to the fact that additional activities may be scheduled that affect a structure, system, or component (including physical security hardware) or program element for which one or more ITAAC have been closed. This will allow the NRC inspection staff to discuss the licensee's plans for resolving the issue to determine if the staff wants to observe any of the upcoming activities for the purpose of making a future staff determination about whether the acceptance criteria for those ITAAC continue to be met.

    All ITAAC Complete Notification

    Another notification that the NRC is requiring is the “all ITAAC complete” notification under 10 CFR 52.99(c)(4). The purpose of this notification is to facilitate the required Commission finding under 10 CFR 52.103(g) that the acceptance criteria in the combined license are met. After, or concurrent with, the last ITAAC closure notification required by 10 CFR 52.99(c)(1), the licensee is required to notify the NRC that all ITAAC are complete. When the licensee submits the all ITAAC complete notification, the NRC would expect that all activities requiring ITAAC post-closure notifications have been completed and that the associated ITAAC determination bases have been updated.

    To support the Commission's finding under 10 CFR 52.103(g) that the acceptance criteria in the combined license are met, the NRC staff will, if and when appropriate, send a recommendation to the Commission to make a finding that all of the specified acceptance criteria are met. The staff will consider that all acceptance criteria “are met” if both of the following conditions hold:Start Printed Page 51885

    • All ITAAC were verified to be met at one time; and
    • The licensee provides confidence, in part through the notifications in 10 CFR 52.99(c), that the ITAAC determination bases have been maintained and the ITAAC acceptance criteria continue to be met; and the NRC has no reasonable information to the contrary.

    This approach will allow licensees to have ITAAC-related structures, systems, or components, or security or emergency preparedness related hardware, undergoing maintenance or certain other activities at the time of the 10 CFR 52.103(g) finding, if the programs credited with maintaining the validity of completed ITAAC guide those activities and the activities are not so significant as to exceed a threshold for reporting. If a reporting threshold has been exceeded, then the NRC would need to evaluate the licensee's ITAAC post-closure notification to determine whether the ITAAC continue to be met. Reporting thresholds are discussed in more detail in Section IV, “Section-by-Section Analysis,” of this document.

    ITAAC Closure Documentation

    This final rule does not contain specific ITAAC documentation and record retention requirements. Consistent with regulatory provisions such as 10 CFR part 50, “Domestic Licensing of Production and Utilization Facilities,” Appendix B, “Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants,” licensees are expected to prepare and retain records supporting the vast majority of ITAAC processes, including the activities supporting the notifications that are required by this final rule. Accordingly, the NRC has not included specific documentation and record retention requirements in this final rule. If the NRC inspections disclose substantial issues with licensees' records on ITAAC maintenance, the NRC will revisit the need for explicit documentation and record retention requirements on ITAAC maintenance.

    NRC Inspection, Publication of Notices, and Availability of Licensee Notifications

    Section 52.99(e)(1) requires that the NRC publish in the Federal Register the NRC staff's determination of the successful completion of inspections, tests, and analyses, at appropriate intervals until the last date for submission of requests for hearing under 10 CFR 52.103(a). Section 52.99(e)(2) currently provides that the NRC shall make publicly available the licensee notifications under current paragraphs (c)(1) and (c)(2). The NRC has revised paragraph (e)(2) to cover all notifications under 10 CFR 52.99(c). In general, the NRC expects to make the paragraph (c) notifications available shortly after the NRC has received the notifications and concluded that they are complete. Furthermore, by the date of the Federal Register notice of intended operation and opportunity to request a hearing on whether acceptance criteria are met (under 10 CFR 52.103(a)), the NRC will make available the licensee notifications under paragraphs (c)(1), (c)(2), and (c)(3) that it has received to date.

    C. Conforming Changes to 10 CFR 2.340

    The 2007 10 CFR part 52 rulemaking amended 10 CFR 2.340, “Initial decision in certain contested proceedings; immediate effectiveness of initial decisions; issuance of authorizations, permits, and licenses,” to clarify, among other things, the scope of the presiding officer's decision in various kinds of NRC proceedings, and remove the requirement for direct Commission involvement in all production and utilization facility licensing proceedings.

    Section 2.340(j) was intended to address these matters in connection with the Commission finding on acceptance criteria and any associated hearing under 10 CFR 52.103. In the course of developing this final rule, the NRC determined that 10 CFR 2.340(j) contains several inconsistencies with the statutory language in Section 185b of the AEA, and could more clearly describe possible ways in which a presiding officer decision may lead to a Commission decision on acceptance criteria. The changes, together with the bases for the changes, are described in the following paragraphs.

    Section 2.340(j) currently states that the Commission makes a finding under 10 CFR 52.103(g) that acceptance criteria “have been or will be met.” This is incorrect; the Commission's finding under 10 CFR 52.103(g) is that the acceptance criteria “are met,” which is the statutory requirement under Section 185b of the AEA. To correct this error, the NRC has amended the introductory language of 10 CFR 2.340(j) to use the correct phrase, “acceptance criteria * * * are met * * *.”

    In addition, 10 CFR 2.340(j), as currently written, does not distinguish among the various circumstances in a contested proceeding where a presiding officer's decision (that acceptance criteria have been met, or will be met) is followed by the overall finding under 10 CFR 52.103(g) that acceptance criteria are met (as required by Section 185b of the AEA). It is not clear from the current language of § 2.340(j) that the presiding officer's initial decision on a contention that acceptance criteria have been met or will be met, does not obviate the need for the Commission (or the appropriate Director) to make the required finding (under Section 185b of the AEA and 10 CFR 52.103(g)) that the acceptance criteria are met. To illustrate this point by counter example, the presiding officer could make, in the initial decision, a “predictive finding” that acceptance criteria “will be met.” Thereafter, the combined license holder would complete the prescribed inspection, test and/or analysis and inform the NRC under § 52.99 that the acceptance criteria have been met. Nonetheless, the Commission (or the appropriate Director) may determine—based on, inter alia, information submitted to the NRC under 10 CFR 52.99 after the hearing record had closed and the presiding officer's initial decision on the contention is made—that the presiding officer's “predictive finding” was not borne out by events and that the acceptance criteria are not met. To clarify some of the possible paths that the Commission (or appropriate Director) could follow (after the presiding officer's initial decision) in making a finding that acceptance criteria are met, the NRC is revising the language of paragraph (j), thereby making clear that the presiding officer's decision on a contested matter is separate from the overall Commission finding under Section 185b and 10 CFR 52.103(g) that acceptance criteria are met.

    IV. Section-by-Section Analysis

    The primary changes on ITAAC maintenance by the NRC in this rulemaking are to 10 CFR 52.99. The changes to 10 CFR 2.340 are corrections.

    Section 2.340 Initial Decision in Certain Contested Proceedings; Immediate Effectiveness of Initial Decisions; Issuance of Authorizations, Permits and Licenses

    Section 2.340(j) Issuance of Finding on Acceptance Criteria Under 10 CFR 52.103

    Paragraph (j) was amended to allow the Commission (or the appropriate NRC Office Director) in a contested proceeding to make the finding under 10 CFR 52.103(g) that the acceptance criteria in a combined license are met, under certain circumstances that are delineated in greater detail in paragraphs (j)(1) through (4). This compares with the current rule, which Start Printed Page 51886contains only two paragraphs, (j)(1) and (2). The matters covered by paragraph (j)(1) of the current rule are described with greater clarity in paragraphs (j)(1) through (3).

    Paragraph (j)(1) clarifies that the Commission may not make the overall 10 CFR 52.103(g) finding unless it is otherwise able to find that all uncontested acceptance criteria (i.e., “acceptance criteria not within the scope of the initial decision of the presiding officer”) are met. The phrase “otherwise able to make” conveys the NRC's determination that the Commission's process for supporting a Commission finding on uncontested acceptance criteria is unrelated to and unaffected by the timing of the presiding officer's initial decision on contested acceptance criteria.

    Paragraph (j)(2) clarifies that a presiding officer's initial decision, which finds that acceptance criteria have been met, is a necessary, but not sufficient prerequisite for the Commission to make a finding that the contested acceptance criteria (i.e., the criteria that are the subject of the presiding officer's initial decision) are met. The Commission must thereafter—even if the presiding officer's initial decision finds that the contested acceptance criteria have been met—be able to make a finding that the contested criteria are met after considering: 1) information submitted in the licensee notifications pursuant to 10 CFR 52.99, and 2) the NRC staff's findings, with respect to these notifications, to issue the overall 10 CFR 52.103 finding. By using the word “thereafter,” the NRC intends to emphasize that the Commission would not make a finding that contested acceptance criteria are met in advance of the presiding officer's initial decision on those acceptance criteria.

    Paragraph (j)(3) expresses the same concept as paragraph (j)(2), but as applied to findings that acceptance criteria will be met. Thus, even if a presiding officer's initial decision finds that the contested acceptance criteria will be met, the Commission must thereafter be able to make a finding that the contested criteria are met after considering: (1) Information submitted in an ITAAC closure notification pursuant to 10 CFR 52.99(c)(1); 2) information submitted in the licensee notifications pursuant to 10 CFR 52.99(c)(2) and (c)(4); and 3) the NRC staff's findings with respect to such notifications, to issue the overall 10 CFR 52.103 finding.

    Paragraph (j)(4) is the same as the existing provision in 10 CFR 2.340(j)(2). This paragraph provides that the Commission may make the 10 CFR 52.103(g) finding notwithstanding the pendency of a petition for reconsideration under 10 CFR 2.345, a petition for review under 10 CFR 2.341, a motion for a stay under 10 CFR 2.342, or a petition under 10 CFR 2.206.

    The NRC notes that 10 CFR 2.340(j) is not intended to be an exhaustive “roadmap” to a possible 10 CFR 52.103(g) finding that acceptance criteria are met. For example, this provision does not directly address what must occur for the Commission to make a 10 CFR 52.103(g) finding where the presiding officer finds, with respect to a contention, that acceptance criteria have not been or will not be met. The NRC also notes that this provision applies only to contested proceedings. If there is no hearing under 10 CFR 52.103 or if the hearing ends without a presiding officer's initial decision on the merits (e.g., a withdrawal of the sole party in a proceeding), then 10 CFR 2.340(j) does not govern the process by which the Commission (or the appropriate staff Office Director) makes the 10 CFR 52.103(g) finding.

    Section 52.99 Inspection During Construction; ITAAC Schedules and Notifications; NRC Notices

    Although the NRC is not making changes to every paragraph under 10 CFR 52.99, for simplicity, this rulemaking would replace the section in its entirety. Therefore, the NRC is providing a section-by-section discussion for every paragraph in 10 CFR 52.99. For those paragraphs where little or no change is being proposed, the NRC is repeating the section-by-section discussion from the 2007 major revision to 10 CFR part 52 with editorial and conforming changes, as appropriate.

    The purpose of this section is to present the requirements to support the NRC's inspections during construction, including requirements for ITAAC schedules and notifications and for NRC notices of ITAAC closure. The title of this section was changed from Inspection during construction to Inspections during construction; ITAAC schedules and notifications; NRC Notices to reflect the contents of this section.

    Section 52.99(a) Licensee Schedule for Completing Inspections, Tests, or Analyses

    The NRC is not making any changes to § 52.99(a). Paragraph (a) requires that the licensee submit to the NRC, no later than 1 year after issuance of the combined license or at the start of construction as defined at 10 CFR 50.10, whichever is later, its schedule for completing the inspections, tests, or analyses in the ITAAC. This provision also requires the licensee to submit updates to the ITAAC schedule every 6 months thereafter and, within 1 year of its scheduled date for initial loading of fuel, licensees must submit updates to the ITAAC schedule every 30 days until the final notification is provided to the NRC under § 52.99(c)(1). The information provided by the licensee will be used by the NRC in developing the NRC's inspection activities and activities necessary to support the Commission's finding whether all of the ITAAC are met prior to the licensee's scheduled date for fuel load. Even in the case where there were no changes to a licensee's ITAAC schedule during an update cycle, the NRC expects the licensee to notify the NRC that there have been no changes to the schedule.

    Section 52.99(b) Licensee and Applicant Conduct of Activities Subject to ITAAC

    The NRC is making an editorial change to the last sentence of § 52.99(b) to replace the words “have been met” with “are met” for consistency with the requirements of Section 185b of the AEA, as implemented in 10 CFR 52.103(g). The purpose of the requirement in 10 CFR 52.99(b) is to clarify that an applicant may proceed at its own risk with design and procurement activities subject to ITAAC, and that a licensee may proceed at its own risk with design, procurement, construction, and preoperational testing activities subject to an ITAAC, even though the NRC may not have found that any particular ITAAC are met.

    Section 52.99(c) Licensee Notifications

    Section 52.99(c)(1) ITAAC Closure Notification and § 52.99(c)(3) Uncompleted ITAAC Notification

    The NRC has made editorial changes in § 52.99(c)(1) to replace the words “have been met” with “are met.” Section 52.99(c)(1) requires the licensee to notify the NRC that the prescribed inspections, tests, and analyses have been performed and that the prescribed acceptance criteria are met. Section 52.99(c)(1) further requires that the notification contain sufficient information to demonstrate that the prescribed inspections, tests, and analyses have been performed and that the prescribed acceptance criteria are met.

    The NRC has renumbered current § 52.99(c)(2) as paragraph (c)(3). In addition, the NRC has made an editorial change to the last sentence in final § 52.99(c)(3) (former 10 CFR 52.99(c)(2)) Start Printed Page 51887to replace the words “have been met” with “are met.” Section 52.99(c)(3) requires that, if the licensee has not provided, by the date 225 days before the scheduled date for initial loading of fuel, the notification required by paragraph (c)(1) of this section for all ITAAC, then the licensee shall notify the NRC that the prescribed inspections, tests, or analyses for all uncompleted ITAAC will be performed and that the prescribed acceptance criteria will be met prior to operation (consistent with the AEA Section 185b requirement that the Commission, “prior to operation,” find that the acceptance criteria in the combined license are met). The notification must be provided no later than the date 225 days before the scheduled date for initial loading of fuel, and must provide sufficient information to demonstrate that the prescribed inspections, tests, or analyses will be performed and the prescribed acceptance criteria for the uncompleted ITAAC will be met.

    Section 52.99(c) ensures that: (1) The NRC has sufficient information to complete all of the activities necessary for the Commission to make a finding as to whether all of the ITAAC are met prior to initial operation, and (2) interested persons will have access to information on both completed and uncompleted ITAAC at a level of detail sufficient to address the AEA Section 189a(1)(B) threshold for requesting a hearing on acceptance criteria. It is the licensee's burden to demonstrate compliance with the ITAAC, and the NRC expects the information submitted under paragraph (c)(1) to contain more than just a simple statement that the licensee believes the ITAAC has been completed and the acceptance criteria met. The NRC would expect the notification to be sufficiently complete and detailed so that a reasonable person could understand the basis for the licensee's representation that the inspections, tests, and analyses have been successfully completed and the acceptance criteria are met. The term “sufficient information” would require, at a minimum, a summary description of the basis for the licensee's conclusion that the inspections, tests, or analyses have been performed and that the prescribed acceptance criteria are met.

    Furthermore, with respect to uncompleted ITAAC, it is the licensee's burden to demonstrate that it will comply with the ITAAC, and the NRC would expect the information that the licensee submits under proposed paragraph (c)(3) to be sufficiently detailed so that the NRC staff can determine what activities it will need to undertake to determine if the acceptance criteria for each of the uncompleted ITAAC are met, once the licensee notifies the NRC that those ITAAC have been successfully completed and their acceptance criteria met. The term “sufficient information” requires, at a minimum, a summary description of the basis for the licensee's conclusion that the inspections, tests, or analyses will be performed and that the prescribed acceptance criteria will be met. In addition, “sufficient information” includes, but is not limited to, a description of the specific procedures and analytical methods to be used for performing the inspections, tests, and analyses and determining that the acceptance criteria are met.

    The NRC notes that, even though it did not include a provision requiring the completion of all ITAAC by a certain time prior to the licensee's scheduled fuel load date, the NRC staff will require some period of time to perform its review of the last ITAAC once the licensee submits its notification that the ITAAC has been successfully completed and the acceptance criteria met. In addition, the Commission itself will require some period of time to perform its review of the staff's conclusions regarding all of the ITAAC and the staff's recommendations regarding the Commission finding under 10 CFR 52.103(g).

    Section 52.99(c)(2) ITAAC Post-Closure Notifications

    The NRC has added a new paragraph (c)(2) that would require the licensee to notify the NRC, in a timely manner, of new information that materially alters the basis for determining that either inspections, tests, or analyses were performed as required, or that acceptance criteria are met. The notification must contain sufficient information to demonstrate that, notwithstanding the new information, the prescribed inspections, tests, or analyses have been performed as required, and the prescribed acceptance criteria are met. Fundamentally, those circumstances requiring notification under proposed paragraph (c)(2) fall into the following two categories:

    • The information presented or referenced in the original 10 CFR 52.99(c)(1) notification is insufficient, either because it omits material information, or because the information is materially erroneous or incorrect, and the licensee discovers or determines there is a material omission or error after filing the original 10 CFR 52.99(c)(1) notification.
    • The information presented or referenced in the original 10 CFR 52.99(c)(1) notification was complete (i.e., not omitting material information) and accurate (i.e., not materially erroneous), but there is new material information with respect to the subject of the original 10 CFR 52.99(c)(1) notification.

    The term “materially altering” refers to situations in which there is information not contained in the 10 CFR 52.99(c)(1) notification that “has a natural tendency or capability to influence an agency decision maker” in either determining whether the prescribed inspection, test, or analysis was performed as required, or finding that the prescribed acceptance criterion is met. See Final Rule; Completeness and Accuracy of Information, December 31, 1987; 52 FR 49362, at 49363. Applying this concept in the context of 10 CFR 52.99(c), information for which notification would be required under paragraph (c)(2) is that information which, considered by itself or when considered in connection with information previously submitted or referenced by the licensee in a paragraph (c)(1) notification, relates to information which is necessary for any of the following:

    • The licensee to assert that the prescribed inspections, tests, and analyses have been performed and the acceptance criteria are met;
    • The NRC staff to determine if (and provide a recommendation to the Commission as to whether) the prescribed inspections, tests, and analyses were performed and the acceptance criteria are met; or
    • The Commission to find that the acceptance criteria are met, as required by Section 185b of the AEA and 10 CFR 52.103(g).

    The term “new information” falls into three categories:

    • New information (i.e., a “discovery” or new determination identified after the 10 CFR 52.99(c)(1) notification) about the accuracy of material information provided in, referenced by, or necessary to support representations made in that notification.
    • New information (i.e., a “discovery” or new determination identified after the 10 CFR 52.99(c)(1) notification) that previously existing information should have been, but was not provided, in the notification or referenced in the supporting documentation (i.e., an omission of material information).
    • Information on a “new” event or circumstance (i.e., an event or circumstance occurring after the 10 CFR 52.99(c)(1) notification) that materially affects the accuracy or completeness of the basis—as reported or relied upon in Start Printed Page 51888the § 52.99(c)(1) notification—for the licensee's representation that the acceptance criteria are met.

    Applying these concepts, the NRC believes that the circumstances for which reporting under this provision would be required include:

    • Material Error or Omission—Is there a material error or omission in the original ITAAC closure notification?
    • Post Work Verification (PWV)—Will the PWV use a significantly different approach than the original performance of the inspection, test, or analysis as described in the original ITAAC notification?
    • Engineering Changes—Will an engineering change be made that materially alters the determination that the acceptance criteria are met?
    • Additional Items To Be Verified—Will there be additional items that need to be verified through the ITAAC?
    • Complete and Valid ITAAC Representation—Will any other licensee activities materially alter the ITAAC determination basis?

    Additional guidance on implementing these reporting thresholds is contained in the revision to RG 1.215, being issued simultaneously with this final rule. This guidance is discussed further in Section V, “Availability of Regulatory Guidance,” of this document.

    Paragraph (c)(2) would require the licensee to submit an ITAAC post-closure notification documenting the resolution of the circumstances surrounding the identification of new material information. By “resolution,” the NRC means: (1) The completion of the licensee's technical evaluation of the issue and the determination as to whether the prescribed inspection, test, or analysis was performed as required; (2) licensee completion of any necessary corrective or supplemental actions; (3) licensee documentation of the issue and any necessary corrective or supplemental actions in order to bring the ITAAC determination basis up to date; and (4) ultimate licensee determination about whether the affected acceptance criteria continue to be met.

    The information provided in the notification should be at a level of detail comparable to the ITAAC closure notification under paragraph (c)(1). The dual purposes of the proposed paragraph (c)(2) notification, as described in Section III.B, “Additional ITAAC Notifications,” of this document, are comparable to the purposes of the ITAAC closure notification in paragraph (c)(1). Thus, the NRC believes that the considerations for the content of the ITAAC closure notification, as discussed in the final 2007 10 CFR part 52 rule, apply to the paragraph (c)(2) notifications. See 72 FR 49450; August 28, 2007 (second column). It is the licensee's burden to demonstrate compliance with the ITAAC, taking into account any new information that materially alters the determination that a prescribed inspection, test, or analysis was performed as required or that a prescribed acceptance criterion is met. The NRC expects the paragraph (c)(2) notification to contain more than just a simple statement that the licensee has concluded, despite the material new information, that the prescribed inspection, test, or analysis was performed as required and that a prescribed acceptance criterion is met. The NRC expects the notification to be sufficiently complete and detailed such that a reasonable person could understand the basis for the licensee's determination in the paragraph (c)(2) notification. The term “sufficient information” is comparable to the meaning given to that term in paragraph (c)(1), and requires, at a minimum, a summary description of the basis for the licensee's determination. In addition, “sufficient information” includes, but is not limited to, a description of the specific procedures and analytical methods used or relied upon to develop or support the licensee's determination. The paragraph (c)(2) notification must be in writing, and the records on which it is based should be retained by the licensee to support possible NRC inspection. Licensees should use the same process for submitting ITAAC post-closure notifications as would be used to submit initial ITAAC closure notifications. The NRC is issuing guidance on implementation of the requirements in proposed paragraph (c)(2), including the level of detail necessary to comply with the requirements of paragraph (c)(2), as discussed in Section V, “Availability of Regulatory Guidance,” of this document.

    Section 52.99(c)(4) All ITAAC Complete Notification

    The NRC has added a new paragraph (c)(4) which requires the licensee to notify the NRC that all ITAAC are complete (All ITAAC Complete Notification). When the licensee submits the all ITAAC complete notification, the NRC expects that all activities requiring ITAAC post-closure letters have been completed, that the associated ITAAC determination bases have been updated, and that all required notifications under paragraph (c)(2) have been made.

    Section 52.99(d) Licensee Determination of Non-Compliance With ITAAC

    The NRC has made editorial changes in § 52.99(d)(1) to replace the words “have been met” with, “are met” and in § 52.99(d)(2) to replace the phrase “ITAAC has been met” with the phrase “prescribed acceptance criteria are met.” Paragraph (d) states the options that a licensee will have in the event that it is determined that any of the acceptance criteria in the ITAAC are not met. If an activity is subject to an ITAAC derived from a referenced standard design certification and the licensee has not demonstrated that the ITAAC are met, then the licensee may take corrective actions to successfully complete that ITAAC or request an exemption from the standard design certification ITAAC, as applicable. A request for an exemption must also be accompanied by an application for a license amendment under 10 CFR 52.98(f). The NRC will consider and take action on the request for exemption and the license amendment application together as an integrated NRC action.

    Also, if an activity that is subject to an ITAAC not derived from a referenced standard design certification and the licensee has not demonstrated that the prescribed acceptance criteria are met, the licensee may take corrective actions to successfully complete that ITAAC or request a license amendment under 10 CFR 52.98(f).

    Section 52.99(e) NRC Inspection, Publication of Notices, and Availability of Licensee Notifications

    The final rule is substantially the same as the proposed rule with one change to § 52.99(e)(2) to clarify NRC notices to the public. The one language change made to the section, “NRC inspection, publication of notices, and availability of licensee notifications,” is to replace the language “The NRC shall make publicly available the licensee notifications under paragraphs (c)(1) through (4) of this section no later than the date of publication of the notice of intended operations required by 10 CFR 52.103(a)” with:

    “The NRC shall, no later than the date of publication of the notice of intended operation required by 10 CFR 52.103(a), make publicly available those licensee notifications under paragraph (c) of this section that have been submitted to the NRC at least seven (7) days before that notice.” The NRC will make public all paragraph (c) ITAAC notifications that were submitted to the NRC at least seven days before the date of publication of the notice of intended operation required by 10 CFR 52.103(a) Start Printed Page 51889which is, at a minimum, 180 days before the date scheduled for initial loading of fuel. The NRC recognizes that the licensee could submit ITAAC notifications required by paragraph (c) later than the date of publication of the notice of intended operation required by 10 CFR 52.103(a).

    V. Availability of Regulatory Guidance

    Concurrent with this final rule, the NRC is issuing Revision 1 to RG 1.215, “Guidance for ITAAC Closure Under 10 CFR Part 52.” Revision 1 of RG 1.215 was issued in draft form for public comment with a temporary identification as Draft Regulatory Guide, DG-1250 (76 FR 27924, May 13, 2011). This guidance series was developed to describe, and make available to the public, information such as methods that are acceptable to the NRC staff for implementing specific parts of the agency's regulations, techniques that the staff uses in evaluating specific problems or postulated accidents, and data that the staff needs in its review of applications for permits and licenses.

    In Revision 1 of RG 1.215, the NRC is endorsing Revision 4 to the existing industry ITAAC closure guidance in NEI 08-01, submitted to the NRC for endorsement on July 16, 2010 (Package ADAMS Accession No. ML102010076). The revised guidance is intended to provide an acceptable method by which licensees can implement the new requirements in this final rulemaking.

    The proposed final rule requirements for ITAAC maintenance and the draft RG 1.215 were presented to the Advisory Committee on Reactor Safeguards (ACRS) on December 1, 2011 (ADAMS Accession No. ML11342A075). The ACRS conclusion and recommendations were that: (1) The proposed ITAAC rule, “Requirements for Maintenance of Inspections, Tests, Analyses, and Acceptance Criteria,” meets the goal of ensuring maintenance of ITAAC validity and should be approved. (2) The approach in RG 1.215, Revision 1, for closing and maintaining ITAAC should be revised to include an assessment that ensures a change does not introduce unintended consequences. The assessment should also include an evaluation that confirms the original inspections, tests, and analyses and their acceptance criteria are still valid and assures the functionality originally intended. (3) After revision, RG 1.215, Revision 1, should be issued. The NRC agrees to clarify RG 1.215 and the following sentence is included in Section B, where the requirements of NEI 08-01, section 8 are discussed: “The design and configuration control program should include an assessment and evaluation that confirms that the ITAAC potentially affected by a proposed change are still valid and assures the functionality originally intended.”

    VI. Availability of Documents

    The NRC is making the documents identified in the following table available to interested persons through one or more of the following methods as indicated. To access documents related to this action, see the ADDRESSES section of this document.

    DocumentPDRWebADAMS
    SECY-12-0030, “Final Rule: Requirements for Maintenance of Inspections, Tests, Analyses, and Acceptance Criteria (RIN 3150-AI77)”XXML113390369
    Regulatory Analysis for Final Rule—Requirements for Maintenance of Inspections, Tests, Analyses, and Acceptance Criteria, January 2012XXML120100062
    Regulatory Analysis for Proposed Rule—Requirements for Maintenance of Inspections, Tests, Analyses, and Acceptance Criteria, February 2011XXML110040395
    ACRS Letter, Proposed Requirements for ITAAC (Inspections, Tests, Analyses, and Acceptance Criteria) Maintenance and Draft Final Regulatory Guide 1.215, “Guidance for ITAAC Closure Under 10 CFR Part 52XXML11342A075
    Staff Requirements Memorandum for SECY-10-0117, “Proposed Rule: Requirements for Maintenance of Inspections, Tests, Analyses, and Acceptance Criteria (RIN 3150-AI77),” February 4, 2011XXML110350185
    SECY-10-0117, “Proposed Rule: Requirements for Maintenance of Inspections, Tests, Analyses, and Acceptance Criteria (RIN 3150-AI77)”XXML101440146
    ITAAC Proposed Rule Federal Register NoticeXXML101440177
    Regulatory Analysis for Proposed Rule re ITAAC, May 2010ML101440359
    SECY-09-0119, “Staff Progress in Resolving Issues Associated with Inspections, Tests, Analyses and Acceptance Criteria,” August 26, 2009XXML091980372 (Package)
    SRM-M090922, “Staff Requirements—Periodic Briefing on New Reactor Issues—Progress in Resolving Issues Associated with Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC), 9:30 a.m., Tuesday, September 22, 2009, Commissioners' Conference Room, One White Flint North, Rockville, Maryland (Open To Public Attendance),” October 16, 2009XXML092890658
    Inspection Procedure 40600, “Licensee Program for ITAAC Management”XXML072530607
    Regulatory Guide 1.215, “Guidance for ITAAC Closure Under 10 CFR Part 52,” Revision 1, January 2012XXML112580018
    Regulatory Guide 1.215, “Guidance for ITAAC Closure Under 10 CFR Part 52,” Revision 0, October 31, 2009XXML091480076
    NEI Comments on ITAAC Maintenance Proposed RuleXXML11208C708
    NEI Comments on DG-1250 Guidance for ITAAC ClosureXXML11209C487
    Staff Responses to Public Comments on DG-1250ML11284A006
    NEI 08-01, “Industry Guideline for the ITAAC Closure Process Under 10 CFR part 52,” Revision 3, January 2009XXML090270415
    NEI 08-01, “Industry Guideline for the ITAAC Closure Process Under 10 CFR part 52,” Revision 4XXML102010076 (Package) ML102010051
    NEI Comments on NRC Plans to Amend Regulations Related to ITAAC MaintenanceXXML101300103
    Russell Bell Ltr. RE: Response to Nuclear Energy Institute on NRC Plans to Amend Regulations Related to ITAAC MaintenanceXXML101590526
    Draft Regulatory Guide DG-1250 (Proposed Revision 1 of Regulatory Guide 1.215), “Guidance for ITAAC Closure Under 10 CFR Part 52XXML102530401
    Start Printed Page 51890
    NUREG/BR-0058, “Regulatory Analysis Guidelines of the U.S. Nuclear Regulatory Commission,” Revision 4, September 2004XXML042820192

    VII. Plain Writing

    The Plain Writing Act of 2010 (Pub. L. 111-274) requires Federal agencies to write documents in a clear, concise, well-organized manner that also follows other best practices appropriate to the subject or field and the intended audience. The NRC has attempted to use plain language in promulgating this rule consistent with the Federal Plain Writing Act guidelines.

    VIII. Agreement State Compatibility

    Under the “Policy Statement on Adequacy and Compatibility of Agreement States Programs,” approved by the Commission on June 20, 1997, and published in the Federal Register (62 FR 46517; September 3, 1997), this rule is classified as compatibility “NRC.” Compatibility is not required for Category “NRC” regulations. The NRC program elements in this category are those that relate directly to areas of regulation reserved to the NRC by the AEA or the provisions of 10 CFR. Although an Agreement State may not adopt program elements reserved to the NRC, it may wish to inform its licensees of certain requirements via a mechanism that is consistent with the particular State's administrative procedure laws. Category “NRC” regulations do not confer regulatory authority on the State.

    IX. Voluntary Consensus Standard

    The National Technology Transfer and Advancement Act of 1995, Public Law 104-113, requires that Federal agencies use technical standards that are developed or adopted by voluntary consensus standards bodies unless using such a standard is inconsistent with applicable law or is otherwise impractical. The requirements in this rulemaking address procedural and information collection and reporting requirements necessary to support the NRC's regulatory activities on combined licenses under 10 CFR part 52, and to facilitate the NRC's conduct of hearings on ITAAC which may be held under Section 189 of the AEA. These requirements do not establish standards or substantive requirements with which combined license holders must comply. Thus, this rulemaking does not constitute establishment of a standard containing generally applicable requirements falling within the purview of the National Technology Transfer and Advancement Act and the implementing guidance issued by the Office of Management and Budget (OMB).

    X. Environmental Impact—Categorical Exclusion

    The NRC has determined that these amendments fall within the types of actions described as categorical exclusions under 10 CFR 51.22(c)(2) and (c)(3). Therefore, neither an environmental impact statement nor an environmental assessment has been prepared for this regulation.

    XI. Paperwork Reduction Act Statement

    This final rule contains new or amended information collection requirements that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These requirements were approved by OMB, approval number 3150-0151.

    The burden to the public for these information collections is estimated to average 22 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the information collection. Send comments on any aspect of these information collections, including suggestions for reducing the burden, to the Information Services Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail to INFOCOLLECTS.RESOURCE@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0151), Office of Management and Budget, Washington, DC 20503. You may also email comments to Chad_S_Whiteman@omb.eop.gov or comment by telephone at 202-395-4718.

    Public Protection Notification

    The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid OMB control number.

    XII. Regulatory Analysis

    The Commission has prepared a regulatory analysis on this final regulation. The analysis examines the costs and benefits of the alternatives considered by the Commission.

    The regulatory analysis is in ADAMS under Accession No. ML120100062.

    The regulatory analysis may also be viewed and downloaded electronically via the Federal rulemaking Web site at http://www.regulations.gov by searching on Docket ID NRC-2010-0012.

    The regulatory analysis examines the benefits and costs of the final rule requirements. The key findings of the analysis are as follows:

    • Total Cost to Industry. The final rule would result in additional reporting and recordkeeping costs for the industry. The total annual cost for the rule is $244,800. The total present value of the costs is estimated at $940,000 (using a 7-percent discount rate) and $1,021,000 (using a 3-percent discount rate) over the next 20 years.
    • Annual Impact to the Economy. Under the Congressional Review Act of 1996 and as a result of consultations with the Office of Information and Regulatory Affairs of the Office of Management and Budget, the NRC has determined that these actions are not major rules. This determination is based on the estimated one-time costs (expected to occur within the first year) of implementing this action for the total industry is not to exceed $111,350.
    • Value of Benefits Not Reflected Above. The cost figures shown above do not reflect the value of the benefits of the proposed rule. These benefits are evaluated qualitatively in Section 3.1 of the regulatory analysis. This regulatory analysis concluded the costs of the rule are justified in view of the qualitative benefits.
    • Costs to NRC. The NRC would incur costs to review and process licensee responses to the proposed reporting requirements. The total annual costs are approximately $293,760. The NRC will incur one-time costs for developing the infrastructure to process the new notifications, developing guidance, and training NRC staff on the proposed requirements estimated to be $49,920.
    • Decision Rationale. Although the NRC did not quantify the benefits of this rule, the staff did qualitatively examine benefits and concluded that the rule would provide enhanced regulatory effectiveness and efficiency and enhanced openness of the regulatory process. The sum total of the requirements in the proposed rule Start Printed Page 51891would be to establish reporting of issues affecting closed ITAAC.

    XIII. Regulatory Flexibility Act Certification

    In accordance with the Regulatory Flexibility Act (5 U.S.C. 605(b)), the Commission certifies that this rule will not, if promulgated, have a significant economic impact on a substantial number of small entities. This final rule affects only the licensing and operation of nuclear power plants. The companies that own these plants do not fall within the scope of the definition of “small entities” set forth in the Regulatory Flexibility Act or the size standards established by the NRC (10 CFR 2.810).

    XIV. Backfitting and Issue Finality

    The NRC has determined that neither the backfit rule, 10 CFR 50.109, nor any of the finality provisions in 10 CFR part 52, apply to this final rule. Therefore, a backfit analysis is not required because the proposed ITAAC maintenance rule does not contain any provisions that would impose backfitting as defined in the backfit rule, nor does it contain provisions that are inconsistent with the finality provisions applicable to applicants for or holders of combined licenses in 10 CFR part 52.

    The final rule applies only to holders of combined licenses. The backfitting provisions in 10 CFR 50.109 and the finality provisions in Subpart C of 10 CFR part 52 protect holders of combined licenses (with the exception discussed further in this document). Subpart C of 10 CFR part 52 contains issue finality provisions which protect combined license applicants, but that protection extends only to issue resolution of matters resolved in referenced early site permits, standard design certifications, standard design approvals, or manufactured reactors. This rule does not alter issue resolution associated with referenced early site permits, standard design certifications, standard design approvals, or manufactured reactors. Instead, this final rule addresses requirements concerning the collection and reporting of information to the NRC to support the Commission's finding that ITAAC are met, and the conduct of hearings addressing whether prescribed inspections, tests, and analyses have been or will be performed and whether the prescribed acceptance criteria have been or will be met. Neither the backfit rule nor the issue finality provisions of 10 CFR part 52 apply to information collection and reporting requirements.

    To the extent that the rule revises these information collection and reporting requirements for future combined licenses, these requirements do not constitute backfitting or are otherwise inconsistent with the finality provisions in 10 CFR part 52, for the additional reason that the ITAAC Maintenance Rule's requirements are prospective in nature and effect. Neither the backfit rule nor the issue finality provisions in 10 CFR part 52 were intended to apply to every NRC action, which substantially changes the obligations of future licensees under 10 CFR part 52. Accordingly, the NRC has not prepared a backfit analysis or other evaluation for this final rule.

    XV. Congressional Review Act

    Under the Congressional Review Act of 1996, the NRC has determined that these actions are not major rules and has verified this determination with the Office of Information and Regulatory Affairs of OMB.

    Start List of Subjects

    List of Subjects

    10 CFR Part 2

    • Administrative practice and procedure
    • Antitrust
    • Byproduct material
    • Classified information
    • Environmental protection
    • Nuclear materials
    • Nuclear power plants and reactors
    • Penalties
    • Sex discrimination
    • Source material
    • Special nuclear material
    • Waste treatment and disposal

    10 CFR Part 52

    • Administrative practice and procedure
    • Antitrust
    • Backfitting
    • Combined license
    • Early site permit
    • Emergency planning
    • Fees
    • Inspection
    • Limited work authorization
    • Nuclear power plants and reactors
    • Probabilistic risk assessment
    • Prototype
    • Reactor siting criteria
    • Redress of site
    • Reporting and recordkeeping requirements
    • Standard design
    • Standard design certification
    End List of Subjects

    For the reasons set out in the preamble and under the authority of the Atomic Energy Act of 1954, as amended; the Energy Reorganization Act of 1974, as amended; and 5 U.S.C. 552 and 553, the NRC is adopting the following amendments to 10 CFR parts 2 and 52.

    Start Part

    PART 2—RULES OF PRACTICE FOR DOMESTIC LICENSING PROCEEDINGS AND ISSUANCE OF ORDERS

    End Part Start Amendment Part

    1. The authority citation for part 2 continues to read as follows:

    End Amendment Part Start Authority

    Authority: Atomic Energy Act secs.161, 181, 191 (42 U.S.C. 2201, 2231, 2241); Energy Reorganization Act sec. 201 (42 U.S.C. 5841); 5 U.S.C. 552; Government Paperwork Elimination Act sec. 1704 (44 U.S.C. 3504 note).

    End Authority

    Section 2.101 also issued under Atomic Energy Act secs. 53, 62, 63, 81, 103, 104 (42 U.S.C. 2073, 2092, 2093, 2111, 2133, 2134, 2135); Nuclear Waste Policy Act sec. 114(f) (42 U.S.C. 10143(f)); National Environmental Policy Act sec. 102 (42 U.S.C. 4332); Energy Reorganization Act sec. 301 (42 U.S.C. 5871).

    Sections 2.102, 2.103, 2.104, 2.105, 2.321 also issued under Atomic Energy Act secs. 102, 103, 104, 105, 183i, 189 (42 U.S.C. 2132, 2133, 2134, 2135, 2233, 2239). Sections 2.200-2.206 also issued under Atomic Energy Act secs. 161, 186, 234 (42 U.S.C. 2201 (b), (i), (o), 2236, 2282); sec. 206 (42 U.S.C. 5846). Section 2.205(j) also issued under Pub. L. 101-410, as amended by section 3100(s), Pub. L. 104-134 (28 U.S.C. 2461 note). Subpart C also issued under Atomic Energy Act sec. 189 (42 U.S.C. 2239). Section 2.301 also issued under 5 U.S.C. 554. Sections 2.343, 2.346, 2.712 also issued under 5 U.S.C. 557. Section 2.340 also issued under Nuclear Waste Policy Act secs. 135, 141, Pub. L. 97-425, 96 Stat. 2232, 2241 (42 U.S.C. 10155, 10161). Section 2.390 also issued under 5 U.S.C. 552. Sections 2.600-2.606 also issued under sec. 102 (42 U.S.C. 4332). Sections 2.800 and 2.808 also issued under 5 U.S.C. 553. Section 2.809 also issued under 5 U.S.C. 553; Atomic Energy Act sec. 29 (42 U.S.C. 2039). Subpart K also issued under Atomic Energy Act sec. 189 (42 U.S.C. 2239); Nuclear Waste Policy Act sec. 134 (42 U.S.C. 10154). Subpart L also issued under Atomic Energy Act sec. 189 (42 U.S.C. 2239). Subpart M also issued under Atomic Energy Act sec. 184, 189 (42 U.S.C. 2234, 2239). Subpart N also issued under Atomic Energy Act sec. 189 (42 U.S.C. 2239).

    Start Amendment Part

    2. In § 2.340, revise paragraph (j) to read as follows:

    End Amendment Part
    Initial decision in certain contested proceedings; immediate effectiveness of initial decisions; issuance of authorizations, permits and licenses.
    * * * * *

    (j) Issuance of finding on acceptance criteria under 10 CFR 52.103. The Commission, the Director of the Office of New Reactors, or the Director of the Office of Nuclear Reactor Regulation, as appropriate, shall make the finding under 10 CFR 52.103(g) that acceptance criteria in a combined license are met within 10 days from the date of the presiding officer's initial decision:

    (1) If the Commission or the appropriate director is otherwise able to make the finding under 10 CFR 52.103(g) that the prescribed acceptance criteria are met for those acceptance criteria not within the scope of the initial decision of the presiding officer;

    (2) If the presiding officer's initial decision—with respect to contentions that the prescribed acceptance criteria have not been met—finds that those acceptance criteria have been met, and the Commission or the appropriate director thereafter is able to make the finding that those acceptance criteria are met;

    (3) If the presiding officer's initial decision—with respect to contentions Start Printed Page 51892that the prescribed acceptance criteria will not be met—finds that those acceptance criteria will be met, and the Commission or the appropriate director thereafter is able to make the finding that those acceptance criteria are met; and

    (4) Notwithstanding the pendency of a petition for reconsideration under 10 CFR 2.345, a petition for review under 10 CFR 2.341, or a motion for stay under 10 CFR 2.342, or the filing of a petition under 10 CFR 2.206.

    * * * * *
    Start Part

    PART 52—LICENSES, CERTIFICATIONS, AND APPROVALS FOR NUCLEAR POWER PLANTS

    End Part Start Amendment Part

    3. The authority citation for part 52 continues to read as follows:

    End Amendment Part Start Authority

    Authority: Atomic Energy Act secs. 103, 104, 147, 149, 161, 181, 182, 183, 185, 186, 189, 223, 234 (42 U.S.C. 2133, 2201, 2167, 2169, 2232, 2233, 2235, 2236, 2239, 2282); Energy Reorganization Act secs. 201, 202, 206, 211 (42 U.S.C. 5841, 5842, 5846, 5851); Government Paperwork Elimination Act sec. 1704 (44 U.S.C. 3504 note); Energy Policy Act of 2005, Pub. L. 109-58, 119 Stat. 594 (2005).

    End Authority Start Amendment Part

    4. Revise § 52.99 to read as follows:

    End Amendment Part
    Inspection during construction; ITAAC schedules and notifications; NRC notices.

    (a) Licensee schedule for completing inspections, tests, or analyses. The licensee shall submit to the NRC, no later than 1 year after issuance of the combined license or at the start of construction as defined at 10 CFR 50.10(a), whichever is later, its schedule for completing the inspections, tests, or analyses in the ITAAC. The licensee shall submit updates to the ITAAC schedules every 6 months thereafter and, within 1 year of its scheduled date for initial loading of fuel, the licensee shall submit updates to the ITAAC schedule every 30 days until the final notification is provided to the NRC under paragraph (c)(1) of this section.

    (b) Licensee and applicant conduct of activities subject to ITAAC. With respect to activities subject to an ITAAC, an applicant for a combined license may proceed at its own risk with design and procurement activities, and a licensee may proceed at its own risk with design, procurement, construction, and preoperational activities, even though the NRC may not have found that any one of the prescribed acceptance criteria are met.

    (c) Licensee notifications—(1) ITAAC closure notification. The licensee shall notify the NRC that prescribed inspections, tests, and analyses have been performed and that the prescribed acceptance criteria are met. The notification must contain sufficient information to demonstrate that the prescribed inspections, tests, and analyses have been performed and that the prescribed acceptance criteria are met.

    (2) ITAAC post-closure notifications. Following the licensee's ITAAC closure notifications under paragraph (c)(1) of this section until the Commission makes the finding under 10 CFR 52.103(g), the licensee shall notify the NRC, in a timely manner, of new information that materially alters the basis for determining that either inspections, tests, or analyses were performed as required, or that acceptance criteria are met. The notification must contain sufficient information to demonstrate that, notwithstanding the new information, the prescribed inspections, tests, or analyses have been performed as required, and the prescribed acceptance criteria are met.

    (3) Uncompleted ITAAC notification. If the licensee has not provided, by the date 225 days before the scheduled date for initial loading of fuel, the notification required by paragraph (c)(1) of this section for all ITAAC, then the licensee shall notify the NRC that the prescribed inspections, tests, or analyses for all uncompleted ITAAC will be performed and that the prescribed acceptance criteria will be met prior to operation. The notification must be provided no later than the date 225 days before the scheduled date for initial loading of fuel, and must provide sufficient information to demonstrate that the prescribed inspections, tests, or analyses will be performed and the prescribed acceptance criteria for the uncompleted ITAAC will be met, including, but not limited to, a description of the specific procedures and analytical methods to be used for performing the prescribed inspections, tests, and analyses and determining that the prescribed acceptance criteria are met.

    (4) All ITAAC complete notification. The licensee shall notify the NRC that all ITAAC are complete.

    (d) Licensee determination of non-compliance with ITAAC. (1) In the event that an activity is subject to an ITAAC derived from a referenced standard design certification and the licensee has not demonstrated that the prescribed acceptance criteria are met, the licensee may take corrective actions to successfully complete that ITAAC or request an exemption from the standard design certification ITAAC, as applicable.

    A request for an exemption must also be accompanied by a request for a license amendment under 10 CFR 52.98(f).

    (2) In the event that an activity is subject to an ITAAC not derived from a referenced standard design certification and the licensee has not demonstrated that the prescribed acceptance criteria are met, the licensee may take corrective actions to successfully complete that ITAAC or request a license amendment under 10 CFR 52.98(f).

    (e) NRC inspection, publication of notices, and availability of licensee notifications. The NRC shall ensure that the prescribed inspections, tests, and analyses in the ITAAC are performed.

    (1) At appropriate intervals until the last date for submission of requests for hearing under 10 CFR 52.103(a), the NRC shall publish notices in the Federal Register of the NRC staff's determination of the successful completion of inspections, tests, and analyses.

    (2) The NRC shall make publicly available the licensee notifications under paragraph (c) of this section. The NRC shall, no later than the date of publication of the notice of intended operation required by 10 CFR 52.103(a), make publicly available those licensee notifications under paragraph (c) of this section that have been submitted to the NRC at least seven (7) days before that notice.

    Start Signature

    Dated at Rockville, Maryland, this 22nd day of August, 2012.

    For the Nuclear Regulatory Commission.

    Annette L. Vietti-Cook,

    Secretary of the Commission.

    End Signature End Supplemental Information

    Footnotes

    1.  In this discussion, the phrases “completion of ITAAC” and “ITAAC completion” mean that the licensee has determined that: (1) The prescribed inspections, tests, and analyses were performed; and (2) the prescribed acceptance criteria are met.

    Back to Citation

    [FR Doc. 2012-21207 Filed 8-27-12; 8:45 am]

    BILLING CODE 7590-01-P

Document Information

Comments Received:
0 Comments
Effective Date:
9/27/2012
Published:
08/28/2012
Department:
Nuclear Regulatory Commission
Entry Type:
Rule
Action:
Final rule and regulatory guide, issuance.
Document Number:
2012-21207
Dates:
The effective date is September 27, 2012.
Pages:
51880-51892 (13 pages)
Docket Numbers:
NRC-2010-0012
RINs:
3150-AI77: Requirements for Maintenance of Inspections, Tests, Analyses, and Acceptance Criteria [NRC-2010-0012]
RIN Links:
https://www.federalregister.gov/regulations/3150-AI77/requirements-for-maintenance-of-inspections-tests-analyses-and-acceptance-criteria-nrc-2010-0012-
Topics:
Administrative practice and procedure, Antitrust, Classified information, Environmental protection, Fees, Nuclear materials, Nuclear power plants and reactors, Penalties, Reporting and recordkeeping requirements, Sex discrimination, Waste treatment and disposal
PDF File:
2012-21207.pdf
Supporting Documents:
» Regulatory Analysis for Proposed Rule - Requirements for Maintenance of Inspections, Tests, Analyses and Acceptance Criteria
» NUREG/BR-0058, "Regulatory Analysis Guidelines of the U.S. Nuclear Regulatory Commission," Revision 4 (September 2004)
» Regulatory Guide 1.215, "Guidance for ITAAC Closure Under 10 CFR Part 52," Revision 0 (October 31, 2009)
» Inspection Procedure 40600, "Licensee Program for ITAAC Management"
» SRM-M090922 - Staff Requirements - Periodic Briefing on New Reactor Issues - Progress in Resolving Issues Associated with Inspections, Tests, Analyses and Acceptance Criteria (ITAAC), 9:30 A.M., Tuesday, September 22, 2009 (October 16, 2009)
» SECY-09-0119, "Staff Progress in Resolving Issues Associated with Inspections, Tests, Analyses and Acceptance Criteria" (August 26, 2009)
CFR: (2)
10 CFR 2.340
10 CFR 52.99