99-24618. Energy Alternatives, Inc., LLC, et al.; Electric Rate and Corporate Regulation Filings  

  • [Federal Register Volume 64, Number 183 (Wednesday, September 22, 1999)]
    [Notices]
    [Pages 51301-51305]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-24618]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    [Docket No. EG99-200-000, et al.]
    
    
    Energy Alternatives, Inc., LLC, et al.; Electric Rate and 
    Corporate Regulation Filings
    
    September 13, 1999.
        Take notice that the following filings have been made with the 
    Commission:
    
    1. Energy Alternatives, Inc.
    
    [Docket No. EG99-200-000]
    
        Take notice that on September 10, 1999, Energy Alternatives, Inc. 
    (Energy Alternatives) filed with the Federal Energy Regulatory 
    Commission an amended application for determination of exempt wholesale 
    generator status pursuant to Part 365 of the Commission's regulations.
        Energy Alternatives, a Minnesota corporation, is a wholly-owned 
    subsidiary of Midwest Energy Services, Inc., a Minnesota corporation, 
    which is a wholly-owned subsidiary of Dakota Electric Association, a 
    Minnesota cooperative corporation, which owns and operates an electric 
    distribution system.
        Energy Alternatives will own and operate generating facilities with 
    a nominal capacity of 20 MW located in distribution substations near 
    the cities of Lakeville, Miesville, and Hastings, Minnesota and in the 
    townships of Byllesby and Castle Rock in Dakota County, Minnesota, 
    consisting of ten 2 MW Caterpillar diesel reciprocating engine 
    generator sets, five 480 volt/12,470 volt step up transformers, and 
    associated circuit breakers. The facilities will be interconnected with 
    the distribution system of Dakota Electric Association.
        Comment date: October 4, 1999, in accordance with Standard 
    Paragraph E at the end of this notice. The Commission will limit its 
    consideration of comments to those that concern the adequacy or 
    accuracy.
    
    2. CMS Marketing, Services & Trading Company
    
    [Docket No. ER96-2350-019]
    
        Take notice that on September 7, 1999, CMS Marketing, Services and 
    Trading Company (CMS MST), tendered for filing an updated market power 
    analysis in accordance with the order issued by the Federal Energy 
    Regulatory Commission dated September 6, 1996 in Docket No. ER96-2350-
    000.
        Comment date: September 27, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    3. Murphy Oil USA, Inc.
    
    [Docket No. ER97-610-009]
    
        Take notice that on September 1, 1999, the above-mentioned power 
    marketer filed a quarterly report with the Commission in the above-
    mentioned proceeding for information only. This filing is available for 
    public inspection and copying in the Public Reference Room or on the 
    web at www.ferc.fed.us/online/rims.htm for viewing and downloading 
    (call 202-208-2222 for assistance).
    
    4. Avista Corporation Avista Energy, Inc. Spokane Energy, LLC
    
    [Docket Nos. ER99-1435-001, ER96-2408-015 and ER98-4336-004
    
        Take notice that on September 7, 1999, Avista Corporation and its 
    subsidiaries listed as Avista Energy, Inc., and Spokane Energy, LLC 
    collectively tendered for filing an updated market analysis as required 
    by the Commission's orders approving market based rates.
        Comment date: September 27, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    5. Virginia Electric and Power Company
    
    [Docket No. ER99-1886-000]
    
        Take notice that on September 8, 1999, Virginia Electric and Power 
    Company (Virginia Power) tendered for filing pursuant to Section 205 of 
    the Federal Power Act, 16 U.S.C. Section 824d, an amendment to its 
    February 22, 1999 and April 20, 1999 filings in the above referenced 
    docket number. Virginia Power's filings pertain to a Service Agreement 
    under the Company's Open Access Transmission Tariff with The Wholesale 
    Power Group for Long Term Firm Point-to-Point Transmission Service.
        Copies of this filing were served upon The Wholesale Power Group, 
    the Virginia State Corporation Commission and the North Carolina 
    Utilities Commission.
        Comment date: September 28, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    6. California Independent System Operator Corporation
    
    [Docket No. ER99-1971-004]
    
        Take notice that on September 8, 1999, the California Independent 
    System Operator Corporation (ISO), tendered for filing a Notice of 
    Implementation which specifies that the software required to implement 
    the portions of Amendment No. 14 to the ISO Tariff relating to Inter-
    Scheduling Coordinator Trades of Ancillary Services will be in place 
    for Ancillary Service bids submitted in the Day-Ahead Market on 
    Wednesday, September 15, 1999 for Trading Day Thursday, September 16, 
    1999.
        The ISO states that this filing has been served on all parties 
    listed on the official service list in the above-referenced docket.
        Comment date: September 28, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    7. Ameren Services Company
    
    [Docket Nos. ER99-3972-000 and ER99-4047-000]
    
        Take notice that on September 7, 1999, Ameren Services Company 
    (ASC), the transmission provider, tendered for filing changes to its 
    Transmission System Interconnection Agreements between ASC and Trigen-
    St. Louis Energy Corporation and Union Electric Development 
    Corporation. ASC asserts
    
    [[Page 51302]]
    
    that the purpose of the changes are to correct minor errors in the 
    Agreements.
        Comment date: September 27, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    8. Arizona Public Service Company
    
    [Docket No. ER99-4124-000]
    
        Take notice that on August 19, 1999, Arizona Public Service Company 
    (APS), tendered for filing an application for an order accepting its 
    revised Market Rate Tariff and approving the Code of Conduct governing 
    APS' relationship with its affiliate.
        Copies of this filing have been served upon customers taking 
    service under APS' Market Rate Tariff and the Arizona Corporation 
    Commission.
        Comment date: September 27, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    9. Tampa Electric Company
    
    [Docket No. ER99-4211-000]
    
        Take notice that on September 7, 1999, Tampa Electric Company 
    (Tampa Electric) tendered for filing an executed service agreement with 
    the Orlando Utilities Commission (OUC) under Tampa Electric's market-
    based sales tariff. The executed service agreement replaces the 
    unexecuted service agreement with OUC that Tampa Electric filed in this 
    docket on August 24, 1999.
        Tampa Electric renews its request that the service agreement be 
    made effective on July 25, 1999.
        Copies of the filing have been served on OUC and the Florida Public 
    Service Commission.
        Comment date: September 27, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    10. Fitchburg Gas and Electric Light Company
    
    [Docket No. ER99-4369-000]
    
        Take notice that on September 3, 1999, Fitchburg Gas and Electric 
    Light Company (Fitchburg), tendered for filing a service agreement 
    between Fitchburg and Reliant Energy Services, Inc., for service under 
    Fitchburg's Market-Based Power Sales Tariff. This Tariff was accepted 
    for filing by the Commission on September 25, 1997, in Docket No. ER97-
    2463-000.
        Fitchburg requests waiver of the 30-day period requirement and 
    requests an effective date of June 1, 1999 for the service agreement.
        Comment date: September 23, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    11. Unitil Power Corp.
    
    [Docket No. ER99-4370-000]
    
        Take notice that on September 3, 1999, Unitil Power Corp. (Unitil), 
    tendered for filing a service agreement between Unitil and Reliant 
    Energy Services, Inc. (Reliant), for service under Unitil's Market-
    Based Power Sales Tariff. This Tariff was accepted for filing by the 
    Commission on September 25, 1997, in Docket No. ER97-2460-000.
        Unitil requests a waiver of the 30-day filing period and requests 
    an effective date of June 1, 1999, for the service agreement.
        Comment date: September 23, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    12. PJM Interconnection, L.L.C.
    
    [Docket No. ER99-4371-000]
    
        Take notice that on September 3, 1999, PJM Interconnection, L.L.C. 
    (PJM), tendered for filing amendments to the PJM Open Access 
    Transmission Tariff (PJM Tariff) and the Amended and Restated Operating 
    Agreement of PJM Interconnection, L.L.C. (Operating Agreement) to 
    address (1) compensation for generators that PJM requests to reduce 
    output in emergencies, which will better enable PJM to manage voltage 
    or other problems that it may experience during peak conditions; (2) 
    modification of the determination of the hour at which annual zonal 
    peaks occur for billing purposes in order properly to reflect curtailed 
    loads; and (3) clarification of PJM's borrowing authority.
        PJM requests a waiver of the Commission's 60 day notice requirement 
    and an effective date of September 4, 1999, for the amendment 
    addressing compensation for generators, and an effective date of 
    November 3, 1999, which is sixty days after the date of this filing, 
    for the other amendments.
        Copies of this filing were served upon all PJM Members and the 
    state electric utility regulatory commissions in the PJM Control Area.
        Comment date: September 23, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    13. Virginia Electric and Power Company
    
    [Docket No. ER99-4372-000]
    
        Take notice that on September 3, 1999, Virginia Electric and Power 
    Company (Virginia Power), tendered for filing the following:
        1. Service Agreement for Firm Point-to-Point Transmission Service 
    by Virginia Electric and Power Company to TXU Energy Trading Company.
        2. Service Agreement for Non-Firm Point-to-Point Transmission 
    Service by Virginia Electric and Power Company to TXU Energy Trading 
    Company.
    
    The foregoing Service Agreements are tendered for filing under the Open 
    Access Transmission Tariff to Eligible Purchasers dated July 14, 1997. 
    Under the tendered Service Agreements, Virginia Power will provide 
    point-to-point service to the Transmission Customer under the rates, 
    terms and conditions of the Open Access Transmission Tariff.
        Virginia Power requests an effective date of September 3, 1999, the 
    date of filing of the Service Agreements.
        Copies of the filing were served upon TXU Energy Trading Company, 
    the Virginia State Corporation Commission and the North Carolina 
    Utilities Commission.
        Comment date: September 23, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    14. Central Illinois Public Service Company
    
    [Docket No. ER99-4373-000]
    
        Take notice that on September 3, 1999, Central Illinois Public 
    Service Company (CIPS), tendered for filing the Wholesale Voluntary 
    Curtailment Rider to the Service Agreement for Full Requirements 
    Service between CIPS and Mt. Carmel Public Utility Company (Mt. 
    Carmel). CIPS states that the Rider will allow Mt. Carmel and its 
    retail customers to participate in a voluntary curtailment program 
    similar to that applicable to its retail electric service customers.
        CIPS has proposed to make the Rider effective on September 9, 1999.
        Comment date: September 23, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    15. UtiliCorp United Inc.
    
    [Docket No. ER99-4374-000]
    
        Take notice that on September 3, 1999, UtiliCorp United, Inc. 
    (UtiliCorp), tendered for filing service agreements with Basin Electric 
    Power Cooperative for service under its Non-Firm Point-to-Point open 
    access service tariff for its operating divisions, Missouri Public 
    Service and WestPlains Energy-Kansas.
        Comment date: September 23, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    16. UtiliCorp United Inc.
    
    [Docket No. ER99-4375-000]
    
        Take notice that on September 3, 1999, UtiliCorp United Inc. 
    (UtiliCorp), tendered for filing service agreements with Basin Electric 
    Power Cooperative
    
    [[Page 51303]]
    
    for service under its short-term firm point-to-point open access 
    service tariff for its operating divisions, Missouri Public Service, 
    WestPlains Energy-Kansas and WestPlains Energy-Colorado.
        Comment date: September 23, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    17. Commonwealth Edison Company
    
    [Docket No. ER99-4376-000]
    
        Take notice that on September 3, 1999, Commonwealth Edison Company 
    (ComEd), tendered for filing a Non-Firm Transmission Service Agreement 
    with Edison Mission Marketing & Trading, Inc., (EMMT) and a Firm 
    Transmission Service Agreement with Wisconsin Electric Power Company 
    (WEPCO) under the terms of ComEd's Open Access Transmission Tariff 
    (OATT).
        ComEd requests an effective date of September 3, 1999, and 
    accordingly, seeks waiver of the Commission's notice requirements.
        Copies of this filing were served on EMMT and WEPCO.
        Comment date: September 23, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    18. South Carolina Electric & Gas Company
    
    [Docket No. ER99-4377-000]
    
        Take notice that on September 3, 1999, South Carolina Electric & 
    Gas Company (SCE&G), tendered for filing a service agreement 
    establishing New Horizon Electric Cooperative as a customer under the 
    terms of SCE&G's Negotiated Market Sales Tariff.
        SCE&G requests an effective date of one day subsequent to the date 
    of filing. Accordingly, SCE&G requests waiver of the Commission's 
    notice requirements.
        Copies of this filing were served upon New Horizon Electric 
    Cooperative and the South Carolina Public Service Commission.
        Comment date: September 23, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    19. Central Illinois Light Company
    
    [Docket No. ER99-4378-000]
    
        Take notice that on September 3, 1999, Central Illinois Light 
    Company (CILCO), 300 Liberty Street, Peoria, Illinois 61602, tendered 
    for filing with the Commission a substitute Open Access Transmission 
    Tariff to facilitate the retail access program initiated by the 
    Illinois deregulation legislation.
        CILCO requested an effective date of October 1, 1999.
        Copies of the filing were served on all affected customers, and the 
    Illinois Commerce Commission.
        Comment date: September 23, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    20. Virginia Electric and Power Company
    
    [Docket No. ER99-4382-000]
    
        Take notice that on September 3, 1999, Virginia Electric and Power 
    Company (Virginia Power), tendered for filing an assignment letter 
    indicating that Phibro Power LLC (Phibro Power) will replace Phibro 
    Inc. (PI) as the wholesale power customer in a Service Agreement dated 
    October 18, 1995 and originally filed under the Company's Power Sales 
    Tariff to Eligible Purchasers dated May 27, 1994. The original Service 
    Agreement was approved by the FERC in Docket No. ER96-248-000 in a 
    Letter Order dated December 8, 1995.
        Virginia Power requests an effective date of September 3, 1999, the 
    date of filing of the assignment letter.
        Copies of this filing were served upon Phibro Power, the Virginia 
    State Corporation Commission and the North Carolina Utilities 
    Commission.
        Comment date: September 23, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    21. Southern Company Services, Inc.
    
    [Docket No. ER99-4384-000]
    
        Take notice that on September 8, 1999, Southern Company Services, 
    Inc. filed with the Commission an initial Generator Backup Service 
    Tariff on its own behalf and as agent for Alabama Power Company, 
    Georgia Power Company, Gulf Power Company, Mississippi Power Company 
    and Savannah Electric and Power Company (the Southern Companies).
        Southern Companies state that pursuant to the tariff, they will 
    provide backup service for independent generators interconnecting with 
    the transmission system of Southern Companies to provide for 
    differences between scheduled generation and actual generation at a 
    generator's facility.
        Southern Companies have requested that the initial tariff be made 
    effective as of September 7, 1999.
        Comment date: September 28, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    22. Maine Public Service Company
    
    [Docket No. ER99-4385-000]
    
        Take notice that on September 7, 1999, Maine Public Service Company 
    (Maine Public), tendered for filing an executed Service Agreement for 
    short-term firm point-to-point transmission service under Maine 
    Public's open access transmission tariff with Entergy Power Marketing 
    Corp.
        Comment date: September 27, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    23. Maine Public Service Company
    
    [Docket No. ER99-4386-000]
    
        Take notice that on September 7, 1999, Maine Public Service Company 
    (Maine Public), tendered for filing an executed Service Agreement for 
    non-firm point-to-point transmission service under Maine Public's open 
    access transmission tariff with Entergy Power Marketing Corp.
        Comment date: September 27, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    24. Southern Indiana Gas and Electric Company
    
    [Docket No. ER99-4387-000]
    
        Take notice that on September 7, 1999, Southern Indiana Gas and 
    Electric Company (SIGECO) tendered for filing service agreements for 
    firm and non-firm transmission service under Part II of its 
    Transmission Services Tariff with Consumers Energy Company.
        Copies of the filing were served upon each of the parties to the 
    service agreement.
        Comment date: September 27, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    25. Southern Indiana Gas and Electric Company
    
    [Docket No. ER99-4388-000]
    
        Take notice that on September 7, 1999, Southern Indiana Gas and 
    Electric Company (SIGECO) tendered for filing the following agreements 
    concerning the provision of electric service to Cargill-Alliant LLC, 
    Duquesne Light Company, OGE Energy Resources, Inc., and Transalta 
    Energy Marketing (U.S.) Inc., as umbrella service agreements under its 
    market-based Wholesale Power Sales Tariff:
        1. Wholesale Energy Service agreement, dated July 29, 1999, by and 
    between Southern Indiana Gas and Electric Company and Cargill-Alliant 
    LLC.
        2. Wholesale Energy Service Agreement dated July 28, 1999, by and 
    between Southern Indiana Gas and Electric Company and Duquesne Light 
    Company.
        3. Wholesale Energy Service Agreement, dated July 27, 1999, by and 
    between Southern Indiana Gas and Electric Company and OGE Energy 
    Resources, Inc.
        4. Wholesale Energy Service Agreement, dated July 29, 1999, by and
    
    [[Page 51304]]
    
    between Southern Indiana Gas and Electric Company and Transalta Energy 
    Marketing (U.S.) Inc.
        Comment date: September 27, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    26. Georgia Power Company
    
    [Docket No. ER99-4389-000]
    
        Take notice that on September 7, 1999, Georgia Power Company 
    tendered for filing a Memorandum of Understanding Regarding Application 
    of the New Southern Companies Open Access Transmission Tariff Rates to 
    the Revised and Restated Coordination Services Agreement by and among 
    itself and Oglethorpe Power Corporation and Georgia System Operations 
    Corporation.
        Comment date: September 27, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    27. Yadkin, Inc.
    
    [Docket No. ER99-4391-000]
    
        Take notice that on September 8, 1999, Yadkin, Inc. (Yadkin) 
    tendered for filing an umbrella service agreement for Firm Point-to-
    Point Transmission Service between Yadkin and itself under Yadkin's 
    FERC Electric Tariff Original Volume No. 1--Open Access Transmission 
    Tariff (OATT).
        The service agreement provides for transmission service under 
    Yadkin's OATT and is proposed to be effective June 27, 1999.
        Comment date: September 28, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    28. Southwest Power Pool, Inc.
    
    [Docket No. ER99-4392-000]
    
        Take notice that on September 7, 1999, Southwest Power Pool, Inc. 
    (SPP) tendered for filing changes to its open access transmission 
    tariff (Tariff) intended to add network services, change the method for 
    calculating the SPP's administrative charge, and make other changes to 
    the Tariff. SPP also submitted a Membership Agreement intended to 
    better define the rights and responsibilities of SPP and its members, 
    and establish a disinterested Board of Directors for the SPP.
        SPP requests an effective date of February 1, 2000 for these 
    changes and January 1, 2000 for the Membership Agreement changes.
        Copies of this filing were served upon members and customers of 
    SPP, and on all affected state commissions.
        Comment date: September 27, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    29. Pacific Gas and Electric Company
    
    [Docket No. ER99-4393-000]
    
        Take notice that on September 8, 1999, Pacific Gas and Electric 
    Company (PG&E) tendered for filing proposed changes in rates for 
    Sacramento Municipal Utility District (SMUD), to be effective July 1, 
    1999, developed using a rate adjustment mechanism previously agreed by 
    PG&E and SMUD for PG&E Rate Schedule FERC Nos. 88, 91, 136 and 138.
        Copies of this filing have been served upon SMUD and the California 
    Public Utilities Commission.
        Comment date: September 28, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    30. Niagara Mohawk Power Corporation
    
    [Docket No. ER99-4395-000]
    
        Take notice that on September 8, 1999, Niagara Mohawk Power 
    Corporation (Niagara Mohawk) tendered for filing with the Federal 
    Energy Regulatory Commission an executed Transmission Service Agreement 
    between Niagara Mohawk and PP & L Energy Plus Co. This Transmission 
    Service Agreement specifies that PP & L Energy Plus Co. has signed on 
    to and has agreed to the terms and conditions of Niagara Mohawk's Open 
    Access Transmission Tariff as filed in Docket No. OA96-194-000. This 
    Tariff, filed with FERC on July 9, 1996, will allow Niagara Mohawk and 
    PP & L Energy Plus Co. to enter into separately scheduled transactions 
    under which Niagara Mohawk will provide non-firm transmission service 
    for PP & L Energy Plus Co. as the parties may mutually agree.
        Niagara Mohawk requests an effective date of August 19, 1999. 
    Niagara Mohawk has requested waiver of the notice requirements for good 
    cause shown.
        Niagara Mohawk has served copies of the filing upon the New York 
    State Public Service Commission and PP & L Energy Plus Co..
        Comment date: September 28, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    31. Niagara Mohawk Power Corporation
    
    [Docket No. ER99-4396-000]
    
        Take notice that on September 8, 1999, Niagara Mohawk (Niagara 
    Mohawk) tendered for filing with the Federal Energy Regulatory 
    Commission an executed Transmission Service Agreement between Niagara 
    Mohawk and PP & L Energy Plus Co. This Transmission Service Agreement 
    specifies that PP & L Energy Plus Co. has signed on to and has agreed 
    to the terms and conditions of Niagara Mohawk's Open Access 
    Transmission Tariff as filed in Docket No. OA96-194-000. This Tariff, 
    filed with FERC on July 9, 1996, will allow Niagara Mohawk and PP & L 
    Energy Plus Co. to enter into separately scheduled transactions under 
    which Niagara Mohawk will provide firm transmission service for PP & L 
    Energy Plus Co. as the parties may mutually agree.
        Niagara Mohawk requests an effective date of August 19, 1999. 
    Niagara Mohawk has requested waiver of the notice requirements for good 
    cause shown.
        Niagara Mohawk has served copies of the filing upon the New York 
    State Public Service Commission and PP & L Energy Plus Co..
        Comment date: September 28, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    32. Illinois Power Company
    
    [Docket No. ER99-4397-000]
    
        Take notice that on September 8, 1999, Illinois Power Company 
    (Illinois Power), 500 South 27th Street, Decatur, Illinois 62526, 
    tendered for filing firm and non-firm transmission agreements under 
    which Tractebel Energy Marketing, Inc. will take transmission service 
    pursuant to its open access transmission tariff. The agreements are 
    based on the Form of Service Agreement in Illinois Power's tariff.
        Illinois Power has requested an effective date of September 1, 
    1999.
        Comment date: September 28, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    33. Reliant Energy Etiwanda, LLC
    
    [Docket No. ER99-4398-000]
    
        Take notice that on September 8, 1999, Reliant Energy Etiwanda, LLC 
    (Reliant Etiwanda) tendered for filing an ``Addendum to Must-Run 
    Service Agreement'' between Reliant Etiwanda and the California 
    Independent System Operator Corporation (ISO), made as of June 1, 1999.
        This addendum supplements Reliant Etiwanda's Must-Run Agreement, 
    dated June 1, 1999, which was submitted for filing on April 13, 1999 in 
    connection with the Offer of Settlement filed in Docket Nos. ER98-441-
    000, et al., on April 2, 1999.
        Reliant Etiwanda has requested a waiver of the prior notice 
    requirement, to permit the addendum to become effective as of June 1, 
    1999.
        Comment date: September 28, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    [[Page 51305]]
    
    34. Tampa Electric Company
    
    [Docket No. ER99-4399-000]
    
        Take notice that on September 8, 1999, Tampa Electric Company 
    (Tampa Electric) tendered for filing a service agreement with Florida 
    Power & Light Company (FPL) under Tampa Electric's market-based sales 
    tariff.
        Tampa Electric proposes that the service agreement be made 
    effective on August 10, 1999.
        Copies of the filing have been served on FPL and the Florida Public 
    Service Commission.
        Comment date: September 28, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    35. Southern Company Services, Inc.
    
    [Docket No. ER99-4400-000]
    
        Take notice that on September 8, 1999, Southern Company Services, 
    Inc. (SCS), acting on behalf of Alabama Power Company, Georgia Power 
    Company, Gulf Power Company, Mississippi Power Company, and Savannah 
    Electric and Power Company (collectively referred to as Southern 
    Company), filed three unexecuted service agreements for long-term firm 
    point-to-point transmission service between SCS, as agent for Southern 
    Company, and Carolina Power & Light Company under the Open Access 
    Transmission Tariff of Southern Company (FERC Electric Tariff, Original 
    Volume No. 5). One such agreement provides for service from June 1, 
    1999 through May 31, 2000, and the other two agreements provide for 
    service from June 1, 2000 through May 31, 2001.
        Comment date: September 28, 1999, in accordance with Standard 
    Paragraph E at the end of this notice.
    
    Standard Paragraphs
    
        E. Any person desiring to be heard or to protest such filing should 
    file a motion to intervene or protest with the Federal Energy 
    Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426, 
    in accordance with Rules 211 and 214 of the Commission's Rules of 
    Practice and Procedure (18 CFR 385.211 and 385.214). All such motions 
    or protests should be filed on or before the comment date. Protests 
    will be considered by the Commission in determining the appropriate 
    action to be taken, but will not serve to make protestants parties to 
    the proceeding. Any person wishing to become a party must file a motion 
    to intervene. Copies of these filings are on file with the Commission 
    and are available for public inspection. This filing may also be viewed 
    on the Internet at http://www.ferc.fed.us/online/rims.htm (call 202-
    208-2222 for assistance).
    David P. Boergers,
    Secretary.
    [FR Doc. 99-24618 Filed 9-21-99; 8:45 am]
    BILLING CODE 6717-01-P
    
    
    

Document Information

Published:
09/22/1999
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
99-24618
Dates:
October 4, 1999, in accordance with Standard Paragraph E at the end of this notice. The Commission will limit its consideration of comments to those that concern the adequacy or accuracy.
Pages:
51301-51305 (5 pages)
Docket Numbers:
Docket No. EG99-200-000, et al.
PDF File:
99-24618.pdf