DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP98-792-000]
Texas Eastern Transmission Corporation; Notice of Request Under
Blanket Authorization
September 23, 1998.
Take notice that on September 18, 1998, Texas Eastern Transmission
Corporation (Texas Eastern) 5400 Westheimer Court, Houston, Texas
77056-5310, filed in Docket No. CP98-792-000 a request pursuant to
Sections 157.205 and 157.211 of the Commission's Regulations under the
Natural Gas Act for authorization to construct a delivery point in
Madison County, Kentucky, so that Texas Eastern may provide natural gas
deliveries to Delta Natural Gas Company (Delta), a local distribution
company and existing Texas Eastern customer. Texas Eastern makes this
request, all as more fully set forth in the request for authorization
on file with the Commission and open for public inspection, under its
blanket certificate issued in Docket No. CP82-535-000.\1\
---------------------------------------------------------------------------
\1\ See, 21 FERC para. 62,199 (1982).
---------------------------------------------------------------------------
Texas Eastern proposes to construct and install dual 2-inch tap
valves, dual 2-inch isolation valves, a 2-inch check valve and a 2-inch
insulating flange on Texas Eastern's existing 30-inch Line Nos. 10 and
15 at approximate Mile Post 457.99 in Madison County, Kentucky (Tap).
In addition to the facilities described above, Delta will install, or
cause to be installed, a dual 2-inch turbine meter plus associated
piping (Meter Station), approximately 100 feet of 2-inch pipeline which
will extend from the Meter Station to the Tap (Connecting Pipe), and
electronic gas measurement equipment (EGM).
Delta will reimburse Texas Eastern for 100% of the costs and
expenses that Texas Eastern will incur for installing the Tap and for
reviewing and inspecting the installation of the Meter Station,
Connecting Pipe, and EGM. Such costs and expenses are estimated to be
approximately $34,611, including an allowance for federal income taxes.
Texas Eastern states that the transportation service will be
rendered pursuant to Texas Eastern's Open Access Rate Schedules of
Texas Eastern's FERC Gas Tariff, Volume No. 1. Texas Eastern's existing
tariff does not prohibit the addition of this facility. Texas Eastern
states that the installation of the delivery point will have no effect
on Texas Eastern's peak day or annual deliveries. Texas Eastern submits
that its proposal will be accomplished without detriment or
disadvantage to Texas Eastern's other customers.
Any person or the Commission's staff may, within 45 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to Section 157.205 of
the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to
the request. If no protest is filed within the time allowed therefor,
the proposed activity shall be deemed to be authorized effective the
day after the time allowed for filing a protest. If a protest is filed
and not withdrawn within 30 days after the time allowed for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to Section 7 of the Natural Gas Act.
David P. Boergers,
Secretary.
[FR Doc. 98-25938 Filed 9-28-98; 8:45 am]
BILLING CODE 6717-01-M