96-24496. Northwest Pipeline Corporation; Notice of Petition To Amend  

  • [Federal Register Volume 61, Number 187 (Wednesday, September 25, 1996)]
    [Notices]
    [Pages 50288-50289]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-24496]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Docket No. CP96-576-001]
    
    
    Northwest Pipeline Corporation; Notice of Petition To Amend
    
    September 19, 1996.
        Take notice that on September 16, 1996, Northwest Pipeline 
    Corporation (Northwest), P.O. Box 58900, Salt Lake City, Utah 84108-
    0900, filed in Docket No. CP96-576-001 a petition to amend its 
    application filed in Docket No. CP96-576-000 to delete that portion of 
    the application proposing to construct approximately 2.775 miles of 10-
    inch pipeline and metering facilities in Clark County, Washington, all 
    as more fully set forth in the petition which is on file with the 
    Commission and open to public inspection.
        Northwest indicates that, in the original filing submitted under 
    the prior notice procedure in Docket No. CP96-576-000, it proposed to 
    construct and operate approximately 2.775 miles of 10-inch pipeline and 
    a new metering station in Clark County, Washington to implement a firm 
    transportation service
    
    [[Page 50289]]
    
    for Washington Water Power Company (Water Power) for redelivery to a 
    new electrical plant built by the Public Utility District No. 1 of 
    Clark County. It is also stated that Northwest Natural Gas Company 
    protested the filing citing Northwest's failure to address impacts on 
    firm service reliability and an interruption of the facilities 
    reimbursement provision of Northwest's tariff. Northwest states that 
    the protest was not withdrawn during the 30-day reconciliation period 
    provided under 157.205(g) of the Commission's Regulations. It is 
    indicated that, because of adverse cost impacts to be caused by a 
    construction delay, Northwest, at the request of Water Power and Inland 
    Pacific Energy Services, elected to construct the facilities under the 
    auspices of Section 311 of the Natural Gas Policy Act of 1978.
        Northwest has amended its application to delete its request to 
    construct the above-mentioned facilities. No other changes are proposed 
    in Northwest's original application.
        Any person desiring to be heard or to make any protest with 
    reference to said petition to amend should on or before October 10, 
    1996, file with the Federal Energy Regulatory Commission, Washington, 
    D.C. 20426, a motion to intervene or a protest in accordance with the 
    requirements of the Commission's Rules of Practice and Procedure (18 
    CFR 385.214 or 385.211) and the Regulations under the Natural Gas Act 
    (18 CFR 157.10). All protests filed with the Commission will be 
    considered by it in determining the appropriate action to be taken but 
    will not serve to make the protestants parties to the proceeding. Any 
    person wishing to become a party to a proceeding or to participate as a 
    party in any hearing therein must file a motion to intervene in 
    accordance with the Commission's Rules.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 96-24496 Filed 9-24-96; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
09/25/1996
Department:
Energy Department
Entry Type:
Notice
Document Number:
96-24496
Pages:
50288-50289 (2 pages)
Docket Numbers:
Docket No. CP96-576-001
PDF File: