2024-21294. Ketchikan Public Utilities; Notice of Intent To Prepare an Environmental Assessment and Revising the Processing Schedule  

  • Milestone Target date
    Commission issues EA December 2024.1
    Comments on EA January 2024.
    1  The Council on Environmental Quality's (CEQ) regulations under 40 CFR 1501.10(b)(1) (2023) require that EAs be completed within 1 year of the federal action agency's decision to prepare an EA. See National Environmental Policy Act, 42 U.S.C. 4321 et seq., as amended by section 107(g)(1)(B)(iii) of the Fiscal Responsibility Act of 2023, Pub. L. 118-5, 4336a, 137 Stat. 42.

Document Information

Published:
09/19/2024
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2024-21294
Pages:
76823-76824 (2 pages)
Docket Numbers:
Project No. 1922-052