98-23594. Northeast Utilities Company, et al.; Electric Rate and Corporate Regulation Filings  

  • [Federal Register Volume 63, Number 170 (Wednesday, September 2, 1998)]
    [Notices]
    [Pages 46786-46787]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-23594]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    [Docket No. ER92-65-001, et al.]
    
    
    Northeast Utilities Company, et al.; Electric Rate and Corporate 
    Regulation Filings
    
    August 24, 1998.
        Take notice that the following filings have been made with the 
    Commission:
    
    1. Northeast Utilities Service Co.
    
    [Docket No. ER88-463-001, ER90-373-000, ER90-390-000, EL90-39-000]
    
        Take notice that on August 19, 1998, Northeast Utilities Service 
    Company, in compliance with the order of the Federal Energy Regulatory 
    Commission in Northeast Utilities Service Company, et al., 83 FERC 
    61,184 (1998), submitted revised pages to the transmission service 
    agreements filed in the above-referenced dockets. Copies of the 
    compliance filing were served on the customers taking service under the 
    agreements.
        Comment date: September 8, 1998, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    2. Northeast Utilities Service Company
    
    [Docket No. ER92-65-001]
    
        Taken notice that on August 19, 1998, Northeast Utilities Service 
    Company, in compliance with the order of the Federal Energy Regulatory 
    Commission in Northeast Utilities Service Company, et al., 83 FERC 
    61,184 (1998), submitted revised pages to the transmission service 
    agreement filed in the above-referenced docket. Copies of the 
    compliance filing were served on the customer taking service under the 
    agreement.
        Comment date: September 8, 1998, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    3. Northeast Utilities Service Company
    
    [Docket No. ER92-66-001]
    
        Take notice that on August 19, 1998, Northeast Utilities Service 
    Company, in compliance with the order of the Federal Energy Regulatory 
    Commission in Northeast Utilities Service Company, et al., 83 FERC 
    61,184 (1998), submitted revised pages to the transmission service 
    agreement filed in the above-referenced docket. Copies of the 
    compliance filing were served on the customer taking service under the 
    agreement.
        Comment date: September 8, 1998, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    4. Northeast Utilities Service Company
    
    [Docket No. ER93-219-004]
    
        Take notice that on August 19, 1998, Northeast Utilities Service 
    Company, in compliance with the order of the Federal Energy Regulatory 
    Commission in Northeast Utilities Service Company, et al., 83 FERC 
    61,184 (1998), submitted revised pages to the transmission service 
    agreement filed in the above-referenced docket. Copies of the 
    compliance filing were served on the
    
    [[Page 46787]]
    
    customer taking service under the agreement.
        Comment date: September 8, 1998, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    5. PJM Interconnection, L.L.C.
    
    Docket No. ER97-3189-011]
    
        Take notice that on August 19, 1998, PJM Interconnection, L.L.C. 
    (PJM), tendered for filing revised tariff sheets in compliance with the 
    Commission's order in PJM Interconnection, L.L.C., 84 FERC 61,051 
    (1998).
        PJM requests an effective date for the tariff revisions submitted 
    with the compliance filing of April 1, 1998, consistent with the 
    effective date of the revised PJM Tariff.
        Comment date: September 8, 1998, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    6. California Independent System Operator Corporation
    
    [Docket No. ER98-1310-001]
    
        Take notice that on August 19, 1998, the California Independent 
    System Operator Corporation (ISO), tendered for filing Amendment No. 2, 
    to the Participating Generator Agreement between the ISO and El Sequndo 
    Power, LLC (El Segundo), for acceptance by the Commission. The ISO 
    states that Amendment No. 2, modifies the Participating Generator 
    Agreement by extending the date by which El Segundo must obtain 
    certification by the ISO in accordance with Section 4.3.2 of the 
    agreement.
        The ISO requests waiver of the 60-day prior notice requirements, so 
    that Amendment No. 2, may become effective as of July 1, 1998.
        The ISO states that this filing has been served on all parties 
    listed on the Restricted Service List in the above-referenced docket.
        Comment date: September 8, 1998, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    7. California Independent System Operator Corporation
    
    [Docket No. ER98-1933-001]
    
        Take notice that on August 19, 1998, the California Independent 
    System Operator Corporation (ISO), tendered for filing Amendment No. 1, 
    to the Participating Generator Agreement between the ISO and Long Beach 
    Generation LLC (Long Beach) for acceptance by the Participating 
    Generator Agreement by extending the date by which Section 4.3.2 of the 
    agreement.
        The ISO states that this filing has been served on all parties 
    listed on the Restricted Service List in the above-referenced docket.
        Comment date: September 8, 1998, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    Standard Paragraphs
    
        E. Any person desiring to be heard or to protest said filing should 
    file a motion to intervene or protest with the Federal Energy 
    Regulatory Commission, 888 First Street, NE, Washington, DC 20426, in 
    accordance with Rules 211 and 214 of the Commission's Rules of Practice 
    and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such motions or 
    protests should be filed on or before the comment date. Protests will 
    be considered by the Commission in determining the appropriate action 
    to be taken, but will not serve to make protestants parties to the 
    proceeding. Any person wishing to become a party must file a motion to 
    intervene. Copies of these filings are on file with the Commission and 
    are available for public inspection.
    Linwood A. Watson, Jr.,
    Acting Secretary.
    [FR Doc. 98-23594 Filed 9-1-98; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
09/02/1998
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
98-23594
Dates:
September 8, 1998, in accordance with Standard Paragraph E at the end of this notice.
Pages:
46786-46787 (2 pages)
Docket Numbers:
Docket No. ER92-65-001, et al.
PDF File:
98-23594.pdf