96-24863. CNG Transmission Corporation; Grant of Waiver  

  • [Federal Register Volume 61, Number 189 (Friday, September 27, 1996)]
    [Notices]
    [Pages 50900-50902]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-24863]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF TRANSPORTATION
    Research and Special Programs Administration
    [Docket No. P-96-8W; Notice 2]
    
    
    CNG Transmission Corporation; Grant of Waiver
    
    ACTION: Notice of grant of waiver.
    
    -----------------------------------------------------------------------
    
    Summary
    
        The Research and Special Programs Administration (RSPA) waives 
    specified operations regulations to permit CNG Transmission Corporation 
    (CNGT) to requalify the maximum allowable operating pressure (MAOP) of 
    ten line segments by a combination of hydrostatic testing of certain 
    segments and internal inspection(s) of the 26-inch diameter gas 
    transmission line. The need for requalification of the MAOP results 
    from a recent increase in population density that has caused the hoop 
    stress corresponding to the established MAOP to be incommensurate with 
    the present class locations. The 26-inch diameter portion of 
    transmission line TL-400 is located in central Ohio and the affected 
    line segments (totaling 10.91 miles) are spread throughout the 163.19 
    mile length.
    
    Background
    
        By a letter dated April 23, 1996, and supplemented by 
    correspondence dated May 2 and May 14, 1996, (cumulatively referred to 
    as the ``petition''), CNGT petitioned RSPA for a waiver from compliance 
    with the requirements of 49 CFR 192.611(a) that require confirmation of 
    the MAOP of the affected segments by hydrostatic testing. Instead, CNGT 
    proposed an alternative approach involving: a close interval pipe-to-
    soil corrosion survey; certain hydrostatic testing; and the internal 
    inspection(s) of the entire 26-inch diameter transmission line with a 
    geometry pig followed by an
    
    [[Page 50901]]
    
    instrumented internal inspection device commonly known as a ``smart 
    pig''. Also, CNGT requested ( if needed) the extension of the 18-month 
    period for hydrostatic testing contained in Sec. 192.611(c), from 
    October 19, 1996, to June 30, 1997.
    
    Alternative Approach
    
        Rather than hydrostatically testing all ten affected segments, CNGT 
    requested a waiver permitting an alternative approach which they 
    believed would achieve both an equivalent level of safety in the 
    affected segments and internal inspection(s) that would evaluate the 
    163.19 mile transmission line. Because of its knowledge of the good 
    physical condition of this line as presented in Notice 1 (described 
    below), CNGT expected that its implementation of the provisions of 
    Alternative A would be less costly and would reduce the number of days 
    that the gas transmission line would be out of service. Nonetheless, 
    CNGT understood that if the physical condition of the line was found to 
    be less than anticipated, its implementation of the provisions of 
    Alternate B would be more costly than total compliance with the 
    hydrostatic testing requirements of 49 CFR 192.611(a). To provide 
    clarity and continuity, the provisions of Alternative A and Alternative 
    B are set out as they appeared in Notice 1:
        Alternative A consists of the following:
        (A) Conducting a close interval pipe-to-soil corrosion survey (CIS) 
    of the 163.19 mile line;
        (A2) Hydrostatic testing four segments (totaling 4.96 miles). If no 
    leak occurs, or only a specified minor leak \1\ occurs and is 
    remediated, the hydrostatic testing is completed;
    ---------------------------------------------------------------------------
    
        \1\ Specified minor leak--A leak from valve packings, gaskets, 
    threaded fittings, or hydrostatic test equipment; and from localized 
    corrosion pitting on the 26-in line pipe.
    ---------------------------------------------------------------------------
    
        (A3) Inspecting the 163.19 mile line with a geometry pig followed 
    by a high resolution ``smart pig.'' Any defects impacting the MAOP are 
    promptly remediated. All defects detected by the ``smart pig'' are 
    cross-referenced with the CIS to correct any deficiencies in the 
    cathodic protection system, all before October 19, 1996; and
        (A4) Inspecting the 163.19 mile line with a geometry pig followed 
    by a high resolution ``smart pig'' remediation of any defects impacting 
    the MAOP, all in the year 2001.
        Alternative B would be performed only if, during the implementation 
    of (A2), a leak other than a specified minor leak \2\ occurs. 
    Alternative B consists of the following:
    ---------------------------------------------------------------------------
    
        \2\ Other than a specified minor leak--A leak from a crack, 
    crack-like defects, general corrosion, or from any other source 
    (except localized corrosion pitting) on the 26-inch line pipe.
    ---------------------------------------------------------------------------
    
        (B1) If a leak, other than a specified minor leak occurs during 
    (A2) and is remediated, the hydrostatic testing of the four segments is 
    completed;
        (B2) Inspecting the 163.19 mile line with a geometry pig following 
    by a high resolution ``smart pig.'' Any defects impacting the MAOP are 
    promptly remediated. All before October 19, 1996; and
        (B3) The period to qualify the MAOP is extended until (B3) is 
    completed. All defects detected by the ``smart pig'' are cross-
    referenced with the CIS to correct any deficiencies in the cathodic 
    protection system. Hydrostatic testing and remediation of any leaks 
    occurring in the remaining six segments (totaling 5.95 miles), all 
    before June 30, 1997.
    
    Basis for the Alternative Approach
    
        CNGT's proposed alternative approach is based on their contention 
    that this transmission line is in good physical condition. In its 
    petition (and set out under this same heading in Notice 1), CNGT 
    supported that assertion by providing comprehensive information on the 
    transmission line's construction, operation, and maintenance history.
        Furthermore, CNGT expressed confidence in the good physical 
    condition of this 26-inch diameter line by agreeing to the potential 
    consequences (during the implementation of Alternative A) of any leak 
    other than a specified minor leak during the hydrostatic testing of 
    (A2); because, such a leak would trigger the need to implement the more 
    costly and time consuming Alternative B. In such a case, under the 
    provisions of (B1) and (B3), CNGT would hydrostatically test all ten 
    segments as required by Sec. 192.611(a). Moreover, under (B2), they 
    would inspect the 163.19 mile transmission line with a geometry pig and 
    with a high resolution ``smart pig.''
    
    RSPA Review
    
        Our review of the petition showed the following:
        (1) CNGT's contention that this 26-inch diameter transmission line 
    is in good physical condition was well supported with information on 
    the submerged-arc welded pipe, internal and external coatings, cathodic 
    protection, and (apart from one third party dig-in) the transmission 
    line's outstanding leak free record;
        (2) During the period 1990 through 1996, the MAOP of six such 
    segments in this line were requalified by hydrostatic testing without a 
    leak or failure;
        (3) The requirements of Sec. 192.611(a) for requalification would 
    be only partially waived during (A2), because four of the ten segments 
    (representing 4.96 miles or a 45.46% sampling of the total 10.91 miles) 
    would be hydrostatically tested;
        (4) If a leak, other than a specified minor leak occurs during the 
    hydrostatic testing of (A2), then under (B1) the leak is remediated and 
    under (B3) the remaining six segments would be hydrostatically tested 
    before June 30, 1997. This would (with the extension of the 18-month 
    period in Sec. 192.611(c)) result in total compliance with 
    Sec. 192.611(a). Additionally, during (B2) there would be an internal 
    inspection of the 163.19 mile transmission line during 1996;
        (5) If no leak occurred, or only a specified minor leak occurred, 
    under (A3) the complete transmission line would be internally inspected 
    during 1996 and under (A4) internally inspected again during the year 
    2001;
        (6) The implementation of either (A3) or (B2), the ``smart pig'' 
    inspection in 1996, would be the first time the 26-inch diameter line 
    has been inspected by a ``smart pig.'' A ``smart pig'' is capable of 
    detecting certain flaws in the pipe wall that (when interpreted) may 
    disclose defects that jeopardize the safe operation of the gas 
    transmission line . CNGT would run a ``smart pig'' of the high 
    resolution type, which is considered to be state-of-the-art technology 
    for the identification of pipe wall defects;
        (7) Defects detected by the ``smart pigs'' would be cross-
    referenced with the close interval pipe-to-soil corrosion survey to 
    correct any deficiencies in the cathodic protection system; and
        (8) The ``smart pig'' runs would be preceded by a geometry pig that 
    is capable of detecting dents in the pipe wall and girth welds.
    
    Notice 1
    
        In response to the CNGT's petition and the justification it 
    contained, RSPA issued a Notice of petition for waiver inviting persons 
    to submit written comments, (Notice 1) (61 FR 35860; July 8, 1996). In 
    that notice, RSPA explained why neither the implementation of Alternate 
    A nor its backup, Alternate B, would be inconsistent with pipeline 
    safety. In fact, we saw the implementation of either alternative as 
    contributing to the safety of the 163.19 mile transmission line.
    
    [[Page 50902]]
    
    Discussion of Comments
    
        RSPA received public comments on Notice 1 from six gas pipeline 
    operators and one pipeline related trade association. All seven 
    commenters endorsed the alternative approach proposed by the petitioner 
    and believed that the plan of action would ensure pipeline safety. Two 
    pipeline operators stated that ``CNGT's proposal appears to be an 
    excellent implementation of RSPA's proposed implementation of Risk 
    Based Pipeline Operations procedures.''
    
    Action on Petition
    
        In accordance with the foregoing and by this order, RSPA finds that 
    the requested waiver would not be inconsistent with pipeline safety. 
    However, if during the hydrostatic testing required under Alternative 
    A, a leak other than a specified minor leak occurs, CNGT is required to 
    implement Alternative B. Accordingly, CNGT's petition for waiver from 
    compliance with the requirements of 49 CFR 192.611(a) is granted under 
    the provisions set out in Alternate A and Alternate B (above) under the 
    heading Alternate Approach.
    
        Issued in Washington, DC on September 24, 1996.
    Richard B. Felder,
    Associate Administrator for Pipeline Safety.
    [FR Doc. 96-24863 Filed 9-26-96; 8:45 am]
    BILLING CODE 4910-60-P
    
    
    

Document Information

Published:
09/27/1996
Department:
Research and Special Programs Administration
Entry Type:
Notice
Action:
Notice of grant of waiver.
Document Number:
96-24863
Pages:
50900-50902 (3 pages)
Docket Numbers:
Docket No. P-96-8W, Notice 2
PDF File:
96-24863.pdf