E5-4199. Pacific Gas and Electric; Notice of Application Tendered for Filing With the Commission, Soliciting Additional Study Requests, and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments  

  • Start Preamble July 28, 2005.

    Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection.

    a. Type of Application: New major license.

    b. Project No.: 2155.

    c. Date Filed: July 15, 2005.

    d. Applicant: Pacific Gas and Electric Company.

    e. Name of Project: Chili Bar Project.

    f. Location: On the South Fork American River in El Dorado, near Placerville, California. The project affects 48 acres of Federal land administered by the Bureau of Land Management.

    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).

    h. Applicant Contact: Randal S. Livingston, Power Generation Senior Director, Pacific Gas and Electric Company, P.O. Box 770000, Mail Code: N11E, San Francisco, CA 94177.

    i. FERC Contact: Jim Fargo, (202) 502-6095 or James.Fargo@ferc.gov.

    j. Cooperating Agencies: We are asking Federal, state, local, and tribal Start Printed Page 45387agencies with jurisdiction and/or special expertise with respect to environmental issues to cooperate with us in the preparation of the environmental document. Agencies who would like to request cooperating status should follow the instructions for filing comments described in item l below.

    k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's regulations, if any resource agency, Indian Tribe, or person believes that an additional scientific study should be conducted in order to form an adequate factual basis for a complete analysis of the application on its merit, the resource agency, Indian Tribe, or person must file a request for a study with the Commission not later than 60 days from the date of filing of the application, and serve a copy of the request on the applicant.

    l. Deadline for Filing Additional Study Requests and Requests for Cooperating Agency Status: September 15, 2005.

    All Documents (Original and Eight Copies) Should be Filed With: Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426.

    The Commission's Rules of Practice require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency.

    Additional study requests and requests for cooperating agency status may be filed electronically via the Internet in lieu of paper. The Commission strongly encourages electronic filings. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web site (http://www.ferc.gov) under the “e-Filing” link.

    m. This application is not ready for environmental analysis at this time.

    n. The existing Chili Bar Project consists of: (1) A 120-foot-high concrete gravity dam; (2) a 110-acre reservoir with a useable storage of 1,339 acre-feet; (3) a powerhouse with one 7-MW unit and (4) appurtenant facilities. The applicant estimates that the total average annual generation would be 33,500 megawatt hours. All generated power is utilized within the applicant's electric utility system.

    o. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission's Web site at http://www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll-free at 1-866-208-3676, or for TTY, (202) 502-8659. A copy is also available for inspection and reproduction at the address in item h above.

    You may also register online at http://www.ferc.gov/​docs-filing/​esubscription.asp to be notified via e-mail of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support.

    p. With this notice, we are initiating consultation with the California State Historic Preservation Officer (SHPO), as required by (106, National Historic Preservation Act, and the regulations of the Advisory Council on Historic Preservation, 36 CFR 800.4.

    q. Procedural Schedule and Final Amendments: The application will be processed according to the following Hydro Licensing Schedule. Revisions to the schedule will be made as appropriate.

    Issue Acceptance/Deficiency Letter and request additional information, if needed, November 2005.

    Issue Scoping Document for comments, December 2005.

    Notice of application is ready for environmental analysis, April 2006.

    Notice of the availability of the draft EIS, December 2006.

    Notice of the availability of the final FEIS, June 2007.

    Ready for Commission's decision on the application, August 2007.

    Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis.

    Start Signature

    Linda Mitry,

    Deputy Secretary.

    End Signature End Preamble

    [FR Doc. E5-4199 Filed 8-4-05; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Published:
08/05/2005
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
E5-4199
Pages:
45386-45387 (2 pages)
Docket Numbers:
Project No. 2155
EOCitation:
of 2005-07-28
PDF File:
e5-4199.pdf