    Associated Electric Cooperative, Inc.; Notice of Intent
    
    AGENCY: Rural Utilities Service, USDA.
    
    ACTION: Notice of intent to hold scoping meeting and prepare an 
    Environmental Assessment and/or Environmental Impact Statement.
    
    -----------------------------------------------------------------------
    
    SUMMARY: Notice is hereby given that the Rural Utilities Service (RUS), 
    pursuant to the National Environmental Policy Act of 1969 (NEPA) (42 
    U.S.C. 4321 et seq.), the Council on Environmental Quality (CEQ) 
    Regulations for Implementing NEPA (40 CFR Parts 1500-1508), and RUS 
    Environmental Policies and Procedures (7 CFR Part 1794) proposes to 
    prepare an Environmental Assessment and/or an Environmental Impact 
    Statement (EIS) for its Federal action related to a proposal by 
    Associated Electric Cooperative, Inc., to construct two, 100 megawatt 
    simple cycle electric turbines in Northwest Missouri.
    
    MEETING INFORMATION: RUS will conduct a scoping meeting in an open 
    house forum on Tuesday, September 8, 1998, from 6 p.m. until 8 p.m at 
    the headquarters of United Electric Cooperative in Maryville, Missouri. 
    The headquarters is located on Highway 136 East approximately 2.5 miles 
    east of Maryville.
    
    FOR INFORMATION CONTACT: Bob Quigel, Engineering and Environmental 
    Staff, Rural Utility Service, Stop 1571, 1400 Independence Avenue, SW, 
    Washington, DC 20250-1571, telephone (202) 720-0468. Bob's E-mail 
    address is bquigel@rus.usda.gov.
    
    SUPPLEMENTARY INFORMATION: Associated Electric Cooperative, Inc., 
    proposes to construct the plant at one of two potential sites. These 
    sites are in the Nodaway County, Missouri. One site is approximately 
    5.5 miles southeast of Maryville about 0.5 miles south of the 
    intersection of County Highways N and F along County Highway N. The 
    other site is located approximately 1.5 miles east of Graham along 
    County Highway A then 1 mile north up a gravel road.
        The proposed project will be composed of two nominal 100 megawatt 
    simple cycle combustion turbines. They will be primarily gas-fired 
    combustion turbines with the option to burn fuel oil. The combustion 
    turbines will be used for peaking capacity. The hours of operation of 
    the combustion turbines will be limited. The number of operating hours 
    will depend on the emission rates ultimately guaranteed by
    
    [[Page 41544]]
    
    the vendor. The project will be permitted as a minor air pollution 
    source (less than 250 tons of any criteria pollutant). The simple cycle 
    gas-fired combustion turbines require minimal water for operation. 
    Depending on temperature and humidity conditions, there may be some 
    water discharges from the site. Such discharges will be permitted under 
    the Missouri National Pollutant Discharge Elimination System program.
        Alternatives considered by RUS and Associated Electric Cooperative, 
    Inc., to constructing the generation facility proposed include: (a) No 
    action, (b) purchase of power, (c) load management, (d) construction of 
    additional base load capacity, and (e) renewable energy.
        To be presented at the public scoping meeting will be a siting and 
    alternative study prepared by Associated Electric Cooperative, Inc. The 
    siting and alternative study is available for public review at RUS at 
    the address provided in this notice or at Associated Electric 
    Cooperative, Inc., 2814 South Golden, Springfield, Missouri, 65801-
    0754, phone (417) 881-1204. This document will also be available at the 
    Maryville Public Library which is located at 5th and Main Street in 
    Maryville.
        Government agencies, private organizations, and the public are 
    invited to participate in the planning and analysis of the proposed 
    project. Representatives from RUS and Associated Electric Cooperative, 
    Inc., will be available at the scoping meeting to discuss RUS's 
    environmental review process, describe the project and alternatives 
    under consideration, discuss the scope of environmental issues to be 
    considered, answer questions, and accept oral and written comments. 
    Written comments will be accepted for at least 30 days after the public 
    scoping meeting. Written comments should be sent to RUS at the address 
    provided in this notice.
        From information provided in the siting and alternative study, 
    input that may be provided by government agencies, private 
    organizations, and the public, Associated Electric Cooperative, Inc., 
    and Burns and McDonnell will prepare an environmental analysis to be 
    submitted to RUS for review. If significant impacts are not evident 
    based on a review of the environmental analysis and other relevant 
    information, RUS will prepare an environmental assessment to determine 
    if the preparation of an EIS is warranted.
        Should RUS determine that the preparation of an EIS is not 
    warranted, it will prepare a finding of no significant impact (FONSI). 
    The FONSI will be made available for public review and comment for 30 
    days. Public notification of a FONSI would be published in the Federal 
    Register and in newspapers with a circulation in the project area. RUS 
    will not take its final action related to the project prior to the 
    expiration of the 30-day period.
        Any final action by RUS related to the proposed project will be 
    subject to, and contingent upon, compliance with environmental review 
    requirements as prescribed by CEQ and RUS environmental policies and 
    procedures.
    
        Dated: July 29, 1998.
    Lawrence R. Wolfe,
    Acting Director, Engineering and Environmental Staff.
    [FR Doc. 98-20735 Filed 8-3-98; 8:45 am]
    BILLING CODE 3410-15-U
    
    
    

Document Information

Published:
08/04/1998
Department:
Rural Utilities Service
Entry Type:
Notice
Action:
Notice of intent to hold scoping meeting and prepare an Environmental Assessment and/or Environmental Impact Statement.
Document Number:
98-20735
Pages:
41543-41544 (2 pages)
PDF File:
98-20735.pdf