[Federal Register Volume 62, Number 151 (Wednesday, August 6, 1997)]
[Notices]
[Pages 42246-42249]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 97-20663]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. ER97-3643-000, et al.]
Consolidated Edison Company of New York, Inc., et al. Electric
Rate and Corporate Regulation Filings
July 29, 1997.
Take notice that the following filings have been made with the
Commission:
1. Consolidated Edison Company of New York, Inc.
[Docket No. ER97-3643-000]
Take notice that on July 8, 1997, Consolidated Edison Company of
New York, Inc. (Con Edison), tendered for filing a Supplement to Con
Edison Rate Schedule FERC No. 112 for transmission service for New York
State Electric & Gas Corporation (NYSEG). Con Edison has requested a
waiver so that the supplement can be effective as of April 1, 1997,
consistent with the terms of Rate Schedule 112.
Con Edison states that a copy of this filing has been served by
mail upon NYSEG.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
2. Consolidated Edison Company of New York, Inc.
[Docket No. ER97-3644-000]
Take notice that on July 8, 1997, Consolidated Edison Company of
New York, Inc. (Con Edison), tendered for filing a service agreement to
provide non-firm transmission service pursuant to its Open Access
Transmission Tariff to Virginia Power--The Wholesale Power Group
(Virginia).
Con Edison states that a copy of this filing has been served by
mail upon Virginia.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
3. Consolidated Edison Company of New York, Inc.
[Docket No. ER97-3645-000]
Take notice that on July 8, 1997, Consolidated Edison Company of
New York, Inc. (Con Edison), tendered for filing a service agreement to
provide non-firm transmission service pursuant to its Open Access
Transmission Tariff to PanEnergy Trading & Market Services, L.L.C.
(PanEnergy).
Con Edison states that a copy of this filing has been served by
mail upon PanEnergy.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
4. Consolidated Edison Company of New York, Inc.
[Docket No. ER97-3646-000]
Take notice that on July 8, 1997, Consolidated Edison Company of
New York, Inc. (Con Edison), tendered for filing a service agreement to
provide non-firm transmission service pursuant to its Open Access
Transmission Tariff to Engage Energy US, L.P. (Engage).
[[Page 42247]]
Con Edison states that a copy of this filing has been served by
mail upon Engage.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
5. Wisconsin Public Service Corporation
[Docket No. ER97-3648-000]
Take notice that on July 8, 1997, Wisconsin Public Service
Corporation (WPSC), tendered for filing an executed Transmission
Service Agreement between WPSC and NP Energy Inc., provides for
transmission service under the Open Access Transmission Service Tariff,
FERC Original Volume No. 11.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
6. Wisconsin Public Service Corporation
[Docket No. ER97-3649-000]
Take notice that on July 8, 1997, Wisconsin Public Service
Corporation (WPSC), tendered for filing an executed Transmission
Service Agreement between WPSC and itself. The Agreement provides for
transmission service under the Open Access Transmission Service Tariff,
FERC Original Volume No. 11.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
7. Sierra Pacific Power Company
[Docket No. ER97-3650-000]
Take notice that on July 8, 1997, Sierra Pacific Power Company
(Sierra), tendered for filing pursuant to Section 205 of the Federal
Power Act and 18 CFR Part 35, an energy rate adjustment (including
displacement credit) pursuant to an Electric Service Agreement between
Sierra and Truckee Donner Public Utility District. (District).
Sierra asserts that the filing has been served on the District and
on the regulatory commissions of Nevada and California.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
8. Sierra Pacific Power Company
[Docket No. ER97-3651-000]
Take notice that on July 8, 1997, Sierra Pacific Power Company
(Sierra), tendered for filing pursuant to Section 205 of the Federal
Power Act and 18 CFR Part 35, an energy rate adjustment pursuant to an
Electric Service Agreement between Sierra and City of Fallon (Fallon).
Sierra asserts that the filing has been served on Fallon and on the
regulatory commissions of Nevada and California.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
9. Virginia Electric and Power Company
[Docket No. ER97-3652-000]
Take notice that on July 8, 1997, Virginia Electric and Power
Company (Virginia Power), tendered for filing Service Agreements for
Non-Firm Point-to-Point Transmission Service with Public Service
Electric and Gas Company and GPU Energy under the Open Access
Transmission Tariff to Eligible Purchasers dated July 9, 1996. Under
the tendered Service Agreement Virginia Power will provide firm point-
to-point service to the Transmission Customers as agreed to by the
parties under the rates, terms and conditions of the Open Access
Transmission Tariff.
Copies of the filing were served upon the Virginia State
Corporation Commission, and the North Carolina Utilities Commission.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
10-11. Indianapolis Power & Light Company
[Docket No. ER97-3653-000]
Take notice that on July 8, 1997, Indianapolis Power & Light
Company (IPL), tendered for filing a letter agreement extending by one
year to August 31, 1998, the service IPL currently provides to PSI
Energy, a public utility subsidiary of Cinergy, under an existing
interconnection agreement.
Copies of this filing were sent to the Indiana Utility Regulatory
Commission and Cinergy.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
12. Indianapolis Power & Light Company
[Docket No. ER97-3654-000]
Take notice that on July 8, 1997, Indianapolis Power & Light
Company (IPL), tendered for filing an amendment to an existing
agreement between IPL and Wabash Valley Power Association, Inc. (Wabash
Valley).
Copies of this filing were sent to the Indiana Utility Regulatory
Commission and Wabash Valley.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
13. Wisconsin Public Service Corporation
[Docket No. ER97-3655-000]
Take notice that on July 8, 1997, Wisconsin Public Service
Corporation (WPSC), tendered for filing an executed Transmission
Service Agreement between WPSC and itself. The Agreement provides for
transmission service under the Open Access Transmission Service Tariff,
FERC Original Volume No. 11.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
14. Wisconsin Public Service Corporation
[Docket No. ER97-3656-000]
Take notice that on July 8, 1997, Wisconsin Public Service
Corporation (WPSC), tendered for filing an executed Transmission
Service Agreement between WPSC and Upper Peninsula Power Co. The
Agreement provides for transmission service under the Open Access
Transmission Service Tariff, FERC Original Volume No. 11.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
15. Wisconsin Public Service Corporation
[Docket No. ER97-3657-000]
Take notice that on July 8, 1997, Wisconsin Public Service
Corporation (WPSC), tendered for filing an executed Transmission
Service Agreement between WPSC and Wisconsin Power & Light Company. The
Agreement provides for transmission service under the Open Access
Transmission Service Tariff, FERC Original Volume No. 11.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
16. Northeast Utilities Service Company
[Docket No. ER97-3658-000]
Take notice that on July 8, 1997, Northeast Utilities Service
Company (NUSCO), tendered for filing, a Service Agreement with Green
Mountain Power Corp. (GMP) under the NU System Companies' System Power
Sales/Exchange Tariff No. 6. NUSCO requested deferral of Commission
action on the filing until NUSCO made its filing for functional
unbundling of services under the Tariff pursuant to the Commission's
Order No. 888.
NUSCO states that a copy of this filing has been mailed to GMP.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
[[Page 42248]]
17. Virginia Electric and Power Company
[Docket No. ER97-3659-000]
Take notice that on July 8, 1997, Virginia Electric and Power
Company (Virginia Power), tendered for filing Service Agreements for
Firm Point-to-Point Transmission Service with PECO Energy--Power Team
and The Wholesale Power Group under the Open Access Transmission Tariff
to Eligible Purchasers dated July 9, 1996. Under the tendered Service
Agreement Virginia Power will provide firm point-to-point service to
the Transmission Customers as agreed to by the parties under the rates,
terms and conditions of the Open Access Transmission Tariff.
Copies of the filing were served upon the Virginia State
Corporation Commission, and the North Carolina Utilities Commission.
NUSCO requests that the Service Agreement become effective July 1,
1997.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
18. Virginia Electric and Power Company
[Docket No. ER97-3660-000]
Take notice that on July 8, 1997, Virginia Electric and Power
Company (Virginia Power), tendered for filing executed Service
Agreements between Virginia Electric and Power Company and
Constellation Power Source, Inc., and NP Energy, Inc., under the Power
Sales Tariff to Eligible Purchasers dated May 27, 1994, as revised on
December 31, 1996. Under the tendered Service Agreements Virginia Power
agrees to provide services to Constellation Power Source, Inc., and NP
Energy, Inc., under the rates, terms and conditions of the Power Sales
Tariff as agreed by the parties pursuant to the terms of the applicable
Service Schedules included in the Power Sales Tariff.
Copies of the filing were served upon the Virginia State
Corporation Commission, and the North Carolina Utilities Commission.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
19. Central Power and Light Company; Public Service Company of
Oklahoma; Southwestern Electric Power Company; West Texas Utilities
Company
[Docket No. ER97-3661-000]
Take notice that on July 8, 1997, Central Power and Light Company
(CPL), Public Service Company of Oklahoma (PSO), Southwestern Electric
Power Company (SWEPCO) and West Texas Utilities Company (WTU)
(collectively, the Companies) each tendered for filing Service
Agreements establishing NP Energy Inc., and PacifiCorp Power Marketing,
Inc., as customers under the terms of each Company's CSRT-1 Tariff.
The Companies request an effective date of June 8, 1997 for each of
the service agreements and, accordingly, seek waiver of the
Commission's notice requirements. Copies of this filing were served on
the two customers, the Arkansas Public Service Commission, the
Louisiana Public Service Commission, the Oklahoma Corporation
Commission and the Public Utility Commission of Texas.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
20. San Diego Gas & Electric Company
[Docket No. ER97-3662-000]
Take notice that on July 8, 1997, San Diego Gas & Electric Company
(SDG&E), tendered for filing and acceptance, pursuant to 18 CFR 35.13,
a Service Agreement (Service Agreement) with San Diego Gas & Electric
Co. (Energy Trading) for Point-To-Point Transmission Service under
SDG&E's Open Access Transmission Tariff (Tariff) filed in compliance
with FERC Order No. 888.
SDG&E filed the executed Service Agreement with the Commission in
compliance with applicable Commission regulations. SDG&E also provided
Sheet No. 114 (Attachment E) to the Tariff, which is a list of current
subscribers. SDG&E requests waiver of the Commission's notice
requirement to permit an effective date of July 1, 1997 for the Service
Agreement.
Copies of this filing were served upon the Public Utilities
Commission of the State of California and all interested parties.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
21. Tucson Electric Power Company
[Docket No. ER97-3665-000]
Take notice that on July 9, 1997, Tucson Electric Power Company
(TEP), tendered for filing two (2) service agreements for firm point-
to-point transmission service and three (3) service agreements for non-
firm point-to-point transmission service under Part II of its Open
Access Transmission Tariff filed in Docket No. OA96-140-000. TEP
requests waiver of notice to permit the service agreements to become
effective as of June 15, 1997. The service agreements are as follows:
(1) Service Agreement for Non-Firm Point-to-Point Transmission
Service with e prime, Inc., dated May 27, 1997.
(2) Service Agreement for Firm Point-to-Point Transmission Service
with Enron Power Marketing, Inc., dated June 23, 1997.
(3) Service Agreement for Firm Point-to-Point Transmission Service
with Enron Power Marketing, Inc., dated June 27, 1997.
(4) Service Agreement for Non-Firm Point-to-Point Transmission
Service with El Paso Electric Co., Inc., dated July 3, 1997.
(5) Service Agreement for Non-Firm Point-to-Point Transmission
Service with WESCO (Williams Energy Services Company) dated July 7,
1997.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
22. Columbia Power Marketing Corporation
[Docket No. ER97-3667-000]
Take notice that on July 9, 1997, Columbia Power Marketing
Corporation (CPM), tendered for filing with the Federal Energy
Regulatory Commission, CPM's Rate Schedule No. 1, which permits CPM to
make wholesale power sales at market-based rates.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
23. Atlantic City Electric Company
[Docket No. ER97-3668-000]
Take notice that on July 9, 1997, Atlantic City Electric Company
(Atlantic Electric), tendered for a filing service agreement under
which Atlantic Electric will sell capacity and energy to EnerZ
Corporation under Atlantic Electric's market-based rate sales tariff.
Atlantic Electric requests the agreement be accepted to become
effective on July 1, 1997.
Atlantic Electric states that a copy of the filing has been served
on EnerZ Corporation.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
24. Northeast Utilities Service Company
[Docket No. ER97-3669-000]
Take notice that on July 9, 1997, Northeast Utilities Service
Company (NUSCO), on behalf of The Connecticut Light & Power Company
(CL&P), tendered for filing pursuant to Section 205 of the Federal
Power Act and Section 35.13 of the Commission's Regulations, a rate
schedule change for sales of electric energy to the Wallingford
Electric Division (CL&P No. 514).
[[Page 42249]]
NUSCO states that a copy of this filing has been mailed to
Wallingford.
NUSCO requests that the rate schedule become effective on August 1,
1997.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
25. Ohio Edison Company Pennsylvania Power Company
[Docket No. ER97-3670-000]
Take notice that on July 9, 1997, Ohio Edison Company, tendered for
filing on behalf of itself and Pennsylvania Power Company, a Service
Agreement with GPU Energy under Ohio Edison's Power Sales Tariff. This
filing is made pursuant to Section 205 of the Federal Power Act.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
26. Ohio Edison Company; Pennsylvania Power Company
[Docket No. ER97-3671-000]
Take notice that on July 9, 1997, Ohio Edison Company tendered for
filing on behalf of itself and Pennsylvania Power Company, a Service
Agreement for Non-Firm Point-to-Point Transmission Service with Rainbow
Energy Marketing Corporation Inc., and Ohio Edison Company pursuant to
Ohio Edison's Open Access Tariff. This Service Agreement will enable
the parties to obtain Non-Firm Point-to-Point Transmission Service in
accordance with the terms of the Tariff.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
27. Allegheny Power Service Corporation, on behalf of Monongahela
Power Company, The Potomac Edison Company, and West Penn Power
Company (Allegheny Power)
[Docket No. ER97-3672-000]
Take notice that on July 9, 1997, Allegheny Power Service
Corporation on behalf of Monongahela Power Company, The Potomac Edison
Company and West Penn Power Company (Allegheny Power), filed Supplement
No. 21 to add NP Energy Inc., and Northeast Utilities Service Company
to Allegheny Power Open Access Transmission Service Tariff which has
been submitted for filing by the Federal Energy Regulatory Commission
in Docket No. OA96-18-000. The proposed effective date under the
Service Agreements is July 8, 1997.
Copies of the filing have been provided to the Public Utilities
Commission of Ohio, the Pennsylvania Public Utility Commission, the
Maryland Public Service Commission.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
28. New York State Electric & Gas Corporation
[Docket No. ER97-3674-000]
Take notice that on July 9, 1997, New York State Electric & Gas
Corporation (NYSEG) tendered for filing a Notice of Cancellation of
NYSEG's Rate Schedule FERC No. 165 between NYSEG and Virginia Electric
and Power Company (VEPCO).
NYSEG requests that this cancellation become effective on July 7,
1997.
Notice of the proposed cancellation has been served upon the New
York State Public Service Commission and on the Customer.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
29. Union Electric Company
[Docket No. ER97-3675-000]
Take notice that on July 9, 1997, Union Electric Company tendered
for filing Sixth Amendment dated as of June 24, 1997, modifying the
September 18, 1979, Interconnection Contract between City of Columbia,
Missouri, and Union Electric Company.
Said Amendment primarily provides for an increased rate cap to the
reservation charge for Short-Term Non-Firm Power.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
30. Southwestern Public Service Company
[Docket No. ER97-3676-000]
Take notice that on July 10, 1997, Southwestern Public Service
Company (Southwestern) submitted an executed service agreement under
its open access transmission tariff with Tenaska Power Services
Company. The service agreement is for umbrella non-firm point-to-point
transmission service.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
31. Allegheny Power Service Corporation, on behalf of Monongahela
Power Company, The Potomac Edison Company and West Penn Power
Company (Allegheny Power)
[Docket No. ER97-3673-000]
Take notice that on July 9, 1997, Allegheny Power Service
Corporation on behalf of Monongahela Power Company, The Potomac Edison
Company and West Penn Power Company (Allegheny Power) filed Supplement
No. 27 to add two (2) new Customers to the Standard Generation Service
Rate Schedule under which Allegheny Power offers standard generation
and emergency service on an hourly, daily, weekly, monthly or yearly
basis. Allegheny Power requests a waiver of notice requirements to make
service available as of July 8, 1997, to NP Energy Inc., and Northeast
Utilities Company.
Copies of the filing have been provided to the Public Utilities
Commission of Ohio, the Pennsylvania Public Utility Commission, the
Maryland Public Service Commission, the Virginia State Corporation
Commission, the West Virginia Public Service Commission, and all
parties of record.
Comment date: August 12, 1997, in accordance with Standard
Paragraph E at the end of this notice.
Standard Paragraph
E. Any person desiring to be heard or to protest said filing should
file a motion to intervene or protest with the Federal Energy
Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426,
in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such
motions or protests should be filed on or before the comment date.
Protests will be considered by the Commission in determining the
appropriate action to be taken, but will not serve to make protestants
parties to the proceeding. Any person wishing to become a party must
file a motion to intervene. Copies of this filing are on file with the
Commission and are available for public inspection.
Lois D. Cashell,
Secretary.
[FR Doc. 97-20663 Filed 8-5-97; 8:45 am]
BILLING CODE 6717-01-P