95-23510. Tuscarora Gas Transmission Company; Notice of Request Under Blanket Authorization
[Federal Register Volume 60, Number 184 (Friday, September 22, 1995)]
[Notices]
[Page 49272]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 95-23510]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
[Docket No. CP95-723-000]
Tuscarora Gas Transmission Company; Notice of Request Under
Blanket Authorization
September 18, 1995.
Take notice that on August 31, 1995, Tuscarora Gas Transmission
Company (Tuscarora), 6100 Neil Road, P.O. Box 30057, Reno, Nevada
89520-3057 filed in Docket No. CP95-723-000, a request pursuant to
Section 157.205 of the Commission's Regulations under the Natural Gas
Act (18 CFR 157.205) for authorization to construct and operate a new
tap and meter station in Washoe County, Nevada, to be known as the La
Posada Meter Site, for the delivery of gas to an existing customer,
Sierra Pacific Power Company (SPPC), under the blanket certificate
issued in Docket No. CP93-685-000, pursuant to Section 7(c) of the
Natural Gas Act, all as more fully set forth in the request which is on
file with the Commission and open to public inspection.
Tuscarora proposes to install an 8-inch tap and associated meter at
Milepost 217.2 on its mainline in Washoe County, Nevada to establish an
additional point for the delivery of natural gas to SPPC, for
redelivery and resale to consumers in Reno, Nevada and environs.
Tuscarora indicates that construction of the tap will enable SPPC to
receive up to 12,000 MMBtu of natural gas directly into the La Posada
area of its existing service area. Tuscarora asserts that the
construction of this additional delivery point is consistent with
Tuscarora's tariff and the total volume to be delivered to SPPC will
not exceed the volume previously authorized for delivery to SPPC.
Tuscarora states the projected cost of the proposed facilities is
$198,000.
Any person or the Commission's staff may, within 45 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to Sec. 157.205 of the
Regulations under the Natural Gas Act (18 CFR 157.205) a protest to the
request. If no protest is filed within the time allowed therefor, the
proposed activity shall be deemed to be authorized effective the day
after the time allowed for filing a protest. If a protest is filed and
not withdrawn within 30 days after the time allowed for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to Section 7 of the Natural Gas Act.
Lois D. Cashell,
Secretary.
[FR Doc. 95-23510 Filed 9-21-95; 8:45 am]
BILLING CODE 6717-01-M
Document Information
- Published:
- 09/22/1995
- Department:
- Energy Department
- Entry Type:
- Notice
- Document Number:
- 95-23510
- Pages:
- 49272-49272 (1 pages)
- Docket Numbers:
- Docket No. CP95-723-000
- PDF File:
-
95-23510.pdf