2014-22368. Defense Federal Acquisition Regulation Supplement: Multiyear Contracts-Statutory References and Cancellation Ceiling Threshold (DFARS Case 2014-D019)
-
Start Preamble
AGENCY:
Defense Acquisition Regulations System, Department of Defense (DoD).
ACTION:
Proposed rule.
SUMMARY:
DoD is proposing to amend the Defense Federal Acquisition Regulation Supplement to update the cancellation ceiling threshold for multiyear contracts and to correct statutory references.
DATES:
Comment date: Comments on the proposed rule should be submitted in writing to the address shown below on or before November 18, 2014, to be considered in the formation of a final rule.
ADDRESSES:
Submit comments identified by DFARS Case 2014-D019, using any of the following methods:
○ Regulations.gov: http://www.regulations.gov. Submit comments via the Federal eRulemaking portal by entering “DFARS Case 2014-D019” under the heading “Enter keyword or ID” and selecting “Search.” Select the link “Submit a Comment” that corresponds with “DFARS Case 2014-D019.” Follow the instructions provided at the “Submit a Comment” screen. Please include your name, company name (if any), and “DFARS Case 2014-D019” on your attached document.
○ Email: osd.dfars@mail.mil. Include DFARS Case 2014-D019 in the subject line of the message.
○ Fax: 571-372-6094.
○ Mail: Defense Acquisition Regulations System, Attn: Ms. Jennifer Hawes, OUSD(AT&L)DPAP/DARS, Room 3B941, 3060 Defense Pentagon, Washington, DC 20301-3060.
Comments received generally will be posted without change to http://www.regulations.gov,, including any personal information provided. To confirm receipt of your comment(s), please check www.regulations.gov,, approximately two to three days after submission to verify posting (except allow 30 days for posting of comments submitted by mail).
Start Further InfoFOR FURTHER INFORMATION CONTACT:
Jennifer Hawes, Defense Acquisition Regulations System, OUSD(AT&L)DPAP/DARS, Room 3B941, 3060 Defense Pentagon, Washington, DC 20301-3060. Telephone 571-372-6115.
End Further Info End Preamble Start Supplemental InformationSUPPLEMENTARY INFORMATION:
I. Background
DoD is proposing to revise the DFARS regarding multiyear contracts to correct statutory references and to update the cancellation ceiling threshold at DFARS 217.170(e)(1)(iv) and (e)(5) for consistency with the Federal Acquisition Regulation (FAR). Currently, DFARS 217.170(e)(1)(iv) requires DoD to provide notification to Start Printed Page 56332the congressional defense committees at least 30 days before entering into a multiyear contract that includes a cancellation ceiling in excess of $100 million. DoD issued a final rule (75 FR 45072), effective October 1, 2010, to implement the requirements of section 807 of the National Defense Authorization Act for Fiscal Year 2005 (Pub. L. 108-375) by escalating acquisition-related thresholds throughout the DFARS; however, the increase to the cancellation ceiling threshold at DFARS 217.170(e)(1)(iv) and (e)(5) was not included in the rule, resulting in a conflict with the cancellation ceiling threshold of $125 million identified at FAR 17.108(b).
II. Discussion and Analysis
The rule proposes to amend DFARS 217.170(e)(1)(iv) and (e)(5), redesignating paragraph (e) as paragraph (d), and to increase the cancellation ceiling threshold from $100 million to $125 million to ensure consistency with the FAR. This rule also corrects references to 10 U.S.C. 2306b, 10 U.S.C. 2306c, and section 8008a of Public Law 105-56 throughout DFARS subpart 217.1 and makes the following corrections regarding multiyear contracts for supplies:
- The language at DFARS 217.170(b), under the “General” section, applies only to the acquisition of property in accordance with 10 U.S.C. 2306b. This language is moved to a new paragraph (j) under DFARS 217.172, Multiyear contracts for supplies.
- The current language at 217.172(c) states that multiyear contracts in amounts exceeding $500 million must be specifically authorized by law and that a multiyear supply contract may be authorized by an appropriations act or a law other than an appropriations act. However, the language at 10 U.S.C. 2306b(i)(3), which addresses the acquisition of property, states that a multiyear contract in excess of $500 million must be specifically authorized by law in an act other than an appropriations act. In addition, 10 U.S.C. 2306b(l)(3) states that the head of the agency may not initiate a multiyear procurement contract for any system (or component thereof) if the value of the multiyear contract would exceed $500 million unless authority for the contract is specifically provided in an appropriations act. The language at 217.172(c) is corrected and a new paragraph regarding multiyear procurement contracts is added.
III. Executive Orders 12866 and 13563
Executive Orders (E.O.s) 12866 and 13563 direct agencies to assess all costs and benefits of available regulatory alternatives and, if regulation is necessary, to select regulatory approaches that maximize net benefits (including potential economic, environmental, public health and safety effects, distributive impacts, and equity). E.O. 13563 emphasizes the importance of quantifying both costs and benefits, of reducing costs, of harmonizing rules, and of promoting flexibility. This is not a significant regulatory action and, therefore, was not subject to review under section 6(b) of E.O. 12866, Regulatory Planning and Review, dated September 30, 1993. This rule is not a major rule under 5 U.S.C. 804.
IV. Regulatory Flexibility Act
DoD does not expect this proposed rule to have a significant economic impact on a substantial number of small entities within the meaning of the Regulatory Flexibility Act, 5 U.S.C. 601, et seq. However, an initial regulatory flexibility analysis has been performed and is summarized as follows:
This rule proposes to amend the DFARS regarding multiyear contracts to ensure consistency with the FAR and the underlying statutes.
The objective of this rule is to increase the cancellation ceiling threshold at DFARS 217.170(e)(1)(iv) from $100 million to $125 million to ensure consistency with the threshold at FAR 17.108(b). In addition, this rule will correct references to 10 U.S.C. 2306b, 10 U.S.C. 2306c, and section 8008(a) of Public Law 105-56 throughout DFARS subpart 217.1 and make the following clarifications: (1) A multiyear contract for supplies in excess of $500 million must be specifically authorized by law in an act other than an appropriations act in accordance with 10 U.S.C. 2306b(i)(3); and, (2) a multiyear procurement contract for any system (or component thereof) with a value greater than $500 million must be specifically authorized in an appropriations act 10 U.S.C. 2306b(i)(3).
Small businesses will not be affected by this rule. This rule will impact procedures and authorities internal to the Government for multiyear contracts that require a cancellation ceiling up to $125 million or are valued in excess of $500 million and are for supplies.
This rule does not add any new information collection requirements. The rule does not duplicate, overlap, or conflict with any other Federal rules. No alternatives were identified that will accomplish the objectives of the rule.
DoD invites comments from small business concerns and other interested parties on the expected impact of this rule on small entities.
DoD will also consider comments from small entities concerning the existing regulations in subparts affected by this rule in accordance with 5 U.S.C. 610. Interested parties must submit such comments separately and should cite 5 U.S.C. 610 (DFARS Case 2014-D019), in correspondence.
V. Paperwork Reduction Act
The rule does not contain any information collection requirements that require the approval of the Office of Management and Budget under the Paperwork Reduction Act (44 U.S.C. chapter 35).
Start List of SubjectsList of Subjects in 48 CFR Part 217
- Government procurement
Manuel Quinones,
Editor, Defense Acquisition Regulations System.
Therefore, 48 CFR part 217 is proposed to be amended as follows:
Start PartPART 217—SPECIAL CONTACTING METHODS
End Part Start Amendment Part1. The authority citation for 48 CFR part 217 continues to read as follows:
End Amendment Part[Amended]2. Amend section 217.103, in the definition for “Military installation,” by removing “( 10 U.S.C. 2801(c)(2))” and adding “(10 U.S.C. 2801(c)(4))” in its place.
End Amendment Part Start Amendment Part3. Amend section 217.170 by—
End Amendment Part Start Amendment Parta. Removing paragraph (b);
End Amendment Part Start Amendment Partb. Redesignating paragraphs (c),(d), and (e) as paragraphs (b) (c), and (d), respectively;
End Amendment Part Start Amendment Partc. Revising newly redesignated paragraphs (d)(1)(ii), (iii), and (iv); and
End Amendment Part Start Amendment Partd. In newly redesignated paragraph (d)(5), removing “$100 million” and adding “$125 million” in its place.
End Amendment PartThe revisions read as follows:
General.* * * * *(d)(1) * * *
(ii) Employ economic order quantity procurement in excess of $20 million in any one year of the contract (see 10 U.S.C. 2306b(l)(1)(B)(i)(I) and section 8008(a) of Pub. L. 105-56 and similar sections in subsequent DoD appropriations acts);
(iii) Involve a contract for advance procurement leading to a multiyear contract that employs economic order quantity procurement in excess of $20 million in any one year (see 10 U.S.C. 2306b(l)(1)(B)(ii) and section 8008(a) of Start Printed Page 56333Pub. L. 105-56 and similar sections in subsequent DoD appropriations acts); or
(iv) Include a cancellation ceiling in excess of $125 million (see 10 U.S.C. 2306c(d)(4) and 10 U.S.C. 2306b(g)(1)).
* * * * *[Amended]4. Amend section 217.171 by—
End Amendment Part Start Amendment Parta. In the introductory text of paragraph (a), removing “( 10 U.S.C. 2306c)” and adding “(10 U.S.C. 2306c(a))” in its place;
End Amendment Part Start Amendment Partb. In paragraph (a)(5)(iii), adding “( 10 U.S.C. 2306c(b))” at the end of the sentence, before the period;
End Amendment Part Start Amendment Partc. In paragraph (b)(3), adding “( 10 U.S.C. 2306c(c))” at the end of the sentence, before the period;
End Amendment Part Start Amendment Partd. In paragraph (c)(3), adding “( 10 U.S.C. 2306c(a))” at the end of the sentence, before the period; and
End Amendment Part Start Amendment Parte. In paragraph (d), removing “( 10 U.S.C. 2306(c))” and adding “(10 U.S.C. 2306c(d)(2))” in its place.
End Amendment Part Start Amendment Part5. Amend section 217.172 by—
End Amendment Part Start Amendment Parta. Revising paragraph (c);
End Amendment Part Start Amendment Partb. Redesignating paragraphs (d) through (h) as paragraphs (e) through (i), respectively;
End Amendment Part Start Amendment Partc. Adding a new paragraph (d);
End Amendment Part Start Amendment Partd. In newly redesignated paragraph (f)(1), adding a parenthesis to close the parenthetical phrase “(when entered into or extended)” and removing “( 10 U.S.C. 2306b(1)(5))” and adding “(10 U.S.C. 2306b(l)(5))” in its place.
End Amendment Part Start Amendment Parte. In newly redesignated paragraph (f)(2), removing the parenthetical reference “( 10 U.S.C. 2306b(a)(l)(7))”;
End Amendment Part Start Amendment Partf. In newly redesignated paragraph (g)(1), adding the parenthetical reference “( 10 U.S.C. 2306b(h)(1))” before the semicolon;
End Amendment Part Start Amendment Partg. In newly redesignated paragraph (g)(2), adding the parenthetical reference “( 10 U.S.C. 2306b(h)(2))” at the end of the first sentence, before the period;
End Amendment Part Start Amendment Parth. In newly redesignated paragraph (h)(2)(vii)—
End Amendment Part Start Amendment Parti. Adding the parenthetical reference “( 10 U.S.C. 2306b(i)(1)(G))” at the end of the first sentence before the period, and removing it from the end of the second sentence; and
End Amendment Part Start Amendment Partii. Removing “USD(C)(P/B)” and adding “OUSD(C)(P/B)” in its place.
End Amendment Part Start Amendment Parti. In newly redesignated paragraph (h)(2)(viii) introductory text, removing “USD(C)(P/B)” and adding “OUSD(C)(P/B)” in its place.
End Amendment Part Start Amendment Partj. In newly redesignated paragraph (h)(8) introductory text, removing the parenthetical reference “( 10 U.S.C. 2306b(i)(2))”; and
End Amendment Part Start Amendment Partk. Adding a new paragraph (j).
End Amendment PartThe revisions and additions read as follows:
Multiyear contracts for supplies.* * * * *(c) Multiyear contracts in amounts exceeding $500 million must be specifically authorized by law in an act other than an appropriations act (10 U.S.C. 2306b(i)(3)).
(d) The head of an agency may not initiate a multiyear procurement contract for any system (or component thereof) if the value of the multiyear contract would exceed $500 million unless authority for the contract is specifically provided in an appropriations act (10 U.S.C. 2306b(l)(3)).
* * * * *(j) Any requests for increased funding or reprogramming for procurement of a major system under a multiyear contract shall be accompanied by an explanation of how the request for increased funding affects the determinations made by the Secretary of Defense under 217.172(g)(2) (10 U.S.C. 2306b(m)).
[FR Doc. 2014-22368 Filed 9-18-14; 8:45 am]
BILLING CODE 5001-06-P
Document Information
- Published:
- 09/19/2014
- Department:
- Defense Acquisition Regulations System
- Entry Type:
- Proposed Rule
- Action:
- Proposed rule.
- Document Number:
- 2014-22368
- Pages:
- 56331-56333 (3 pages)
- RINs:
- 0750-AI37: Multiyear Contracts--Statutory References and Cancellation Ceiling Threshold (DFARS Case 2014-D019)
- RIN Links:
- https://www.federalregister.gov/regulations/0750-AI37/multiyear-contracts-statutory-references-and-cancellation-ceiling-threshold-dfars-case-2014-d019-
- Topics:
- Government procurement
- PDF File:
- 2014-22368.pdf
- CFR: (4)
- 48 CFR 217.103
- 48 CFR 217.170
- 48 CFR 217.171
- 48 CFR 217.172