2023-21047. Golden Triangle Storage, LLC; Notice of Application and Establishing Intervention Deadline  

  • Start Preamble

    Take notice that on September 12, 2023, Golden Triangle Storage, LLC (GTS), 919 Milam Street, Suite 2425, Houston, Texas 77002, filed an application under section 7(c) of the Natural Gas Act (NGA), and part 157 of the Commission's regulations requesting authorization for its Expansion Project (Project). The Project consists of expanding its existing natural gas storage facility in Jefferson County, Texas, through the construction and operation of two new salt dome storage caverns, additional compression, and other appurtenant facilities. The Project will meet documented market demand for increased storage capacity, enhance operational capabilities at the existing storage facilities, and ensure that GTS will be able to continue to offer safe, reliable storage services for both existing and new customers. Further, GTS requests reaffirmation of its market-based rate authority and related authorizations and waivers, all as more fully set forth in the application which is on file with the Commission and open for public inspection.

    In addition to publishing the full text of this document in the Federal Register , the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission's Home Page ( www.ferc.gov) using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission's Public Reference Room. For assistance, contact the Federal Energy Regulatory Commission at FercOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TTY (202) 502–8659.

    Any questions regarding the proposed project should be directed to James F. Bowe, Jr., King & Spalding LLP, 1700 Pennsylvania Avenue, Suite 900, Washington, DC 20006 by phone at Start Printed Page 66443 (202) 626–9601, or by email at jbowe@kslaw.com.

    Pursuant to section 157.9 of the Commission's Rules of Practice and Procedure,[1] within 90 days of this Notice the Commission staff will either: complete its environmental review and place it into the Commission's public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff's issuance of the final environmental impact statement (FEIS) or environmental assessment (EA) for this proposal. The filing of an EA in the Commission's public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify Federal and State agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all Federal authorizations within 90 days of the date of issuance of the Commission staff's FEIS or EA.

    Water Quality Certification

    GTS's application states that a water quality certificate under section 401 of the Clean Water Act is required for the project from the Texas Commission on Environmental Quality (TCEQ) and the Railroad Commission of Texas (RRC). The request for certification must be submitted to the certifying agency and to the Commission concurrently. Proof of the certifying agency's receipt date must be filed no later than five (5) days after the request is submitted to the certifying agency.

    Public Participation

    There are three ways to become involved in the Commission's review of this project: you can file comments on the project, you can protest the filing, and you can file a motion to intervene in the proceeding. There is no fee or cost for filing comments or intervening. The deadline for filing a motion to intervene is 5 p.m. eastern time on October 11, 2023. How to file protests, motions to intervene, and comments is explained below.

    The Commission's Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202)502–6595 or OPP@ferc.gov.

    Comments

    Any person wishing to comment on the project may do so. Comments may include statements of support or objections, to the project as a whole or specific aspects of the project. The more specific your comments, the more useful they will be.

    Protests

    Pursuant to sections 157.10(a)(4) [2] and 385.211 [3] of the Commission's regulations under the NGA, any person [4] may file a protest to the application. Protests must comply with the requirements specified in section 385.2001 [5] of the Commission's regulations. A protest may also serve as a motion to intervene so long as the protestor states it also seeks to be an intervenor.

    To ensure that your comments or protests are timely and properly recorded, please submit your comments on or before October 11, 2023.

    There are three methods you can use to submit your comments or protests to the Commission. In all instances, please reference the Project docket number CP23–542–000 in your submission.

    (1) You may file your comments electronically by using the eComment feature, which is located on the Commission's website at www.ferc.gov under the link to Documents and Filings. Using eComment is an easy method for interested persons to submit brief, text-only comments on a project;

    (2) You may file your comments or protests electronically by using the eFiling feature, which is located on the Commission's website ( www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on “eRegister.” You will be asked to select the type of filing you are making; first select “General” and then select “Comment on a Filing”; or

    (3) You can file a paper copy of your comments or protests by mailing them to the following address below. Your written comments must reference the Project docket number (CP23–542–000).

    To file via USPS: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426.

    To file via any other courier: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852.

    The Commission encourages electronic filing of comments (options 1 and 2 above) and has eFiling staff available to assist you at (202) 502–8258 or FercOnlineSupport@ferc.gov.

    Persons who comment on the environmental review of this project will be placed on the Commission's environmental mailing list, and will receive notification when the environmental documents (EA or EIS) are issued for this project and will be notified of meetings associated with the Commission's environmental review process.

    The Commission considers all comments received about the project in determining the appropriate action to be taken. However, the filing of a comment alone will not serve to make the filer a party to the proceeding. To become a party, you must intervene in the proceeding. For instructions on how to intervene, see below.

    Interventions

    Any person, which includes individuals, organizations, businesses, municipalities, and other entities,[6] has the option to file a motion to intervene in this proceeding. Only intervenors have the right to request rehearing of Commission orders issued in this proceeding and to subsequently challenge the Commission's orders in the U.S. Circuit Courts of Appeal.

    To intervene, you must submit a motion to intervene to the Commission in accordance with Rule 214 of the Commission's Rules of Practice and Procedure [7] and the regulations under the NGA [8] by the intervention deadline for the project, which is October 11, 2023. As described further in Rule 214, your motion to intervene must state, to the extent known, your position regarding the proceeding, as well as your interest in the proceeding. For an individual, this could include your status as a landowner, ratepayer, resident of an impacted community, or recreationist. You do not need to have property directly impacted by the project in order to intervene. For more information about motions to intervene, refer to the FERC website at https:// Start Printed Page 66444 www.ferc.gov/​resources/​guides/​how-to/​intervene.asp.

    There are two ways to submit your motion to intervene. In both instances, please reference the Project docket number CP23–542–000 in your submission.

    (1) You may file your motion to intervene by using the Commission's eFiling feature, which is located on the Commission's website ( www.ferc.gov) under the link to Documents and Filings. New eFiling users must first create an account by clicking on “eRegister.” You will be asked to select the type of filing you are making; first select “General” and then select “Intervention.” The eFiling feature includes a document-less intervention option; for more information, visit https://www.ferc.gov/​docs-filing/​efiling/​document-less-intervention.pdf.; or

    (2) You can file a paper copy of your motion to intervene, along with three copies, by mailing the documents to the address below. Your motion to intervene must reference the Project docket number CP23–542–000.

    To file via USPS: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426.

    To file via any other courier: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852.

    The Commission encourages electronic filing of motions to intervene (option 1 above) and has eFiling staff available to assist you at (202) 502–8258 or FercOnlineSupport@ferc.gov.

    Protests and motions to intervene must be served on the applicant either by mail or email at: James F. Bowe, Jr., King & Spalding LLP, 1700 Pennsylvania Avenue, Suite 900, Washington, DC 20006, or at jbowe@kslaw.com. Any subsequent submissions by an intervenor must be served on the applicant and all other parties to the proceeding. Contact information for parties can be downloaded from the service list at the eService link on FERC Online. Service can be via email with a link to the document.

    All timely, unopposed [9] motions to intervene are automatically granted by operation of Rule 214(c)(1).[10] Motions to intervene that are filed after the intervention deadline are untimely, and may be denied. Any late-filed motion to intervene must show good cause for being late and must explain why the time limitation should be waived and provide justification by reference to factors set forth in Rule 214(d) of the Commission's Rules and Regulations.[11] A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies (paper or electronic) of all documents filed by the applicant and by all other parties.

    Tracking the Proceeding

    Throughout the proceeding, additional information about the project will be available from the Commission's Office of External Affairs, at (866) 208–FERC, or on the FERC website at www.ferc.gov using the “eLibrary” link as described above. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings.

    In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. For more information and to register, go to www.ferc.gov/​docs-filing/​esubscription.asp.

    Intervention Deadline: 5 p.m. eastern time on October 11, 2023.

    Start Signature

    Dated: September 20, 2023.

    Kimberly D. Bose,

    Secretary.

    End Signature End Preamble

    Footnotes

    1.  18 CFR (Code of Federal Regulations) 157.9.

    Back to Citation

    4.  Persons include individuals, organizations, businesses, municipalities, and other entities. 18 CFR 385.102(d).

    Back to Citation

    9.  The applicant has 15 days from the submittal of a motion to intervene to file a written objection to the intervention.

    Back to Citation

    [FR Doc. 2023–21047 Filed 9–26–23; 8:45 am]

    BILLING CODE 6717–01–P

Document Information

Published:
09/27/2023
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2023-21047
Pages:
66442-66444 (3 pages)
Docket Numbers:
Docket No. CP23-542-000
PDF File:
2023-21047.pdf