a. Type of Application: New major license.
b. Project No.: P-1893-042.
c. Date filed: December 30, 2003.
d. Applicant: Public Service Company of New Hampshire (PSNH).
e. Name of Project: Merrimack River Project.
f. Location: On the Merrimack River, in Merrimack and Hillsborough counties, New Hampshire. The project does not occupy federal lands.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)—825(r).
h. Applicant Contact: James J. Kearns, 780 North Commercial Street, P.O. Box 330, Manchester, NH, 03105 (603)-634-2936.
i. FERC Contact: Steve Kartalia, Stephen.kartalia@ferc.gov (202) 502-6131.
j. Deadline for filing motions to intervene and protests: 60 days from the issuance date of this notice.
All documents (original and eight copies) should be filed with: Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426.
The Commission's Rules of Practice and Procedures require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency.
Motions to intervene and protests may be filed electronically via the Internet in lieu of paper. The Commission strongly encourages electronic filings. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web site (http://www.ferc.gov) under the “e-Filing” link.
k. This application has been accepted, but is not ready for environmental analysis at this time.
l. The Merrimack project consists of three developments described below:
The Amoskeag Development consisting of: (1) A 29-foot-high, 710-foot-long concrete gravity dam comprised of: (i) a low crest section with 5-foot-high flashboards; and (ii) a high crest section with 3-foot-high flashboards; (2) a 7-mile-long, 478-acre reservoir; (3) a powerhouse, integral with the dam, containing three generating units with a total installed capacity of 16,000 kW; (4) a 415-foot-long, 34.5-kV double circuit transmission line; and (5) other appurtenances.
The Hooksett Development consisting of: (1) A dam comprised of: (i) a 340-foot-long stone masonry section with 2-foot-high flashboards connected to; (ii) a 250-foot-long concrete section with 2-foot-high flashboards; (2) a 15-foot by 20-foot Taintor gate; (3) a 5.5-mile-long, 405-acre reservoir; (4) a powerhouse containing a single generating unit with an installed capacity of 1,600 kW; and (5) other appurtenances.
The Garvins Falls Development consisting of: (1) An 18-foot-high, 550-foot-long concrete and granite gravity dam comprised of: (i) a low crest section with 3-foot-high flashboards; and (ii) a high crest section with 1.2-foot-high flashboards; (2) an 8-mile-long reservoir; (3) a 500-foot-long water canal with a 10-foot-wide waste gate; (4) two powerhouses, each containing two generating units for a total installed capacity of 12,300 kW; (5) a 340-foot-long, 34.5-kV transmission line; and (6) other appurtenances.
m. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission's Web site at http://www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll-free at 1-866-208-3676, or for TTY, (202) 502-8659. A copy is also available for inspection and reproduction at the address in item h above.
You may also register online at http://www.ferc.gov/docs-filing/Start Printed Page 53426esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support.
n. Anyone may submit a protest or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, 385.211, and 385.214. In determining the appropriate action to take, the Commission will consider all protests filed, but only those who file a motion to intervene in accordance with the Commission's Rules may become a party to the proceeding. Any protests or motions to intervene must be received on or before the specified deadline date for the particular application.
All filings must (1) bear in all capital letters the title “PROTEST” or “MOTION TO INTERVENE;” (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application.
o. Procedural schedule and final amendments: The application will be processed according to the following Hydro Licensing Schedule. Revisions to the schedule will be made as appropriate. The Commission staff proposes to issue one environmental assessment rather than issue a draft and final EA. Comments, terms and conditions, recommendations, prescriptions, and reply comments, if any, will be addressed in an EA issued in the summer of 2005.
Notice that application is ready for environmental analysis: January 2005.
Notice of the availability of the EA: June 2005.
Ready for Commission decision on the application: September 2005.
Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis.
Start SignatureMagalie R. Salas,
Secretary.
[FR Doc. E4-1990 Filed 8-31-04; 8:45 am]
BILLING CODE 6717-01-P
Document Information
- Published:
- 09/01/2004
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- E4-1990
- Pages:
- 53425-53426 (2 pages)
- Docket Numbers:
- Project No. 1893-042
- EOCitation:
- of 2004-08-26
- PDF File:
- e4-1990.pdf