96-23996. Lake Dorothy Hydro, Inc.; Notice of Scoping Pursuant to the National Environmental Policy Act of 1969, Notice To File Additional Studies  

  • [Federal Register Volume 61, Number 183 (Thursday, September 19, 1996)]
    [Notices]
    [Pages 49318-49319]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-23996]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Project No. 11556 Alaska]
    
    
    Lake Dorothy Hydro, Inc.; Notice of Scoping Pursuant to the 
    National Environmental Policy Act of 1969, Notice To File Additional 
    Studies
    
    September 13, 1996.
        The Energy Policy Act of 1992, allows applicants to prepare their 
    own draft environmental assessment (EA) for hydropower projects and 
    file it with the Federal Energy Regulatory Commission (Commission) 
    along with their license application as part of the ``applicant-
    prepared EA'' process. Lake Dorothy Hydro, Inc. (LDHI) intends to 
    prepare an EA to file with the Commission for the Lake Dorothy 
    Hydroelectric Project No. 11556. LDHI will hold two public scoping 
    meetings, pursuant to the National Environmental Policy Act of 1969, to 
    identify the scope of environmental issues that should be analyzed in 
    the EA.
    
    Scoping Meetings
    
        The times and locations of the two scoping meetings are:
    
    Agency Meeting
    
        Date: Wednesday, October 9, 1996.
        Place: CBJ Juneau Public Library, 292 Marine Way, Juneau, AK.
        Time: 2:00 pm.
    
    Public Meeting
    
        Date: Wednesday, October 9, 1996.
        Place: CBJ Juneau Public Library, 292 Marine Way, Juneau, AK.
        Time: 6:30 pm.
        At the scoping meetings, LDHI will (1) summarize the environmental 
    issues tentatively identified for analysis in the EA; (2) solicit from 
    the meeting participants all available information, especially 
    quantified data, on the resources at issue; and (3) encourage 
    statements from experts and the public on issues that should be 
    analyzed in the EA.
        Although LDHI's intent is to prepare an EA, there is the 
    possibility that an Environmental Impact Statement (EIS) may be 
    required. Nevertheless, these meetings will satisfy the NEPA scoping 
    requirements, irrespective of whether an EA or EIS is issued by the 
    Commission.
        All interested individuals, organizations, and agencies are invited 
    and encouraged to attend either or both meetings to assist in 
    identifying and clarifying the scope of environmental issues that 
    should be analyzed in the EA.
        To help focus discussions at the meetings, LDHI prepared and 
    distributed Scoping Document 1 for this project. Copies of this scoping 
    document can be obtained by calling Sue Tinney, Licensing Coordinator, 
    of Tinney Associates at (907) 364-2233, or can be obtained directly at 
    either meeting.
    
    Site Visit
    
        LDHI will also conduct a site visit for this project on Tuesday, 
    October 8, 1996. Site visit participants will meet at Temsco 
    Helicopters, Maplesden Way (near the Juneau International Airport) at 
    10:00 am. Those planning to attend the site visit must contact Ms. 
    Helen Davies of LDHI at (907) 463-6315 before October 1, 1996.
    
    Meeting Procedures
    
        The meetings will be conducted according to the procedures used at 
    Commission scoping meetings. Because this meeting will be a NEPA 
    scoping meeting, the Commission will not conduct another NEPA scoping 
    meeting when the application and draft EA are filed with the 
    Commission.
        Both meetings will be recorded by a stenographer, and thus will 
    become a part of the formal record of the proceedings for this project.
        Those who choose not to speak may instead submit written comments 
    on the project. These comments should be mailed to Mr. Corry 
    Hildenbrand, Lake Dorothy Hydro, Inc., 889 South Franklin, Juneau, AK 
    99801. All correspondence should clearly show the following caption on 
    the first page: Scoping Comments, Lake Dorothy Project, FERC No. 11556, 
    Alaska.
    
    Additional Studies
    
        Under section 4.32(b)(7) of the Commission's Regulations, if any 
    agency, Indian Tribe, special interest group, or individual thinks that 
    the applicant should conduct an additional scientific study to form an 
    adequate factual basis for a complete analysis of the project's merits, 
    they must request that study within 60 days of the filing of the 
    license application.
        For the Lake Dorothy Project, however, LDHI requested waiver of 
    section 4.32(b)(7) of the regulations to accommodate their preparation 
    of the Preliminary Draft EA. The waiver has been granted, so the 
    additional studies request opportunity will be afforded now. Therefore, 
    all requests for studies must be filed by November 8, 1996, which would 
    be 30 days after the scoping meetings.
        The study requests, which must conform to section 4.32(b)(7) of the 
    regulations, should clearly identify the following on the first page:
    
    Lake Dorothy Hydroelectric Project (FERC No. 11556).
    
        The requests should then be served on the following two parties:
    
    Mr. Corry V. Hildenbrand, President, Lake Dorothy Hydro, Inc., 889 
    South Franklin, Juneau, Alaska 99801.
    Lois D. Cashell, Secretary, Federal Energy Regulatory Commission, 888 
    First Street, N.E., Washington, DC 20426.
    
        For further information, please contact Mr. Corry Hildenbrand at 
    (907)
    
    [[Page 49319]]
    
    463-6315, or Mike Henry of the Commission at (503) 326-5858 ext. 224.
    Linwood A. Watson, Jr.,
    Acting Secretary.
    [FR Doc. 96-23996 Filed 9-18-96; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
09/19/1996
Department:
Energy Department
Entry Type:
Notice
Document Number:
96-23996
Dates:
Wednesday, October 9, 1996.
Pages:
49318-49319 (2 pages)
Docket Numbers:
Project No. 11556 Alaska