01-24242. Grade Crossing Signal System Safety  

  • Start Preamble

    AGENCY:

    Federal Railroad Administration (FRA), Department of Transportation (DOT).

    ACTION:

    Final Rule.

    SUMMARY:

    On June 20, 1996, FRA published Interim Final Rule Amendments amending the regulations on grade crossing signal system safety. That rule required that railroads comply with specific maintenance, inspection, and testing requirements for active highway-rail grade crossing warning systems. The rule also required that railroads take specific and timely Start Printed Page 49558actions to protect the traveling public and railroad employees from the hazards posed by malfunctioning highway-rail grade crossing warning systems. Aside from the typographical and minor corrections made today, the final rule issued today is identical to the Interim Final Rule Amendments published on June 20, 1996.

    EFFECTIVE DATE:

    This final rule is effective on September 28, 2001.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    William Goodman, Staff Director, Signal and Train Control, Office of Safety, FRA, 400 Seventh Street, S.W. Washington, D.C. 20590 (telephone 202-493-6325), or Mark Tessler, Office of Chief Counsel, FRA, 400 Seventh Street, SW., Washington, DC 20590 (telephone 202-493-6061) (e-mail address: mark.tessler@fra.dot.gov).

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    Background

    On September 30, 1994, FRA published a final rule (59 FR 50086) requiring that railroads comply with specific maintenance, inspection, and testing requirements for active highway-rail grade crossing warning systems. The final rule also requires that railroads take specific and timely actions to protect the traveling public and railroad employees from the hazards posed by malfunctioning highway-rail grade crossing warning systems.

    On June 20, 1996 FRA published an Interim Final Rule which amended the rule issued in 1994 (61 FR 31802). The Interim Final Rule addressed issues raised as a result of actual experience under the new regulations. In addition, shortly after the regulations were issued, an FRA Technical Resolution Committee (TRC) met to discuss the regulations, their interpretation and implementation. Included in the TRC were FRA signal and train control specialists from across the country along with headquarters staff. Representatives from rail labor and management were invited to attend certain sessions as non-voting members to offer their perspective and expertise to the group, together with representatives of two States active in FRA's State Participation Program. Although the purpose of this TRC was to develop the appropriate application and interpretation of the final rule, the discussion, together with other lessons learned during implementation, also indicated the need to clarify certain portions of the regulatory text. Additionally, the American Short Line Railroad Association, the Brotherhood of Railroad Signalmen, and the Association of American Railroads jointly filed a Petition for Reconsideration with FRA requesting that FRA stay enforcement of certain sections of the final rule (§§ 234.215 and 234.223) pending further consideration of those provisions. Subsequent to the joint filing, FRA issued an Interim Policy Manual addressing, among others, the issues and questions raised by the petitioners. FRA granted the petition for reconsideration although it did not agree to stay enforcement since enforcement issues had been addressed in the Interim Policy Manual. The Interim Final Rule was in part a response to the joint petition for reconsideration.

    FRA received a number of comments on the Interim Final Rule. The following discussion addresses those comments.

    The Brotherhood of Railroad Signalmen (BRS) pointed out typographical errors in §§ 234.215 and 234.247(b). Those errors are being corrected.

    Section-By-Section Analysis

    The majority of changes contained in the Interim Final Rule generated no comments. Accordingly, the following section-by-section analysis addresses only those sections about which comments were received.

    Section 234.7 Accidents Involving Grade Crossing Signal Failure

    The Illinois Department of Transportation suggested that the term “activation failure” in the first sentence of § 234.7(a) should be replaced with the term “warning system malfunction” which would then include partial activation and false activation as situations for which telephonic reports of accidents must be made. This section requires reports within 24 hours of occurrence of impact accidents involving activation failure. Because activation failures are much more likely to immediately result in accidents, FRA needs information regarding these malfunctions as soon as possible. Telephonic reports of accidents involving partial and false activations would not materially assist FRA in its safety function, while requiring such reports would place an undue administrative burden on the railroad. FRA will still receive information pertaining to partial activations and false activations in the normal course of accident reporting. This information, together with the record keeping requirements of § 234.109, will provide FRA sufficient information with which to monitor compliance with this part and grade crossing safety generally.

    Section 234.9 Grade Crossing Signal System Failure Reports

    The Illinois Department of Transportation recommends that the term “activation failure” be replaced in this section with the all encompassing term “warning system malfunction”. This change would have the effect of requiring that partial activations and false activations be reported to FRA within 15 days of occurrence. This requirement would burden railroads with a reporting requirement while providing FRA with information not needed on such a short time frame. FRA's information requirements will be adequately served by the record keeping requirements of § 234.109. Under that section, records of partial activations and false activations will be available to FRA for a period of one year after the occurrence. The availability of those records will provide FRA with sufficient information for safety oversight. Therefore, the change suggested by the Illinois Department of Transportation's suggestion will not be adopted.

    Section 234.217 Flashing Light Units

    The Iowa Department of Transportation (Iowa DOT) recommended that the last sentence of paragraph (b) be amended. This paragraph presently states: “Each flashing light unit shall be maintained to prevent dust and moisture from entering the interior of the unit. Roundels and reflectors shall be clean and in good condition.” Iowa DOT suggests adding to the last sentence “including the condition of the paint adequate to provide a contrasting dark background.”

    We agree with the importance of maintaining conditions which ensure that the light unit maintain its visibility to the motorist. Essential to good visibility is the non-reflective black finish of the light hood and background surrounding the light. Maintaining a contrasting dark background contributes to the light's visibility. The present language of the rule is adequate to cover the situation in which the background or hood are in such a condition that the background does not provide sufficient contrast. FRA expects that the railroad responsible for maintenance of the crossing warning system will comply with § 234.207 which requires that “when any essential component of a highway-rail grade crossing warning system fails to perform its intended function, the cause shall be determined and the faulty component adjusted, repaired, or replaced without undue delay.” The railroad thus has the responsibility to repair or replace Start Printed Page 49559backgrounds or hoods if they fail to perform their intended function—to provide adequate contrasting background in the case of the background, and to provide a non-reflective shade in the case of the hood. FRA expects that the railroad responsible for maintenance of the grade crossing warning system will comply with § 234.207 in these situations. FRA Signal and Train Control inspectors will be prepared to enforce this section accordingly.

    Section 234.225 Activation of Warning System

    The Illinois Department of Transportation recommended that language be added to the present regulatory section as follows: “Where highway traffic signals and railroad warning signals are interconnected, additional warning time may be required to enable the traffic signals to clear the intersection and display a green signal for the track approach leg of the intersection. This time will vary depending on the length of storage distance between the tracks and the highway intersection.”

    This important subject has been addressed by the Secretary of Transportation's Technical Working Group. The language proposed by the Illinois DOT is best approached as a general guideline to be used in certain situations rather than as a regulatory requirement. The Technical Working Group has recommended that practitioners, when planning and designing preemption systems, use guidance found in the Institute of Transportation Engineers (ITE) revised Recommended Practices (ITE Journal, February 1997) “Design Guidelines for Railroad Preemption at Signalized Intersections.”

    Section 234.245 Signs

    One commenter suggested that this section require that signs “shall reflect current site conditions.” The content of signs mounted on grade crossing signal posts is not an appropriate matter for a rule dealing with maintenance, inspection and testing and is beyond the scope of this proceeding. The information needed to be conveyed on a signal post is dependent on a decision by the state or local transportation authority having jurisdiction over the highway crossing the railroad tracks and is subject to the requirements of the Federal Highway Administration's Manual on Uniform Traffic Control Devices (MUTCD).

    Section 234.247 Purpose of Inspections and Tests; Removal From Service of Relay or Device Failing To Meet Test Requirements

    The BRS questioned whether a railroad has an obligation under § 234.247, to respond to reports of false activations while a track is out of service. A railroad would have an obligation to respond to any false activation reports since the motorist will be responding to the grade crossing warning system irrespective of the status of rail service. However, this section would not apply if the grade crossing warning system is temporarily taken out of service when the tracks over the grade crossing are taken out of service or when the railroad suspends operations during a portion of the year. Of course, a full inspection and all required tests must be successfully completed before railroad operations over the grade crossing resume. This section is being revised to eliminate the typographical error of in which the phrase “or the railroad suspends operations during a portion of the year” appeared twice in paragraph (b).

    Section 234.261 Highway Traffic Signal Preemption

    Iowa Department of Transportation suggests that this section be amended by adding the following paragraphs: “(b) A tag or marking shall be affixed inside the control unit for any railroad signal which is interconnected with a highway traffic signal. In addition to the words “WARNING, INTERCONNECTION WITH HIGHWAY TRAFFIC SIGNALS,” the name, date and telephone number of the responsible highway authority shall be posted therein in a legible manner and be maintained current as of the date of the last contact with that authority. (c) The responsible highway authority shall be contacted immediately when any change is made in the crossing warning system that affects the operation of the highway traffic signal system.”

    This concept has been addressed by the Secretary's Technical Working Group. A form similar to that suggested by Iowa DOT has been developed and is being distributed throughout the country for placement in both grade crossing signal cases and in highway traffic signal cases. The form states in part: “Highway-Rail Grade Crossing Warning System and Highway Traffic Signals are Interconnected. BEFORE MODIFICATION is made to any operation which connects to or controls the timing of an active railroad warning system and/or timing and phasing of a traffic signal the appropriate party(ies) shall be notified and, if necessary, a joint inspection conducted.” The form contains the U.S. DOT/AAR Crossing Number together with contact names and phone numbers for the appropriate highway agency and railroad. This voluntary approach has been working very well and there does not appear to be any need to regulate this issue.

    Executive Order 12866 and DOT Regulatory Policies and Procedures

    These amendments have been evaluated in accordance with existing policies and procedures. Because these amendments are primarily technically oriented and generally reduce the regulatory burden on railroads, FRA has concluded that this revisions do not constitute a significant rule under either Executive Order 12866 or DOT's regulatory policies and procedures.

    Regulatory Flexibility Act

    The Regulatory Flexibility Act of 1980 (5 U.S.C. 601 et seq.) requires a review of rules to assess their impact on small entities. FRA certifies that this rule will not have a significant impact on a substantial number of small entities. There are no substantial economic impacts for small units of government, businesses, or other organizations.

    Paperwork Reduction Act

    These amendments to part 234 do not change any information collection requirements.

    Environmental Impact

    FRA has evaluated these regulations in accordance with its procedure for ensuring full consideration of the potential environmental impacts of FRA actions, as required by the National Environmental Policy Act (42 U.S.C. 4321 et seq.) and related directives. FRA has determined that this final rule is not a major FRA action requiring the preparation of an environmental impact statement or environmental assessment.

    Federalism

    FRA believes it is in compliance with Executive Order 13132. This final rule will not have a substantial effect on the States, on the relationship between the national government and the States, or on the distribution of power and responsibilities among the various levels of government. This final rule will not have federalism implications that impose substantial direct compliance costs on State and local governments.

    Start List of Subjects

    List of Subjects in 49 CFR Part 234

    • Highway safety
    • Railroad safety
    • Reporting and recordkeeping requirements
    End List of Subjects Start Printed Page 49560

    The Rule

    Start Amendment Part

    In consideration of the foregoing, the interim final rule revising 49 CFR part 234 which was published at 61 FR 31802 on June 20, 1996, is adopted as a final rule with the following changes:

    End Amendment Part Start Part

    PART 234—GRADE CROSSING SIGNAL SYSTEM SAFETY

    End Part Start Amendment Part

    1. The authority citation for part 234 continues to read as follows:

    End Amendment Part Start Authority

    Authority: 49 U.S.C. 20103, 20107, and 49 CFR 1.49.

    End Authority Start Amendment Part

    2. Revise § 234.215 to read as follows:

    End Amendment Part
    Standby power system.

    A standby source of power shall be provided with sufficient capacity to operate the warning system for a reasonable length of time during a period of primary power interruption. The designated capacity shall be specified on the plans required by § 234.201 of this part.

    Start Amendment Part

    3. Revise § 234.247(b) to read as follows:

    End Amendment Part
    Purpose of inspections and tests; removal from service of relay or device failing to meet test requirements.
    * * * * *

    (b) If a railroad elects not to comply with the requirements of §§ 234.249 through 234.271 because all tracks over the grade crossing are out of service or the railroad suspends operations during a portion of the year, and the grade crossing warning system is also temporarily taken out of service, a full inspection and all required tests must be successfully completed before railroad operations over the grade crossing resume.

    * * * * *
    Start Signature

    Issued in Washington, D.C. on September 19, 2001.

    Allan Rutter,

    Federal Railroad Administrator.

    End Signature End Supplemental Information

    [FR Doc. 01-24242 Filed 9-27-01; 8:45 am]

    BILLING CODE 4910-06-P

Document Information

Effective Date:
9/28/2001
Published:
09/28/2001
Department:
Federal Railroad Administration
Entry Type:
Rule
Action:
Final Rule.
Document Number:
01-24242
Dates:
This final rule is effective on September 28, 2001.
Pages:
49557-49560 (4 pages)
Docket Numbers:
FRA Docket No. RSGC-5, Notice No. 9
RINs:
2130-AA97: Maintenance, Inspection, and Testing of Grade-Crossing Signal Systems
RIN Links:
https://www.federalregister.gov/regulations/2130-AA97/maintenance-inspection-and-testing-of-grade-crossing-signal-systems
Topics:
Highway safety, Railroad safety, Reporting and recordkeeping requirements
PDF File:
01-24242.pdf
CFR: (2)
49 CFR 234.215
49 CFR 234.247