95-22995. Pilgrim Nuclear Power Plant; Notice of Withdrawal of Amendment to Facility Operating License  

  • [Federal Register Volume 60, Number 179 (Friday, September 15, 1995)]
    [Notices]
    [Page 47969]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 95-22995]
    
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket No. 50-293]
    
    
    Pilgrim Nuclear Power Plant; Notice of Withdrawal of Amendment to 
    Facility Operating License
    
        The U.S. Nuclear Regulatory Commission (the Commission) has granted 
    the request by Boston Edison Company (the licensee) to withdraw its 
    November 22, 1995, application for an amendment to Facility Operating 
    License No. DRP-35, for the operation of the Pilgrim Nuclear Power 
    Station, located in Plymouth, Massachusetts. Notice of Consideration of 
    Issuance of this amendment was published in the Federal Register on 
    February 1, 1995, (95 FR 6297).
        The purpose of the licensee's amendment request was to revise the 
    Technical Specifications to increase the emergency diesel generator 
    allowed out-of-service time from 72 hours to 7 days.
        Subsequently, the licensee informed the staff that the amendment 
    would be integrated with proposed changes to the Containment Cooling 
    System and resubmitted at a later date. Thus, the amendment application 
    is considered to be withdrawn by the licensee.
        These documents are available for public inspection at the 
    Commission's Public Document Room, the Gelman Building, 2120 L Street, 
    NW., Washington, DC, and at the Local Public Document Room located at 
    the Plymouth Public Library, 11 North Street, Plymouth, Massachusetts 
    02360.
    
        Dated at Rockville, Maryland, this 8th day of September 1995.
    
        For the Nuclear Regulatory Commission.
    Ronald B. Eaton,
    Senior Project Manager, Project Directorate I-1, Division of Reactor 
    Projects--I/II, Office of Nuclear Reactor Regulation.
    [FR Doc. 95-22995 Filed 9-14-95; 8:45 am]
    BILLING CODE 7590-01-P
    
    

Document Information

Published:
09/15/1995
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
95-22995
Pages:
47969-47969 (1 pages)
Docket Numbers:
Docket No. 50-293
PDF File:
95-22995.pdf