98-24461. Maine Yankee Atomic Power Company, Maine Yankee Atomic Power Station; Exemption  

  • [Federal Register Volume 63, Number 176 (Friday, September 11, 1998)]
    [Notices]
    [Pages 48768-48770]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-24461]
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket No. 50-309]
    
    
    Maine Yankee Atomic Power Company, Maine Yankee Atomic Power 
    Station; Exemption
    
    I
    
        Maine Yankee Atomic Power Company (MYAPCo or the licensee) is the 
    holder of Facility Operating License No. DPR-36, which authorizes 
    possession of Maine Yankee Atomic Power Station (Maine Yankee). The 
    license provides, among other things, that the facility is subject to 
    all rules, regulations, and orders of the U.S. Nuclear Regulatory 
    Commission (NRC or the Commission) now or hereafter in effect. The 
    facility is a pressurized-water reactor (PWR) located on the licensee's 
    site in Lincoln County, Maine. On August 7, 1997, the licensee 
    submitted written certifications to the Commission that it had decided 
    to permanently cease operations at Maine Yankee and that all fuel had 
    been permanently removed from the reactor. In accordance with 10 CFR 
    50.82(a)(2), upon docketing of the certifications contained in the 
    letter of August 7, 1997, the facility operating license no longer 
    authorizes MYAPCo to operate the reactor or to place fuel in the 
    reactor vessel.
    
    II
    
        Section 50.54(q) of Title 10 of the Code of Federal Regulations (10 
    CFR 50.54(q)) requires power reactor licensees to follow and maintain 
    in effect emergency plans that meet the standards of 10 CFR 50.47(b) 
    and the requirements of Appendix E to 10 CFR Part 50.
        Pursuant to 10 CFR 50.12(a), the Commission may, upon application 
    by any interested person or upon its own initiative, grant exemptions 
    from the requirements of the regulations that are (1) authorized by 
    law, will not present an undue risk to public health and safety, and 
    are consistent with the common defense and security and (2) present 
    special circumstances. Special circumstances exist when application of 
    the regulation in the particular circumstance would not serve the 
    underlying purpose of the rule or is not necessary to achieve the 
    underlying purpose of the rule (10 CFR 50.12(a)(2)(ii)). The underlying 
    purpose of Section 50.54(q) is to ensure licensees follow and maintain 
    in effect emergency plans that provide reasonable assurance that 
    adequate protective measures can and will be taken in the event of an 
    emergency at a nuclear reactor. Sections 50.47(b) and (c) outline the 
    planning standards and size of Emergency Planning Zones, respectively, 
    that are to be considered in emergency plans and Appendix E to 10 CFR 
    Part 50 identifies the information that must be included in emergency 
    plans.
    
    III
    
        By letter dated November 6, 1997, the licensee requested exemptions 
    from certain requirements of 10 CFR 50.54(q), 10 CFR 50.47(b) and (c), 
    and Appendix E to Part 50; the licensee also made available a draft 
    copy of the Maine Yankee Defueled Emergency Plan (DEP) to assist the 
    staff in its review of the exemption request. The exemptions would 
    allow Maine Yankee to discontinue certain aspects of offsite planning 
    and reduce the scope of onsite emergency planning. The licensee stated 
    that the remaining requirements of 10 CFR 50.54(q), 10 CFR 50.47(b) and 
    (c), and Appendix E to Part 50 will be addressed in the DEP. The 
    licensee plans to implement the DEP without NRC review and approval. 
    Under the provisions of Sec. 50.54(q), when a change to an emergency 
    plan is made, the staff evaluates that change against the bases for 
    commitments made in the plan to determine whether there is a decrease 
    in effectiveness. It is not a decrease in effectiveness if the 
    reduction in the commitment is commensurate with a reduction in the 
    bases for that commitment. In this instance, the staff has determined 
    that there has been a reduction in the bases that require offsite 
    emergency planning. The revised DEP will be reviewed by the NRC after 
    implementation. By letter dated March 25, 1998, the licensee submitted 
    the Emergency Action Levels that it proposes to use with the Defueled 
    Emergency Plan. By letter dated June 29, 1998, the licensee submitted 
    additional information that revised the exemption request. By letters 
    dated January 20, May 15, and June 18, 1998, MYAPCo submitted the 
    results of an assessment of the Maine Yankee spent fuel heatup in the 
    absence of water in the spent fuel pool. By letters dated July 9 and 
    August 5, 1998, the licensee provided the results of radiological 
    analyses applicable to Maine Yankee in the permanently shutdown 
    condition.
        The licensee stated that special circumstances are present at Maine 
    Yankee because (1) application of the regulation in the particular 
    circumstances would not serve the underlying purpose of the rule or is 
    not necessary to achieve the underlying purpose of the rule, (2) 
    compliance would result in undue hardship or other costs that are 
    significantly in excess of those contemplated when the regulation was 
    adopted, or are significantly in excess of those incurred by others in 
    similar circumstances, and (3) there is a material circumstance 
    present, that was not considered when the regulation was adopted, for 
    which it would be in the public interest to grant an exemption.
        With the plant in a permanently shutdown and defueled condition, 
    the applicable design-basis accidents are limited to a fuel handling 
    incident, spent fuel cask drop, and radioactive liquid waste system 
    leak and failure. The calculated maximum offsite dose from these 
    postulated releases is less than the U.S. Environmental Protection 
    Agency (EPA) Protective Action Guides (PAGs). The licensee also 
    estimated that, by March 1998, a beyond-design-basis event, involving 
    fuel damage (caused by a loss of spent fuel pool water and a subsequent 
    overheating of the stored fuel) and the release of radioactive 
    materials sufficient to exceed EPA PAGs at the site boundary is not 
    credible.
        Revision 14 to the Maine Yankee Defueled Safety Analysis Report 
    (DSAR) includes revised analyses of postulated accidents at Maine 
    Yankee in its permanently shutdown status. Chapter 5 of the DSAR 
    describes the radiological consequences of accidents that could release 
    radioactive materials and the consequences of a spent fuel pool
    
    [[Page 48769]]
    
    draindown event. The staff reviewed the licensee's analyses, as 
    modified in licensee submittals dated July 9 and August 5, 1998, to 
    determine whether the radiological impact of these events would require 
    an offsite emergency plan.
        Decontamination of systems during decommissioning and dismantlement 
    operations will generate significant quantities of radioactive waste in 
    the form of contaminated demineralizer resins. The licensee has 
    postulated a bounding accident for the release of radioactivity: the 
    dropping of a highly loaded spent resin liner within the low-level-
    waste storage building (LLWSB), resulting in the liner failure and a 
    release of a fraction of its radioactive materials in an airborne 
    cloud. The analysis indicates that an individual at the exclusion area 
    boundary (EAB) could receive up to 0.11 rem total effective dose 
    equivalent (TEDE) from this event.
        The licensee stated that this event was considered to have higher 
    offsite consequences than the mishandling of resin during resin liner 
    filling and dewatering operations since these activities are performed 
    in containment. Hold-up and confinement of radioactive materials in a 
    containment that is isolated would significantly decrease the potential 
    for offsite release. In addition, the licensee committed in the DSAR to 
    establish administrative controls to ensure that calculated offsite 
    doses from potential decommissioning accidents do not exceed those 
    calculated for a spent resin cask drop accident.
        The licensee did not postulate a fire concurrent with the resin 
    mishandling event owing to the low flammability of the resin itself and 
    the absence of flammable material in the LLWSB. However, the analysis 
    did assume that 1.0 percent of the radioactivity in the liner became 
    airborne during the event. This assumption is the same fraction of 
    material expected to be released by a fire, and is consistent with the 
    release fractions listed in Schedule C to 10 CFR 30.72 for mixed 
    fission and corrosion products. The calculational methods and 
    assumptions used in this analysis are acceptable to the staff.
        Wet storage of spent fuel possesses inherently large safety margins 
    because of the simplicity and robustness of the spent fuel pool design. 
    The design basis includes the ability to withstand an earthquake and to 
    retain sufficient water to adequately cool and shield the stored spent 
    fuel. Specifically, in the DSAR, the licensee states that the spent 
    fuel pool structure is designed to Seismic Class I requirements and is 
    capable of performing its intended safety function under the licensee's 
    design-basis hypothetical earthquake with a 0.1-g peak ground 
    acceleration. The pool has 6-foot reinforced-concrete walls and floor 
    with a \1/4\-inch steel liner. To add to the robustness of the design, 
    the pool is founded on bedrock and is embedded 12.5 feet below grade 
    level, which is at the 20 foot, 1 inch elevation. Since the analyses 
    used in designing the capability of structures, systems, and components 
    (SSCs) to perform their safety function under a hypothetical earthquake 
    have significant margin in them, it is expected that an SSC built to 
    withstand the hypothetical design-basis earthquake actually will be 
    able to withstand a larger earthquake. Thus, the loss of coolant from 
    the Maine Yankee spent fuel pool, which partially or completely 
    uncovers the fuel, is a beyond-design-basis event with a very low 
    probability of occurrence.
        In a letter dated May 15, 1998, the licensee submitted analyses for 
    a complete loss of inventory and several partial loss-of-inventory 
    events within the spent fuel pool. That analysis showed that a partial 
    draindown was more severe than a complete draindown for the licensee's 
    plant. For this case, only 5.5 feet of the active fuel is covered by 
    water. The licensee calculated that it would take 30 hours for the 
    cladding to heat up to 827  deg.C. However, the staff reviewed the 
    calculations and determined that the bounding scenario would be one 
    with the active fuel totally uncovered and water blocking the assembly 
    lower inlet so that no natural circulation flowpath exists. The staff 
    calculated that, for this case, as of August 1, 1998, it would take 
    approximately 10 hours for the hottest location in the highest power 
    assembly to reach 900  deg.C. The heatup time was calculated assuming 
    an adiabatic heatup of a fuel rod and using conservative decay heat 
    assumptions. An adiabatic heatup is defined as one in which all heat 
    generated is retained in the system, with no heat loss to the 
    surroundings. This definition corresponds to a physical situation in 
    which the spent fuel pool water is lost, no cooling mechanism is 
    available, and the fuel is surrounded by a perfect insulator. The staff 
    considers that this scenario would be bounding for any loss-of-
    inventory scenario since any other scenario would have some heat 
    removal from the assembly and a longer heatup time. Consequently, the 
    staff determined that, in view of the low likelihood of the bounding 
    scenario, and the time elapsed since the shutdown of the facility, 
    there would be sufficient time for mitigative actions and, if 
    necessary, offsite protective measures to be initiated after a 
    postulated loss of water and before a postulated release of 
    radioactivity resulting from spent fuel overheating.
        In the event that spent fuel pool water inventory is lost more 
    gradually through the method discussed above or through some other 
    means, such as a siphon or liner leak, plant personnel have various 
    methods for detecting the loss of inventory. The staff reviewed these 
    methods, which include indicators to alert and assist in identifying 
    any loss of coolant inventory. The design includes a low coolant level 
    indicator and an area radiation monitor, both of which alarm in the 
    control room. Although not credited for accident mitigation, these 
    alarms provide methods to alert the operators to a loss-of-inventory 
    event. In the DSAR, the licensee also states that there are several 
    sources of makeup water to the spent fuel pool. Among these sources are 
    the normal sources of makeup water from the refueling water storage 
    tank, demineralizer water from the primary water storage tank, 
    emergency sources from the fire water system, and potable water from 
    the town of Wiscasset water supply system. On the basis of indicators 
    and alarms available to plant personnel and the availability of makeup 
    sources to restore a gradual loss of coolant, the staff finds it 
    reasonable to expect that fuel uncovery as a result of a gradual loss 
    of coolant scenario is highly unlikely.
        Although the event is unlikely, the licensee evaluated the dose 
    consequences of both partial and complete spent fuel pool draindown. 
    Water and the concrete pool structure provide radiation shielding on 
    the sides of the pool. However, water alone accounts for most of the 
    shielding above the spent fuel. A loss of shielding above the fuel 
    could increase the radiation levels at the exclusion area boundary 
    (EAB) due to the scattering of gamma rays streaming up out of the pool. 
    The licensee postulated a partial pool draindown event resulting from a 
    break in the pool cooling system piping, concurrent with a failure of 
    the associated anti-syphon device. The licensee assumed that additional 
    pool water was lost through pool boiling for the following four days 
    before effective corrective actions could be taken to reestablish 
    adequate pool water level. The licensee calculated that the dose rate 
    was 0.00076 rem per hour at the EAB. In addition the licensee 
    calculated the postulated offsite dose rates in the event of a complete 
    draindown of the spent fuel pool (a beyond-design-basis event). 
    Assuming only one year of
    
    [[Page 48770]]
    
    radioactive decay and a site boundary distance of 610 meters, the 
    complete draindown resulted in a postulated dose rate of 0.01 rem per 
    hour. The licensee's calculated dose rate indicates it would take 4.1 
    days for this event to exceed the EPA early-phase PAG of 1 rem.
        The staff concludes that the licensee's request for an exemption 
    from certain requirements of 10 CFR 50.54(q), 10 CFR 50.47(b) and (c), 
    and Appendix E to Part 50 is acceptable in view of the greatly reduced 
    offsite radiological consequences associated with the current plant 
    status. The staff finds that the postulated dose to the general public 
    from any reasonably conceivable accident would not exceed EPA PAGs and, 
    for the bounding accident, the length of time available gives 
    confidence that offsite measures for the public could be taken without 
    preplanning. The staff finds acceptable the licensee's commitment in 
    the DSAR to establish administrative controls to ensure that calculated 
    offsite doses from potential decommissioning accidents do not exceed 
    those determined for a spent resin cask drop accident. Therefore, the 
    staff concludes that the requirement that emergency plans meet all of 
    the standards of 10 CFR 50.47(b) and all of the requirements of 
    Appendix E to Part 50 is not now warranted at Maine Yankee and an 
    exemption from the requirements for offsite emergency planning is 
    acceptable.
    
    IV
    
        The NRC staff has completed its review of the licensee's request 
    for an exemption from the requirements of 10 CFR 50.47(c)(2) and from 
    the requirements of 10 CFR 50.54(q), that emergency plans must meet all 
    of the standards of 10 CFR 50.47(b) and all the requirements of 
    Appendix E to 10 CFR part 50. The standards of 10 CFR 50.47(b) and the 
    requirements of Appendix E to 10 CFR part 50 that remain in effect are 
    listed in Attachment II to the licensee's letter dated June 29, 1998. 
    On the basis of its review, the NRC staff finds that the postulated 
    dose to the general public from any reasonably conceivable accident 
    would not exceed EPA PAGs and, for the bounding accident, the length of 
    time available provides confidence that offsite measures for the public 
    could be taken without preplanning. The analyses submitted by the 
    licensee are consistent with the commitment made in its DSAR, which 
    stated that any decommissioning activities will be analyzed and 
    administrative controls will be established to ensure that the 
    calculated offsite doses do not exceed those determined for the spent 
    resin cask drop accident. The staff finds the exemption from two 
    requirements, 10 CFR 50.47(b)(9) and 10 CFR 50 Appendix E.IV.A.4, 
    acceptable on the basis of the licensee's commitment to continue to 
    maintain capabilities for dose assessment and personnel equivalent to 
    those described in section 7.0 of the draft Defueled Emergency Plan 
    provided in Attachment III to the licensee's letter dated November 6, 
    1997. The information developed from the capability would be used to 
    determine whether offsite measures for the general public would be 
    appropriate. Maine Yankee will continue to maintain an onsite emergency 
    preparedness organization capable of responding to the consequences of 
    radiological events still possible at the site. Thus, the underlying 
    purpose of the regulations will not be adversely affected by 
    eliminating offsite emergency planning activities or reducing the scope 
    of onsite emergency planning.
        For the foregoing reasons, the Commission has determined that, 
    pursuant to 10 CFR 50.12, elimination of offsite emergency planning 
    activities will not present an undue risk to public health and safety 
    and is consistent with common defense and security. Further, special 
    circumstances are present as stated in 10 CFR 50.12(a)(ii). Pursuant to 
    10 CFR 51.32, the Commission has determined that this exemption will 
    not have a significant effect on the quality of the human environment 
    (63 FR 43968, August 17, 1998).
        This exemption is effective upon issuance.
    
        Dated at Rockville, Maryland this 3rd day of September 1998.
    
        For the Nuclear Regulatory Commission.
    Samuel J. Collins,
    Director, Office of Nuclear Reactor Regulation.
    [FR Doc. 98-24461 Filed 9-10-98; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
09/11/1998
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
98-24461
Pages:
48768-48770 (3 pages)
Docket Numbers:
Docket No. 50-309
PDF File:
98-24461.pdf