01-24067. Approval and Promulgation of Air Quality Implementation Plans; Maryland; Rate of Progress Plans and Contingency Measures for the Baltimore Ozone Nonattainment Area  

  • Start Preamble

    AGENCY:

    Environmental Protection Agency (EPA).

    ACTION:

    Final rule.

    SUMMARY:

    EPA is approving State Implementation Plan (SIP) revisions submitted by the State of Maryland. These revisions establish the three percent per year emission reduction rate-of-progress (ROP) requirement for the period from 1996 through 2005 for the Baltimore severe ozone nonattainment area. EPA is also approving contingency measures for failure to meet ROP for the Baltimore nonattainment area. EPA is approving these revisions in accordance with the requirements of the Clean Air Act.

    EFFECTIVE DATE:

    This final rule is effective on October 26, 2001.

    ADDRESSES:

    Copies of the documents relevant to this action are available for public inspection during normal business hours at the Air Protection Division, U.S. Environmental Protection Agency, Region III, 1650 Arch Street, Philadelphia, Pennsylvania 19103; and Maryland Department of the Environment, 2500 Broening Highway, Baltimore, Maryland, 21224.

    Start Further Info Start Printed Page 49109

    FOR FURTHER INFORMATION CONTACT:

    Kristeen Gaffney, (215) 814-2092. Or by e-mail at gaffney.kristeen@epa.gov.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    I. Background

    On August 6, 2001 (66 FR 40947), EPA published a notice of proposed rulemaking (NPR) for the State of Maryland. The NPR proposed approval of the post 1996 ROP plans for milestone years 1999, 2002 and 2005 for the Baltimore ozone nonattainment area submitted by the State of Maryland on December 24, 1997, as revised on April 24 and August 18, 1998, December 21, 1999 and December 28, 2000. The NPR also proposed approval of the contingency plan for failure to meet ROP for the Baltimore nonattainment area. Other specific requirements of Maryland's SIP revisions for the ROP plans and contingency plans for Baltimore and the rationale for EPA's proposed action are explained in the NPR and will not be restated here. No public comments were received on the NPR.

    II. Final Actions

    Final Action: EPA is approving the post 1996 ROP plans for milestone years 1999, 2002 and 2005 for the Baltimore ozone nonattainment area submitted on December 24, 1997, as revised on April 24 and August 18, 1998, December 21, 1999 and December 28, 2000.

    Final Action: EPA is approving the contingency plans for failure to meet ROP for the Baltimore ozone nonattainment area submitted on December 24, 1997, as revised on April 24 and August 18, 1998, December 21, 1999 and December 28, 2000.

    III. Administrative Requirements

    A. General Requirements

    Under Executive Order 12866 (58 FR 51735, October 4, 1993), this action is not a “significant regulatory action” and therefore is not subject to review by the Office of Management and Budget. For this reason, this action is also not subject to Executive Order 13211, “Actions Concerning Regulations That Significantly Affect Energy Supply, Distribution, or Use” (66 FR 28355 (May 22, 2001)). This action merely approves state law as meeting Federal requirements and imposes no additional requirements beyond those imposed by state law. Accordingly, the Administrator certifies that this rule will not have a significant economic impact on a substantial number of small entities under the Regulatory Flexibility Act (5 U.S.C. 601 et seq.). Because this rule approves pre-existing requirements under state law and does not impose any additional enforceable duty beyond that required by state law, it does not contain any unfunded mandate or significantly or uniquely affect small governments, as described in the Unfunded Mandates Reform Act of 1995 (Public Law 104-4). This rule also does not have tribal implications because it will not have a substantial direct effect on one or more Indian tribes, on the relationship between the Federal Government and Indian tribes, or on the distribution of power and responsibilities between the Federal Government and Indian tribes, as specified by Executive Order 13175 (65 FR 67249, November 9, 2000). This action also does not have Federalism implications because it does not have substantial direct effects on the States, on the relationship between the national government and the States, or on the distribution of power and responsibilities among the various levels of government, as specified in Executive Order 13132 (64 FR 43255, August 10, 1999). This action merely approves a state rule implementing a Federal standard, and does not alter the relationship or the distribution of power and responsibilities established in the Clean Air Act. This rule also is not subject to Executive Order 13045 “Protection of Children from Environmental Health Risks and Safety Risks” (62 FR 19885, April 23, 1997), because it is not economically significant.

    In reviewing SIP submissions, EPA's role is to approve state choices, provided that they meet the criteria of the Clean Air Act. In this context, in the absence of a prior existing requirement for the State to use voluntary consensus standards (VCS), EPA has no authority to disapprove a SIP submission for failure to use VCS. It would thus be inconsistent with applicable law for EPA, when it reviews a SIP submission, to use VCS in place of a SIP submission that otherwise satisfies the provisions of the Clean Air Act. Thus, the requirements of section 12(d) of the National Technology Transfer and Advancement Act of 1995 (15 U.S.C. 272 note) do not apply. This rule does not impose an information collection burden under the provisions of the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.).

    B. Submission to Congress and the Comptroller General

    The Congressional Review Act, 5 U.S.C. 801 et seq., as added by the Small Business Regulatory Enforcement Fairness Act of 1996, generally provides that before a rule may take effect, the agency promulgating the rule must submit a rule report, which includes a copy of the rule, to each House of the Congress and to the Comptroller General of the United States. EPA will submit a report containing this rule and other required information to the U.S. Senate, the U.S. House of Representatives, and the Comptroller General of the United States prior to publication of the rule in the Federal Register. This rule is not a “major rule” as defined by 5 U.S.C. 804(2).

    C. Petitions for Judicial Review

    Under section 307(b)(1) of the Clean Air Act, petitions for judicial review of this action to approve the post 1996 ROP plans and contingency plans for the Baltimore ozone nonattainment area must be filed in the United States Court of Appeals for the appropriate circuit by November 26, 2001. Filing a petition for reconsideration by the Administrator of this final rule does not affect the finality of this rule for the purposes of judicial review nor does it extend the time within which a petition for judicial review may be filed, and shall not postpone the effectiveness of such rule or action. This action may not be challenged later in proceedings to enforce its requirements. (See section 307(b)(2).)

    Start List of Subjects

    List of Subjects in 40 CFR Part 52

    • Environmental protection
    • Air pollution control
    • Nitrogen dioxide
    • Ozone
    End List of Subjects Start Signature

    Dated: September 18, 2001.

    Donald S. Welsh,

    Regional Administrator, Region III.

    End Signature Start Amendment Part

    40 CFR part 52 is amended as follows:

    End Amendment Part Start Part

    PART 52—[AMENDED]

    End Part Start Amendment Part

    1. The authority citation for part 52 continues to read as follows:

    End Amendment Part Start Authority

    Authority: 42 U.S.C. 7401 et seq.

    End Authority

    Subpart V—Maryland

    Start Amendment Part

    2. Section 52.1076 is amended by adding and reserving paragraphs (h) and (i) and adding paragraph (j) to read as follows:

    End Amendment Part
    Control strategy and rate-of-progress plan: ozone.
    * * * * *

    (j)(1) EPA approves revisions to the Maryland State Implementation Plan for post 1996 rate of progress plans for milestone years 1999, 2002 and 2005 for the Baltimore severe ozone nonattainment area. These revisions were submitted by the Secretary of the Maryland Department of the Environment on December 24, 1997, as Start Printed Page 49110revised on April 24 and August 18, 1998, December 21, 1999 and December 28, 2000.

    (2) EPA approves the contingency plans for failure to meet rate of progress in the Baltimore severe ozone nonattainment area for milestone years 1999, 2002 and 2005. These plans were submitted by the Secretary of the Maryland Department of the Environment on December 24, 1997, as revised on April 24 and August 18, 1998, December 21, 1999 and December 28, 2000.

    End Supplemental Information

    [FR Doc. 01-24067 Filed 9-25-01; 8:45 am]

    BILLING CODE 6560-50-P

Document Information

Effective Date:
10/26/2001
Published:
09/26/2001
Department:
Environmental Protection Agency
Entry Type:
Rule
Action:
Final rule.
Document Number:
01-24067
Dates:
This final rule is effective on October 26, 2001.
Pages:
49108-49110 (3 pages)
Docket Numbers:
MD057/71/98/115-3082, FRL-7066-3
Topics:
Air pollution control, Environmental protection, Nitrogen dioxide, Ozone
PDF File:
01-24067.pdf
CFR: (1)
40 CFR 52.1076