2020-20858. Exelon Generation Company, LLC; Three Mile Island Nuclear Station, Units 1 and 2  

  • Start Preamble

    AGENCY:

    Nuclear Regulatory Commission.

    ACTION:

    Environmental assessment and finding of no significant impact; issuance.

    SUMMARY:

    The U.S. Nuclear Regulatory Commission (NRC) is considering issuance of exemptions that would permit the licensee to reduce its emergency planning (EP) activities at Three Mile Island Nuclear Station, Unit 1 (TMI-1) and Unit 2 (TMI-2). Specifically, the licensee is seeking exemptions that would eliminate the requirements for the licensee to maintain offsite radiological emergency plans and reduce some of the onsite EP activities based on the reduced risks at TMI-1, which is permanently shut down and defueled, and at TMl-2, which has a possession-only license. However, requirements for certain onsite capabilities to communicate and coordinate with offsite response authorities would be retained. In addition, offsite EP provisions would still exist through State and local government use of a comprehensive emergency management plan process, in accordance with the Federal Emergency Management Agency's (FEMA's) Comprehensive Preparedness Guide (CPG) 101, “Developing and Maintaining Emergency Operations Plans.” The NRC staff is issuing a final Environmental Assessment (EA) and final Finding of No Significant Impact (FONSI) associated with the proposed exemptions.

    DATES:

    The EA and FONSI referenced in this document are available on September 22, 2020.

    ADDRESSES:

    Please refer to Docket ID NRC-2020-0211 when contacting the NRC about the availability of information regarding this document. You may obtain publicly-available information related to this document using any of the following methods:

    • Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2020-0211. Address questions about Docket IDs in Regulations.gov to Jennifer Borges; telephone: 301-287-9127; email: Jennifer.Borges@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document.
    • NRC's Agencywide Documents Access and Management System (ADAMS): You may obtain publicly-available documents online in the ADAMS Public Documents collection at https://www.nrc.gov/​reading-rm/​adams.html. To begin the search, select “Begin Web-based ADAMS Search.” For problems with ADAMS, please contact the NRC's Public Document Room reference staff at 1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. For the convenience of the reader, instructions about obtaining materials referenced in this document are provided in the AVAILABILITY OF DOCUMENTS section of this document.
    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Theodore Smith, Office of Nuclear Material Safety and Safeguards, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-6721; email: Theodore.Smith@nrc.gov.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    I. Introduction

    By letter dated June 20, 2017 (ADAMS Accession No. ML17171A151), pursuant to paragraph 50.82(a)(1)(i) of title 10 of the Code of Federal Regulations (10 CFR), Exelon Generation Company, LLC (Exelon) certified to the NRC that it planned to permanently cease power operations at TMI-1 on or about September 30, 2019. TMI-1 subsequently permanently ceased power operations on September 20, 2019. By letter dated September 26, 2019 (ADAMS Accession No. ML19269E480), pursuant to 10 CFR 50.82(a)(1)(ii), Exelon certified to the NRC that all fuel had been permanently removed from the TMI-1 reactor vessel and placed in the spent fuel pool (SFP) as of September 26, 2019. Accordingly, pursuant to 10 CFR 50.82(a)(2), the TMI-1 renewed facility operating license no longer authorizes operation of the reactor or emplacement or retention of fuel in the reactor vessel. The facility is still authorized to possess and store irradiated (i.e., spent) nuclear fuel. Spent fuel is currently stored onsite at the TMI-1 facility in the SFP. A dry cask independent spent fuel storage installation (ISFSI) is under construction onsite to store the TMI-1 spent fuel.

    TMI-2 has a possession-only license and is currently maintained in accordance with the NRC-approved SAFSTOR condition (method in which a nuclear facility is placed and maintained in a condition that allows it to be safely stored and subsequently decontaminated) known as post-defueling monitored storage. Spent fuel for TMI-2 has already been removed from the site, though residual contamination and radiological materials exist. Therefore, TMI-2 is also permanently shut down and defueled. Exelon maintains the EP responsibilities for TMI-2, which is owned by First Energy Corporation, through a service agreement.

    By letter dated July 1, 2019 (ADAMS Accession No. ML19182A104), as supplemented by letters dated October 9, 2019, and December 10, 2019 (ADAMS Accession Nos. ML19282C285 and ML19344C115, respectively), Exelon requested exemptions from certain EP requirements in 10 CFR part 50 for TMI-1 and TMI-2.

    The NRC regulations concerning EP do not recognize the reduced risks after a reactor is permanently shut down and defueled. As such, a permanently shut down and defueled reactor must continue to maintain the same EP requirements as an operating power reactor under the existing regulatory requirements. To establish a level of EP commensurate with the reduced risks of a permanently shut down and defueled reactor, the licensee requires exemptions from certain EP regulatory requirements before it can change its emergency plans.

    The NRC is considering issuing to the licensee exemptions from portions of 10 CFR 50.47, “Emergency plans,” and appendix E to 10 CFR part 50, “Emergency Planning and Preparedness for Production and Utilization Facilities,” which would eliminate the requirements for the licensee to maintain offsite radiological emergency plans in accordance with 44 CFR, “Emergency Management and Assistance,” part 350, “Review and Approval of State and Local Radiological Emergency Plans and Preparedness,” and reduce some of the onsite EP activities based on the reduced risks 488 days (approximately 16 months) after TMI-1 has permanently ceased power operations.

    Consistent with 10 CFR 51.21, the NRC has determined that an EA is the appropriate form of environmental review for the requested action. Based on the results of the EA, which is Start Printed Page 59566provided in Section II of this document, the NRC has determined not to prepare an environmental impact statement for the proposed action, and is issuing a FONSI.

    II. Environmental Assessment

    Description of the Proposed Action

    The proposed action would exempt the licensee from (1) certain standards as set forth in 10 CFR 50.47(b) regarding onsite and offsite emergency response plans for nuclear power reactors; (2) requirements in 10 CFR 50.47(c)(2) to establish plume exposure and ingestion pathway emergency planning zones (EPZs) for nuclear power reactors; and (3) certain requirements in 10 CFR part 50, appendix E, section IV, which establishes the elements that make up the content of emergency plans. The proposed action of granting these exemptions would eliminate the requirements for the licensee to maintain offsite radiological emergency plans in accordance with 44 CFR part 350 and reduce some of the onsite EP activities at TMI-1 and TMI-2, based on the reduced risks once the TMI-1 reactor has been permanently shut down for a period of 488 days. However, requirements for certain onsite capabilities to communicate and coordinate with offsite response authorities would be retained to an extent consistent with the approved exemptions. Additionally, if necessary, offsite protective actions could still be implemented using a comprehensive emergency management plan (CEMP) process. A CEMP in this context, also referred to as an emergency operations plan (EOP), is addressed in FEMA's CPG 101, “Developing and Maintaining Emergency Operations Plans.” The CPG 101 is the foundation for State, territorial, tribal, and local EP in the United States under the National Preparedness System. It promotes a common understanding of the fundamentals of risk-informed planning and decision making, and assists planners at all levels of government in their efforts to develop and maintain viable, all-hazards, all-threats emergency plans. An EOP is flexible enough for use in all emergencies. It describes how people and property will be protected; details who is responsible for carrying out specific actions; identifies the personnel, equipment, facilities, supplies, and other resources available; and outlines how all actions will be coordinated. A CEMP is often referred to as a synonym for “all-hazards” planning. The proposed action is in accordance with the licensee's application dated July 1, 2019, as supplemented by letters dated October 9, 2019, and December 10, 2019.

    Need for the Proposed Action

    The proposed action is needed for the licensee to revise the TMI-1 and TMI-2 Emergency Plan once the TMI-1 reactor has been permanently shutdown for a period of 488 days. The EP requirements currently applicable to TMI-1 and TMI-2 are for an operating power reactor. Since the certifications for permanent cessation of operations and permanent removal of fuel from the reactor vessel have been docketed for TMI-1, pursuant to 10 CFR 50.82(a)(2), the TMI-1 license no longer authorizes use of the facility for power operation or emplacement or retention of fuel into the reactor vessel and, therefore, the occurrence of postulated accidents associated with TMI-1 reactor operation is no longer credible. Since the TMI-2 license had already been modified to allow possession but not operation before the effective date of the rule requiring these certifications, pursuant to 10 CFR 50.82(a)(2), the certifications have been deemed submitted for TMI-2 as well and, therefore, the occurrence of postulated accidents associated with TMI-2 reactor operation is no longer credible. However, there are no explicit regulatory provisions distinguishing EP requirements for a power reactor that has been permanently shut down and defueled from those for an operating power reactor.

    In its exemption request, the licensee identified four possible radiological accidents at TMI-1 and TMI-2 in their permanently shutdown and defueled condition. These are: (1) A fuel-handling accident; (2) fire in the TMI-2 reactor building with the reactor building purge system in operation; (3) a loss of SFP normal cooling (i.e., boil off); and (4) an adiabatic heat up of the hottest fuel assembly. The NRC staff evaluated these possible radiological accidents in the Commission Paper (SECY) 20-0041, “Request by Exelon Generation Company, LLC for Exemptions from Certain Emergency Planning Requirements for the Three Mile Island Nuclear Station,” dated May 5, 2020 (ADAMS Package Accession No. ML19311C762). In SECY-20-0041, the NRC staff verified that the licensee's analyses and calculations provided reasonable assurance that if the requested exemptions were granted, then: (1) For a design-basis accident (DBA), an offsite radiological release will not exceed the early phase protective action guides (PAGs) at the site boundary, as detailed in Table 1-1 to the U.S. Environmental Protection Agency's (EPA's), “PAG Manual: Protective Action Guides and Planning Guidance for Radiological Incidents,” EPA-400/R-17/001, dated January 2017, and (2) in the highly unlikely event of a beyond DBA resulting in a loss of all SFP cooling, there is sufficient time to initiate appropriate mitigating actions, and in the event a radiological release has or is projected to occur, there would be sufficient time for offsite agencies to take protective actions using a CEMP to protect the health and safety of the public if offsite governmental officials determine that such action is warranted. The Commission approved the NRC staff's recommendation to grant the exemptions based on this evaluation in its Staff Requirements Memorandum (SRM) to SECY-20-0041, dated July 27, 2020 (ADAMS Accession No. ML20209A439).

    Based on these analyses, the licensee states that complete application of the EP rule to TMI-1 and TMI-2 488 days after TMI-1's permanent cessation of power operations would not serve the underlying purpose of the rule or is not necessary to achieve the underlying purpose of the rule. The licensee also states that it would incur undue costs in the application of operating plant EP requirements for the maintenance of an emergency response organization in excess of that actually needed to respond to the diminished scope of credible accidents for TMI-1 and TMI-2 488 days after TMI-1's permanent cessation of power operations.

    Environmental Impacts of the Proposed Action

    The NRC staff has completed its evaluation of the environmental impacts of the proposed action.

    The proposed action consists mainly of changes related to the elimination of requirements for the licensee to maintain offsite radiological emergency plans in accordance with 44 CFR part 350 and reduce some of the onsite EP activities at TMI-1 and TMI-2, based on the reduced risks once the TMI-1 reactor has been permanently shutdown for a period of 488 days. However, requirements for certain onsite capabilities to communicate and coordinate with offsite response authorities will be retained and offsite EP provisions to protect public health and safety will still exist through State and local government use of a CEMP.

    With regard to potential nonradiological environmental impacts, the proposed action would have no direct impacts on land use or water resources, including terrestrial and aquatic biota, as it involves no new construction or modification of plant operational systems. There would be no Start Printed Page 59567changes to the quality or quantity of nonradiological effluents and no changes to the plants' National Pollutant Discharge Elimination System permits would be needed. In addition, there would be no noticeable effect on socioeconomic conditions in the region, no environment justice impacts, no air quality impacts, and no impacts to historic and cultural resources from the proposed action. Therefore, there are no significant nonradiological environmental impacts associated with the proposed action.

    With regard to potential radiological environmental impacts, as stated above, the proposed action would not increase the probability or consequences of radiological accidents. Additionally, the NRC staff has concluded that the proposed action would have no direct radiological environmental impacts. There would be no change to the types or amounts of radioactive effluents that may be released and, therefore, no change in occupational or public radiation exposure from the proposed action. Moreover, no changes would be made to plant buildings or the site property from the proposed action. Therefore, there are no significant radiological environmental impacts associated with the proposed action.

    Environmental Impacts of the Alternatives to the Proposed Action

    As an alternative to the proposed action, the NRC staff considered the denial of the proposed action (i.e., the “no-action” alternative). The denial of the application would result in no change in current environmental impacts. Therefore, the environmental impacts of the proposed action and the alternative action are similar.

    Alternative Use of Resources

    There are no unresolved conflicts concerning alternative uses of available resources under the proposed action.

    Agencies or Persons Consulted

    No additional agencies or persons were consulted regarding the environmental impact of the proposed action. On August 24, 2020, the Commonwealth of Pennsylvania representative was notified of this EA and FONSI.

    III. Finding of No Significant Impact

    The licensee has proposed exemptions from: (1) Certain standards in 10 CFR 50.47(b) regarding onsite and offsite emergency response plans for nuclear power reactors; (2) the requirement in 10 CFR 50.47(c)(2) to establish plume exposure and ingestion pathway EPZs for nuclear power reactors; and (3) certain requirements in 10 CFR part 50, appendix E, section IV, which establishes the elements that make up the content of emergency plans. The proposed action of granting these exemptions would eliminate the requirements for the licensee to maintain offsite radiological emergency plans in accordance with 44 CFR part 350 and reduce some of the onsite EP activities at TMI-1 and TMI-2, based on the reduced risks once the TMI-1 reactor has been permanently shutdown for a period of 488 days. However, requirements for certain onsite capabilities to communicate and coordinate with offsite response authorities will be retained and offsite EP provisions to protect public health and safety will still exist through State and local government use of a CEMP.

    The NRC is considering issuing the exemptions. The proposed action would not significantly affect plant safety, would not have a significant adverse effect on the probability of an accident occurring, and would not have any significant radiological or nonradiological impacts. This FONSI incorporates by reference the EA in Section II of this document. Therefore, the NRC concludes that the proposed action will not have a significant effect on the quality of the human environment. Accordingly, the NRC has determined not to prepare an environmental impact statement for the proposed action.

    The related environmental document is the “Generic Environmental Impact Statement for License Renewal of Nuclear Plants: Regarding Three Mile Island Nuclear Station, Unit 1,” NUREG-1437, Supplement 37, and “Environmental Impact Statement Related to Decontamination and Disposal of Radioactive Wastes Resulting from March 28, 1979 Accident Three Mile Island Nuclear Station, Unit 2,” NUREG-0683 (Vol. I, and Vol. II), which provide the latest environmental review of current operations and description of environmental conditions at TMI-1 and TMI-2.

    IV. Availability of Documents

    The documents identified in the following table are available to interested persons through one or more of the following methods, as indicated.

    DocumentADAMS Accession No./Web link
    Federal Emergency Management Agency, Developing and Maintaining Emergency Operations Plans, Comprehensive Preparedness Guide (CPG) 101, Version 2.0, November 2010https://www.fema.gov/​sites/​default/​files/​2020-05/​CPG_​101_​V2_​30NOV2010_​FINAL_​508.pdf.
    Gallagher, Michael P., Exelon Generation Company, LLC, “Request for Exemptions from Portions of 10 CFR 50.47 and 10 CFR part 50, appendix E,” July 1, 2019ML19182A104.
    Gallagher, Michael P., Exelon Generation Company, LLC, “Supplement to Request for Exemptions from Portions of 10 CFR 50.47 and 10 CFR part 50, appendix E and License Amendment Request for Proposed Changes to the Three Mile Island Emergency Plan for Permanently Defueled Emergency Plan and Emergency Action Level Scheme,” October 9, 2019ML19282C285.
    Gallagher, Michael P., Exelon Generation Company, LLC, “Response to Request for Additional Information (RAI) Regarding Request for Exemptions from Portions of 10 CFR 50.47 and 10 CFR part 50, appendix E,” December 10, 2019ML19344C115.
    Fewell, J. Bradley, Exelon Generation Company, LLC, “Certification of Permanent Cessation of Power Operations for Three Mile Island Nuclear Station, Unit 1,” June 20, 2017ML17171A151.
    Gallagher, Michael P., Exelon Generation Company, LLC, “Certification of Permanent Removal of Fuel from the Reactor Vessel for Three Mile Island Nuclear Station, Unit 1,” September 26, 2019ML19269E480.
    U.S. Environmental Protection Agency, PAG Manual: Protective Action Guides and Planning Guidance for Radiological Incidents, January 2017https://www.epa.gov/​sites/​production/​files/​2017-01/​documents/​epa_​pag_​manual_​final_​revisions_​01-11-2017_​cover_​disclaimer_​8.pdf.
    Start Printed Page 59568
    SECY-20-0041, “Request by Exelon Generation Company, LLC for Exemptions from Certain Emergency Planning Requirements for the Three Mile Island Nuclear Station,” May 5, 2020ML19311C762 (Package).
    Staff Requirements Memorandum to SECY-20-0041, “Request by Exelon Generation Company, LLC for Exemptions from Certain Emergency Planning Requirements for the Three Mile Island Nuclear Station,” July 27, 2020ML20209A439.
    NUREG-1437, Supplement 37, “Generic Environmental Impact Statement for License Renewal of Nuclear Plants: Regarding Three Mile Island Nuclear Station, Unit 1,” June 2009ML091751063.
    Start Signature

    Dated: September 17, 2020.

    For the Nuclear Regulatory Commission.

    Bruce Watson,

    Chief, Reactor Decommissioning Branch, Division of Decommissioning, Uranium Recovery, and Waste Programs, Office of Nuclear Material Safety and Safeguards.

    End Signature End Supplemental Information

    [FR Doc. 2020-20858 Filed 9-21-20; 8:45 am]

    BILLING CODE 7590-01-P

Document Information

Published:
09/22/2020
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Action:
Environmental assessment and finding of no significant impact; issuance.
Document Number:
2020-20858
Dates:
The EA and FONSI referenced in this document are available on September 22, 2020.
Pages:
59565-59568 (4 pages)
Docket Numbers:
Docket Nos. 50-289 and 50-320, NRC-2020-0211
PDF File:
2020-20858.Pdf