2010-23226. Columbia Gas Transmission, LLC; Notice of Application  

  • Start Preamble September 9, 2010.

    Take notice that on August 26, 2010, Columbia Gas Transmission, LLC (Columbia), 1700 MacCorkle Avenue, SE., Charleston, West Virginia 25314, filed an application in Docket No. CP10-492-000 pursuant to sections 7(b) and 7(c) of the Natural Gas Act and Part 157 of the Commission's Regulations, for a certificate of public convenience and necessity to replace, operate, abandon and maintain its existing natural gas pipeline system in Pike County, Pennsylvania, and Orange County, New York as a result of the age and condition of the existing pipeline (the Projects), as more fully detailed in the application. Specifically, Columbia proposes to (1) abandon and remove the 14-inch-diameter Line 1278 and Line K pipelines, and replace it with approximately 16.08 miles of 20-inch-diameter pipeline and 0.44 mile of two 10-inch-diameter parallel pipelines; (2) abandon in place the existing 0.06 miles of 4-inch-diameter Line U pipeline and replace it with 0.08 miles of relocated 4-inch-diameter pipeline; (3) abandon and remove the Sparrowbush Compressor Station; (4) abandon in place 0.08 mile of 8-inch-diameter Line 1842; and (5) perform minor valve, piping, and regulator modifications to the Milford Compressor Station. In all, Columbia proposes to abandon by replacement approximately 16.39 miles of natural gas pipeline for the Projects. The proposed project would enable Columbia to restore the historical design operating pressures and enhance the reliability and flexibility of its system, all as more fully set forth in the application. The application is on file with the Commission and open to public inspection. This filing is available for review at the Commission in the Public Reference Room or may be viewed on the Commission's Web site at http://www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, contact (202) 502-8659.

    Any questions regarding this application should be directed to Fredric J. George, Lead Counsel, Columbia Gas Transmission, LLC, P.O. Box 1273, Charleston, West Virginia 25325-1273; telephone 304-357-2359, fax 304-357-3206.

    Columbia states that by letter dated February 3, 2010, in Docket No. PF10-6-000, the Commission's Office of Energy Projects granted Columbia's January 26, 2010, request to utilize the National Environmental Policy Act (NEPA) Pre-Filing Process for the Projects. Columbia has also submitted an applicant-prepared Draft Environmental Assessment that was prepared during the Pre-Filing Process that was included with this application. Now, as of the filing of this application on August 26, 2010, the NEPA Pre-Filing Process for this project has ended. From this time forward, this proceeding will be conducted in Docket No. CP10-492-000, as noted in the caption of this notice.

    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission's public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff's issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission's public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all Federal authorizations within 90 days of the date of issuance of the Commission staff's FEIS or EA.

    There are two ways to become involved in the Commission's review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below, file with the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission's Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 14 copies of filings made with the Commission and must mail a copy to the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding.

    However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission's rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest.

    Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Start Printed Page 57013Secretary of the Commission. Environmental commentors will be placed on the Commission's environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission's environmental review process. Environmental commentors will not be required to serve copies of filed documents on all other parties. However, the non-party commentors will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission's final order.

    The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the “eFiling” link at http://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy regulatory Commission, 888 First Street, NE., Washington, DC 20426.

    This filing is accessible on-line at http://www.ferc.gov, using the “eLibrary” link and is available for review in the Commission's Public Reference Room in Washington, DC. There is an “eSubscription” link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For TTY, call (202) 502-8659.

    Comment Date: September 30, 2010.

    Start Signature

    Kimberly D. Bose,

    Secretary.

    End Signature End Preamble

    [FR Doc. 2010-23226 Filed 9-16-10; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Comments Received:
0 Comments
Effective Date:
9/30/2010
Published:
09/17/2010
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2010-23226
Dates:
September 30, 2010.
Pages:
57012-57013 (2 pages)
Docket Numbers:
Docket Nos. CP10-492-000, PF10-6-000
EOCitation:
of 2010-09-09
PDF File:
2010-23226.pdf