    [Docket No. CP99-618-000]
    
    
    ANR Pipeline Company; Notice of Request Under Blanket 
    Authorization
    
    September 15, 1999.
        Take notice that on September 10, 1999, ANR Pipeline Company (ANR), 
    500 Renaissance Center, Detroit, Michigan 48243, filed in Docket No. 
    CP99-618-000 a request pursuant to Sections 157.205 and 157.208 of the 
    Commission's Regulations under the Natural Gas Act (18 CFR 157.205 and 
    157.208) for authorization to construct and operate facilities in the 
    Federal Waters, Offshore Louisiana to permit ANR to receive and 
    transport gas from the system of Garden Banks Gas Pipeline, LLC (Garden 
    Banks), under the blanket certificate issued in Docket No. CP82-553-
    000, pursuant to Section 7(c) of the Natural Gas Act, all as more fully 
    set forth in the request which is on file with the Commission and open 
    to public inspection. This filing may be viewed on the web at http://
    www.ferc.fed.us/onLine/htm (call 202-208-2222 for assistance).
        ANR proposes to construct and operate approximately 8.2 miles of 
    16-inch pipeline extending from the terminus of Garden Banks' system in 
    South Marsh Island (SMI) Block 76, to ANR's 20 lateral at SMI Block 61, 
    along with a subsea tie-in at SMI Block 61 and two 10-inch orifice 
    meters on the platform at SMI 76. ANR indicates that the facilities 
    will accommodate up to 225,000 Mcf per day and will cost approximately 
    $10,000,000.
        Any person or the Commission's staff may, within 45 days after 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
    intervene or notice of intervention and pursuant to Section
    
    [[Page 51298]]
    
    157.205 of the Regulations under the Natural Gas Act (18 CFR 157.205) a 
    protest to the request. If no protest is filed within the time allowed 
    therefor, the proposed activity shall be deemed to be authorized 
    effective the day after the time allowed for filing a protest. If a 
    protest is filed and not withdrawn within 30 days after the time 
    allowed for filing a protest, the instant request shall be treated as 
    an application for authorization pursuant to Section 7 of the Natural 
    Gas Act.
    Linwood A. Watson, Jr.,
    Acting Secretary.
    [FR Doc. 99-24626 Filed 9-21-99; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
09/22/1999
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
99-24626
Pages:
51297-51298 (2 pages)
Docket Numbers:
Docket No. CP99-618-000