DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Application Filed with the Commission
September 23, 1998.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Action: Notice of Final Design, Construction Methods,
and Timing of Construction Activities, Including Final Design Drawings
and Specifications for the North Shore Erosion Control Plan for the
Kerr Hydroelectric Project.
b. Project No.: 5-041.
c. Filing Date: June 24, 1998.
d. Licensee: Montana Power Company and Confederated Salish and
Kootenai Tribes of the Flathead Reservation.
e. Name of Project: Kerr Hydroelectric Project.
f. Location: Flathead River, Flathead and Lake Counties, Montana.
g. Authorization: Article 73 of the project license.
h. Licensee contact: Mr. Larry Thompson, General Manager, Power
Generation, Montana Power Company, 40 East Broadway, Butte, MT 59701-
9394, (406) 723-5421.
i. FERC Contact: Robert Grieve (202) 219-2655.
j. Comment Date: November 4, 1998.
k. Description of Proceeding: Article 73 requires the licensee to
file final design, construction methods, and timing of construction
activities, including final design drawings and specifications, for the
north shore erosion control plan at Flathead Lake. Article 73 also
requires the licensee, in addition to erosion control measures to be
located along the Flathead Waterfowl Production Area (WPA) on Flathead
Lake, to construct a shore-aligned erosion protection segment east of
the WPA eastern boundary. The licensee's filing includes the design,
construction methods, and timing of construction activities for: (1) a
shore-aligned revetment structure of approximately 3,400 feet located
on the west side of the Flathead River mouth extending northwest, which
will adjoin an existing 200-foot-long revetment; (2) a shore-aligned
revetment structure of approximately 4,400 feet located on the east
side of the Flathead River mouth extending east to the eastern boundary
of the WPA; and (3) riverbank protection along the west side of the
Flathead River from the river mouth extending north to the northern
boundary of the WPA. The filing did not include the design for the
shore-aligned erosion protection segment east of the WPA as required by
article 73. The licensee states that because offshore revetments along
the WPA are no longer required, a transition structure to prevent
additional erosion is no longer necessary. In addition, the subject
revetment is not needed to protect wildlife habitat on the WPA.
Further, in conveying the parcels of private property, the licensee
reserved easements permitting it to flood these properties and
otherwise affect the land in connection with operation of the project.
By this notice, the Commission requests comments on the licensee's
[[Page 51915]]
plan as filed, to include the licensee's exclusion of the erosion
protection segment east of the WPA boundary.
1. This notice also consists of the following standard paragraphs:
B, C1, and D2.
B. Comments, Protests, or Motions to Intervene--Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214. In determining the appropriate action to take, the Commission
will consider all protests or other comments filed, but only those who
file a motion to intervene in accordance with the Commission's Rules
may become a party to the proceeding. Any comments, protests, or
motions to intervene must be received on or before the specified
comment date for the particular application.
C1. Filing and Service of Responsive Documents--Any filings must
bear in all capital letters the title ``COMMENTS'', ``RECOMMENDATIONS
FOR TERMS AND CONDITIONS'', ``PROTEST'', OR ``MOTION TO INTERVENE'', as
applicable, and the Project Number of the particular application to
which the filing refers. Any of the above-named documents must be filed
by providing the original and the number of copies provided by the
Commission's regulations to: The Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE, Washington, DC 20426. A copy of any
motion to intervene must also be served upon each representative of the
Applicant specified in the particular application.
D2. Agency Comments--Federal, state, and local agencies are invited
to file comments on the described application. A copy of the
application may be obtained by agencies directly from the Applicant. If
an agency does not file comments within the time specified for filing
comments, it will be presumed to have no comments. One copy of an
agency's comments must also be sent to the Applicant's Representatives.
David P. Boergers,
Secretary.
[FR Doc. 98-25939 Filed 9-28-98; 8:45 am]
BILLING CODE 6717-01-M