[Federal Register Volume 59, Number 170 (Friday, September 2, 1994)]
[Notices]
[Page 0]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 94-21782]
[[Page Unknown]]
[Federal Register: September 2, 1994]
=======================================================================
-----------------------------------------------------------------------
ENVIRONMENTAL PROTECTION AGENCY
[ER-FRL-4714-9]
Environmental Impact Statements and Regulations; Availability of
EPA Comments
Availability of EPA comments prepared August 15, 1994 Through
August 19, 1994 pursuant to the Environmental Review Process (ERP),
under Section 309 of the Clean Air Act and Section 102(2)(C) of the
National Environmental Policy Act as amended. Requests for copies of
EPA comments can be directed to the Office of Federal Activities at
(202) 260-5076.
An explanation of the ratings assigned to Draft environmental
impact statements (EISs) was published in FR dated April 8, 1994 (59 FR
16807).
Draft EISs
ERP No. D-AFS-G65059-NM Rating EC2, Santa Fe Ski Area Master
Development Plan, Upgrading and Expansion, Special-Use-Permit, Sante Fe
National Forest, Espanola Ranger District, Santa Fe County, NM.
Summary: EPA requested additional information to: (1) Determine the
potential of the citizens' alternative in meeting the objectives of the
Santa Fe Ski Area Master Development Plan, (2) evaluate impacts from
year-round use of the Ski Area, (3) describe alpine wetland resources,
and (4) consideration of additional mitigation measures.
ERP No. D-COE-G30013-LA Rating EC2, West Bank of the Mississippi River
Hurricane Protection Plan, Implementation, east of the Harvey Canal,
New Orleans, LA.
Summary: EPA requested that additional information and analysis be
provided in the Final EIS on the following areas: (1) secondary and
cumulative effects, (2) description of remaining natural resources
within the project area, and (3) the basis for using preservation as
mitigation for impacts to bottomland hardwoods and cypress swamps.
Final EISs
ERP No. F-AFS-L65224-OR, Newberry Geothermal Pilot Project,
Construction and Operation of a 33-megawatt Power Plant, Approvals,
Deschutes National Forest, Fort Rock Ranger District, Deschutes County,
OR.
Summary: Review of the Final EIS has been completed and the project
found to be satisfactory.
ERP No. F-DOE-L03007-OR, Hermiston Generating Project, Construction of
a Gas-fired Cogeneration Power Plant, Approval of Permits, Umatilla
County, OR.
Summary: The final EIS addressed EPA's concerns with this project.
ERP No. F-DOE-L08051-OR, Coyote Springs Cogeneration Project, General
Transmission Agreement Revision for Construction and Operations of the
Coyote Springs Interconnection, Implementation and COE Permits, Morrow
County, OR.
Summary: EPA had environmental concerns based on potential
significant cumulative CO2 emissions from coal and cogeneration
plants within the project area and because no further analysis was
provided of other possible gas pipeline alternatives that were
considered but dropped from further consideration.
ERP No. F-UAF-G11024-TX, Carswell Air Force Base (AFB) Disposal and
Reuse, Implementation, Tarrant County, TX.
Summary: EPA had no objections to the proposed project.
Dated: August 30, 1994.
Richard E. Sanderson,
Director, Office of Federal Activities.
[FR Doc. 94-21782 Filed 9-1-94; 8:45 am]