96-24085. CNG Transmission Corporation; Notice of Request Under Blanket Authorization  

  • [Federal Register Volume 61, Number 184 (Friday, September 20, 1996)]
    [Notices]
    [Page 49442]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-24085]
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    [Docket No. CP96-782-000]
    
    
    CNG Transmission Corporation; Notice of Request Under Blanket 
    Authorization
    
    September 16, 1996.
        Take notice that on September 11, 1996, CNG Transmission 
    Corporation (CNG), 445 West Main Street, Clarksburg, West Virginia 
    26301, filed a request with the Commission in Docket No. CP96-782-000, 
    pursuant to Sections 157.205, and 157.212 of the Commission's 
    Regulations under the Natural Gas Act (NGA) for authorization to 
    Construct a new transportation tap and appurtenant facilities to serve 
    as a new delivery point to People Natural Gas Company (Peoples) 
    authorized in blanket certificate issued in Docket No. CP82-537-000, 
    all as more fully set forth in the request on file with the Commission 
    and open to public inspection.
        CNG proposes to construct minimal facilities and would transport 
    quantities of natural gas to be delivered to Peoples for redelivery to 
    Elliott Turbomachinery Co., Inc. located in Westmoreland County, 
    Pennsylvania. CNG states that CNG would then construct a six-inch hot 
    tap and valve on the TL-342 pipeline so that Peoples could redeliver 
    natural gas to Elliott. CNG further states that total cost of 
    construction would be fully reimbursed by Peoples.
        Any person or the Commission's staff may, within 45 days after the 
    Commission has issued this notice, file pursuant to Rule 214 of the 
    Commission's Procedural Rules (18 CFR 385.214) a motion to intervene or 
    notice of intervention and pursuant to Section 157.205 of the 
    Regulations under the NGA (18 CFR 157.205) a protest to the request. If 
    no protest is filed within the allowed time, the proposed activity 
    shall be deemed to be authorized effective the day after the time 
    allowed for filing a protest. If a protest is filed and not withdrawn 
    within 30 days after the time allowed for filing a protest, the instant 
    request shall be treated as an application for authorization pursuant 
    to Section 7 of the NGA.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 96-24085 Filed 9-19-96; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
09/20/1996
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
96-24085
Pages:
49442-49442 (1 pages)
Docket Numbers:
Docket No. CP96-782-000
PDF File:
96-24085.pdf