98-25936. El Paso Natural Gas Company; Notice of Request Under Blanket Authorization  

  • [Federal Register Volume 63, Number 188 (Tuesday, September 29, 1998)]
    [Notices]
    [Page 51907]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-25936]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    [Docket No. CP98-777-000]
    
    
    El Paso Natural Gas Company; Notice of Request Under Blanket 
    Authorization
    
    September 23, 1998.
        Take notice that on September 14, 1998, El Paso Natural Gas 
    Company, (El Pasco) PO Box 1492, El Paso, Texas 79978, filed in Docket 
    No. CP98-777-000 a request pursuant to Sections 157.205 and 157.212 of 
    the Commission's Regulations under the Natural Gas Act (18 CFR 157.205, 
    157.212). El Paso filed for authorization to upgrade an existing bi-
    directional meter station in Lea County, New Mexico, under El Paso's 
    blanket certificates issued in Docket No. CP82-435 and CP88-433-000, 
    pursuant to Section 7 of the Natural Gas Act, all as more fully set 
    forth in the request that is on file with the Commission and open to 
    public inspection.
        Specifically, El Paso would upgrade its Grama Ridge Meter Station 
    by changing one of the three existing orifice plates with a new 5.75 
    bore orifice plate. The new 5.75 orifice would initiate an increase of 
    the maximum peak day capacity from 50,000 Mcf to 95,000 Mcf of natural 
    gas for LG&E Natural Gathering and Processing Company's anticipated 
    increase in storage withdrawal and injection at its storage facility in 
    Lea County. El Paso estimates the cost to upgrade the station at $200 
    and states that it has sufficient capacity to accomplish the 
    transportation of the increased service without detriment or 
    disadvantage to its other customers.
        Any person or the Commission's staff may, within 45 days after 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
    intervene or notice of intervention and pursuant to Section 157.205 of 
    the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to 
    the request. If no protest is filed within the time allowed therefor, 
    the proposed activity shall be deemed to be authorized effective the 
    day after the time allowed for filing a protest. If a protest is filed 
    and not withdrawn within 30 days after the time allowed for filing a 
    protest, the instant request shall be treated as an application for 
    authorization pursuant to Section 7 of the Natural Gas Act.
    David P. Boergers,
    Secretary.
    [FR Doc. 98-25936 Filed 9-28-98; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
09/29/1998
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
98-25936
Pages:
51907-51907 (1 pages)
Docket Numbers:
Docket No. CP98-777-000
PDF File:
98-25936.pdf