[Federal Register Volume 59, Number 189 (Friday, September 30, 1994)]
[Unknown Section]
[Page 0]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 94-24080]
[[Page Unknown]]
[Federal Register: September 30, 1994]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Research and Special Programs Administration
49 CFR Parts 192 and 195
RIN 3137-AB71
[Docket No. PS-126; Notice 2]
Passage of Instrumented Internal Inspection Devices
AGENCY: Research and Special Programs Administration (RSPA), DOT.
ACTION: Notice of Proposed Rulemaking; Response to Petitions for
Reconsideration.
-----------------------------------------------------------------------
SUMMARY: On April 12, 1994, RSPA published a final rule requiring that
new and replaced pipeline facilities be constructed to accommodate
inspection by instrumented internal inspection devices commonly known
as ``smart pigs.'' RSPA has received two petitions for reconsideration
of that rule as it applies to gas pipelines. In response to those
petitions, this notice proposes to modify the rule with respect to:
Replacements in gas transmission lines located in less populated areas;
and replacements in gas transmission lines located offshore. In
addition, in order to allow completion of rulemaking on these
proposals, this notice proposes limited extension of the compliance
dates for certain current requirements. Finally, this document
announces RSPA's decision with respect to other matters raised in the
petitions.
DATES: Comments on the limited extension of the compliance dates for
current requirements are due October 31, 1994. Comments on other
modifications of the rule are due November 29, 1994. Commenters should
submit as part of their written comments all the material that is
considered relevant to any statement of fact or argument made.
ADDRESSES: Comments may be mailed or hand delivered to the Dockets Unit
[DHM-20], Room 8421, Research and Special Programs Administration, U.S.
Department of Transportation, 400 Seventh St., SW., Washington, DC
20590-0001. Telephone: (202) 366-5046. Comments should identify the
Docket No. and Regulatory Identification Number (RIN) stated in the
heading of this document; the original and two copies should be
submitted. Persons wishing to receive confirmation of receipt of their
comments should include a self addressed stamped envelope. Public
Dockets may be reviewed and copied between the hours of 8:30 a.m. and
4:30 p.m., Monday through Friday, except Federal holidays.
FOR FURTHER INFORMATION CONTACT: Albert C. Garnett, (202) 366-2036,
Office of Pipeline Safety, regarding the subject matter of this notice,
or Dockets Unit, (202) 366-5046 for copies of this notice or other
materials in the docket.
SUPPLEMENTARY INFORMATION:
Background
RSPA published a final rule under Docket No. PS-126 (Amendments
190-5, 192-72, 193-9, and 195-50) requiring operators of gas, hazardous
liquid and carbon dioxide pipelines to design and construct new
pipelines and portions of pipelines on which replacements are made to
accommodate the passage of smart pigs (59 FR 17275; April 12, 1994).
Among the provisions for gas transmission lines, 49 CFR 192.150(a)
requires that:
* * * each new transmission line and each line section of a
transmission line where the line pipe, valve, fitting or other line
component is replaced must be designed and constructed to
accommodate the passage of instrumented internal inspection devices.
The term ``line section'' was defined (in Sec. 192.3) as a
continuous run of transmission line between adjacent compressor
stations, between a compressor station and storage facilities, between
a compressor station and a block valve, or between adjacent block
valves. It was derived from a definition already in use for hazardous
liquid and carbon dioxide pipelines (Sec. 195.2).
Several specific exceptions to the requirements in Sec. 192.150(a)
are provided, including one for offshore gas transmission lines less
than 10 inches in nominal diameter that transport gas to onshore
facilities. In addition, under Sec. 192.150(b)(8) an operator may seek
a specific exception to be based upon a RSPA finding that it would be
impracticable to design and construct a transmission line for the
passage of smart pigs.
Requests for Stay and Petitions for Reconsideration
The Interstate Natural Gas Association of America (INGAA) filed a
``Request for a Stay of the Effective Date [May 12, 1994] of the Final
Rule; Passage of Instrumented Internal Inspection Devices'' dated May
4, 1994. INGAA requests that RSPA stay until at least January 1, 1995,
that provision of the final rule requiring a line section, as defined
in 49 CFR Sec. 192.3, to be modified to accommodate smart pigs whenever
a line pipe, valve, fitting, or other line component is replaced in a
line section. To support their request for a stay, INGAA notes that the
1994 summer replacement/rehabilitation work is in progress and that
funds for modification of line sections have not been allocated by
operators. INGAA also argues that there was procedural error in the
rulemaking process.
INGAA also filed a ``Petition for Reconsideration of the Final
Rule; Passage of Instrumented Internal Inspection Devices'' dated May
10, 1994. INGAA asks that the definition of ``line section'' be deleted
from 49 CFR Sec. 192.3 and that all offshore gas transmission lines be
exempt from the final rule. Issues raised by INGAA to support its
request for deletion of ``line section'' are lack of authority to
promulgate such a rule and procedural error. INGAA points to technical
infeasibility and impracticability to support its request for exemption
of offshore gas transmission lines.
The American Gas Association (AGA) filed a ``Request for
Administrative Stay of the May 12, 1994 effective date and Petition for
Reconsideration of RSPA's Final Rule on Passage of Instrumented
Internal Inspection Devices.'' Arguing that immediate implementation
would harm public safety by diverting funds from other safety projects,
AGA requests that RSPA immediately stay the effective date with respect
to replacement of line sections. In addition, AGA requests that RSPA
grant reconsideration of the final rule in order to address the costs,
benefits, and practicability of the replacement requirement to modify
the complete line section to accommodate smart pigs. To support this,
AGA argues that RSPA failed to consider the standards for pipeline
safety rules set out in 49 U.S.C. Sec. 60102(b) (formerly section 3(a)
of the Natural Gas Pipeline Safety Act); there was no opportunity for
public comment on the definition of line section; the Technical
Pipeline Safety Standards Committee (TPSSC) was not given opportunity
to review relevant provisions; and the final rule was not reviewed by
the Office of Management and Budget (OMB).
The three documents submitted by INGAA and AGA are in the docket.
Stay of Compliance With Line Section Replacement
In its request to stay application of the line section replacement
provision of the final rule, INGAA explained that ``almost all
decisions, to include funding, for pipeline replacement and
rehabilitation are made at least a year preceding the summer work
season * * *'' INGAA states that the one year lag time includes time
required for ``design work, obtaining bids for work, selecting
contractors, ordering material, obtaining approval from FERC (Federal
Energy Regulatory Commission), performing environmental analyses and
obtaining Federal and State environmental and archaeological permits
when necessary, and obtaining landowner approval for right-of-way work
on their property.'' As a result, INGAA believes that it is ``far too
late to comply with a May 12, 1994, effective date to make `line
sections' piggable''. AGA echoes this sentiment by stating that if the
May 12, 1994, effective date of the final rule remains in place,
``pipeline replacement projects currently in progress for 1994 would
have to be canceled, since the administrative permits and plans for
such projects were in place during the winter of 1993-94.''
The concerns expressed by INGAA and AGA led RSPA to advise INGAA,
AGA, and the American Petroleum Institute on May 12, 1994, that it was
suspending enforcement, until further notice, of the final rule insofar
as it requires making the entire line section accommodate smart pigs if
the line pipe, valve, fitting or other component is replaced. The
suspension did not effect the requirements that pipeline operators
design and construct new onshore and offshore pipelines or the actual
line pipe, valve, fitting or other line component being replaced to
accommodate smart pigs. Furthermore, operators were encouraged to
voluntarily modify any obstructions in the line section to accommodate
smart pigs whenever any replacement is made.
This notice addresses INGAA's and AGA's request for a stay in a
more formal manner. First, this notice proposes to extend the
compliance date for replacements made in gas transmission pipelines to
allow operators to continue replacing any line pipe, valve, fitting or
other line component (with a replacement that accommodates smart pigs)
without requiring that any other obstructions in the line section be
designed and constructed to accommodate smart pigs. As discussed below,
RSPA is proposing to partially grant reconsideration of the final rule
as it applies to replacements in gas transmission pipelines. At the
same time, we are proposing to extend compliance dates to allow for
completion of rulemaking on the reconsideration. Second, the suspension
of enforcement with respect to gas transmission pipelines will remain
in effect until February 2, 1995, or until RSPA finalizes action with
respect to compliance dates, whichever is earlier.
Effect on Hazardous Liquid and Carbon Dioxide Pipelines
The petitions for reconsideration and requests for administrative
stay received addressed only gas transmission pipelines. However,
because of the possibility that the issues raised could be equally
applicable to hazardous liquid and carbon dioxide pipelines, the
suspension of enforcement applied equally to hazardous liquid and
carbon dioxide pipelines.
RSPA has considered whether the reconsideration granted in this
notice with respect to aspects of the final rule as they apply to gas
transmission lines should be expanded to hazardous liquid and carbon
dioxide pipelines. RSPA has decided not to expand the reconsideration
to include hazardous liquid and carbon dioxide pipelines. First, there
has been no request to do so. Second, hazardous liquid pipelines pose
environmental risks generally unrelated to the population surrounding
the pipelines. The relief proposed below with respect to gas
transmission lines arise from the nature of those pipelines and their
location with respect to population. Finally, based on data collected
by RSPA (below) in 1989, approximately 41.7% of (136,359 miles) of
natural gas transmission lines were not able to accommodate a smart pig
for reasons other than lack of launchers or receivers, while only 10.5%
(16,275 miles) of hazardous liquid pipelines were similarly not
piggable.
Because RSPA is not proposing any changes in the final rule with
respect to hazardous liquid and carbon dioxide pipelines, the
suspension of enforcement with respect to those lines is immediately
(insert date of publication of this NPRM) lifted and compliance will be
enforced.
Replacements
A. Authority for Requirement
INGAA argues that RSPA lacks the authority to promulgate a rule
requiring operators to modify line sections to accommodate smart pigs
when portions of the sections are replaced. INGAA bases its argument on
the assumption that the statutory authority for the rule is the change
to the basic authorities for requiring modification of existing
pipelines to accommodate smart pigs that was made by sections 103 and
203 of the Pipeline Safety Act of 1992 (P.L. 102-508, Oct. 24, 1992).
That change authorizes RSPA to require changes to existing lines whose
basic construction would accommodate a smart pig. The 1992 authority
would allow RSPA to require the installation of launchers and receivers
in lines that already can be smart ``pigged'' should the decision be
made in a future rulemaking that the line must be so inspected. INGAA's
assumption that RSPA was relying on this 1992 amendment in this
rulemaking is incorrect.
The requirement in the final rule for replacement of the line
section is based upon authority enacted in 1988 that now reads:
The Secretary shall prescribe minimum safety standards requiring
that the design and construction of a new gas pipeline transmission
facility or hazardous liquid pipeline facility, and the required
replacement of an existing gas pipeline transmission facility,
hazardous liquid pipeline facility, or equipment, be carried out, to
the extent practicable, in a way that accommodates the passage
through the facility of an instrumented internal inspection device
(commonly referred to as a ``smart pig'').
49 U.S.C. 60102 (f). This section supports the final rule that requires
any needed changes to the line section to accommodate smart pigs
whenever one or more components must be replaced. A more narrow
reading, one in which only the individual components must be made smart
``piggable'', would render the provision virtually meaningless. This is
so because the factors that restrict ``piggability'' are often related
to the geometry of the line (such as bends) rather than to an
individual component (such as a valve). The use of valves that cannot
accommodate smart pigs is largely in pipelines in which the geometry
does not allow inspection by smart pigs. Thus a more narrow reading, in
which only the single component being replaced must accommodate the
internal inspection by smart pigs, would result in virtually no change
in the ``piggability'' of existing pipelines. Congress clearly intended
that change in the ``piggability'' occur.
Accordingly, RSPA has the authority to issue the final rule.
However, as discussed below, RSPA agrees that there may be instances in
which the final rule requires that modifications be made to the entire
line section which may not be feasible.
B. Scope of the Notice
AGA and INGAA argue that both the definition of ``line section''
and the mandatory modification of line sections were not included in
the proposed rule, effectively precluding meaningful comment. AGA and
INGAA claim that the notice of proposed rulemaking was so inadequate as
to violate the requirement of the Administrative Procedure Act (APA)
for notice and comment in the informal rulemaking process.
The notice proposed that each ``replacement transmission line''
(or, for hazardous liquid pipelines, each ``replacement pipeline'') be
made to accommodate smart pigs. Much of the comment on the issue of
replacement questioned the scope of the terms ``replacement
transmission lines'' and ``replacement lines.'' Commenters speculated
about the end points of the segments of lines that had to be made to
accommodate smart pigs when a replacement was required. Under the
proposed language, any replacement in a transmission line could require
modification of the entire line to accommodate smart pigs. AGA itself
expressed concern that the proposed rule would be read to require
altering an entire transmission line.
Recommendations to narrow the terms for replacement used in the
proposed rule by substituting the term ``line section'' came from
comments to the proposed rule filed by a pipeline trade association and
a pipeline operator. These two commenters favored the term because it
was already defined in 49 CFR 195.2 and it clearly set out the length
to be made to accommodate smart pigs. Other commenters suggested
similar terms such as ``replacement transmission section'' (recommended
by AGA), ``segment'', and ``line segment''. However, none of these
terms was as clearly defined as ``line section'', and RSPA, on the
basis of the comments, chose to adopt the more recognized term to
clarify the intent of the rule. This solution to the concerns raised by
the commenters is clearly within the scope of the broadly worded
proposal.
Accordingly, RSPA provided an opportunity for meaningful comment,
consistent with the APA.
C. Advisory Committee Review
Both petitioners complain that there was no opportunity for
consideration by the Technical Pipeline Safety Standards Committee
(TPSSC) of the requirement to modify replacement line sections to
accommodate smart pigs because line section was not mentioned in the
notice or in the summary of comments that was prepared by RSPA for the
August 3, 1993 TPSSC meeting. Consistent with 49 U.S.C. 60115, RSPA
presented the published Notice of Proposed Rulemaking to the TPSSC. In
addition, RSPA passed out a draft summary of the comments. The TPSSC
accepted the proposed rule as reasonable, feasible and practicable
provided several changes were incorporated. Since the TPSSC reviews and
advises on the proposed rule, it is understandable that the final rule
may differ from the proposal considered or accepted by that committee.
In this case, the final rule was drafted and published some eight
months later. Although RSPA is required to consider the TPSSC's advice
(but is not obligated to adopt any of the TPSSC's recommendations),
several issues raised by the TPSSC were incorporated in the final rule.
Accordingly, RSPA considered the TPSSC recommendations in an
appropriate manner.
D. Economic Impact
Both INGAA and AGA claim that RSPA failed to consider adequately
the economic impact of the replacement aspect of the final rule.
However, many of the changes RSPA incorporated into the final rule were
done at least in part because of economic arguments advanced by
commenters. For example, based on INGAA's and AGA's comments to the
NPRM, RSPA incorporated the procedure to address unforeseen
contingencies in replacements (Sec. 192.150(c)); a clear exception for
gas gathering lines (Sec. 192.9); an exception for pipelines located in
storage fields because of the small diameter piping configured in a
grid-like pattern (Sec. 192.150(b)(3)); and an exception for
transmission pipelines within a distribution system
(Sec. 192.150(b)(6)). In addition, the definition of ``line section''
was developed in part to address AGA concerns that ``pigging'' a short
segment is not economically feasible and that the proposed rule could
be read to require modification of the entire transmission line. Each
of these incorporated changes reduced the economic impact of the final
rule.
INGAA points to the costs of obtaining needed approvals for
replacement projects from the Federal Energy Regulatory Commission
(FERC), Federal and state environmental and archaeological agencies,
and property owners. INGAA claims that some of these may take a year or
more to obtain. To the extent that approvals are needed before work on
the line can be done, the final rule provides for delays. In response
to INGAA and AGA comments, Sec. 192.150(c) sets out a procedure to
allow an operator to delay required modifications to the line section
for up to one year should situations such as delays in needed approvals
occur. However, many replacements will not require approvals. For
example, FERC regulation 18 CFR Sec. 2.55 does not require prior
approval whenever the replacement is less than $6.6 million (1994
limit) and does not reduce service or change the capacity of the line.
Certainly the replacement of certain obstructions such as reduced port
valves and short radius bends will fall into this category and not
require any approval from FERC.
Both INGAA and AGA argue that the requirement to modify other
obstructions in the line section whenever a replacement is made will
potentially increase the cost of compliance with the final rule to over
$100 million per year. However, very little cost data was provided to
support the argument. Moreover, based on information now available
about numbers of gas transmission lines that will not accommodate smart
pigs and the estimated frequency with which operators must install
replacements in lines, RSPA believes the costs to be substantially
less. The economic evaluation prepared for the final rule was based on
available data relating to costs and frequency of replacements made in
gas transmission lines. That evaluation estimated costs at $1.05
million per year. Now under the heading--Requests for Information from
Commenters--this notice requests the operators to provide up-to-date
information on the gas transmission lines that are the subject of this
notice. Thus, gas operators and petitioners will have an opportunity to
provide specific information on the length of affected lines that are
currently unable to accommodate smart pigs (for reasons other than lack
of launchers and receivers) and the extent of replacements made in
recent years for reasons other than to accommodate smart pigs.
Accordingly, RSPA finds that the cost of compliance with the final
rule would not exceed $100 million annually. In addition, the relief
proposed in this notice will further reduce the cost of compliance.
E. Executive Order 12866
AGA argues additionally that RSPA violated Executive Order (E.O.)
12866, titled ``Regulatory Planning and Review,'' since ``the costs of
compliance with this rule could potentially reach over $100 million
annually'' and the Office of Management and Budget (OMB) did not review
the final rule. RSPA disagrees. In the first place, as already noted,
RSPA believes the costs of the final rule to be well below $100 million
annually. Second, E.O. 12866 provides for OMB review of only
``significant regulatory actions'' unless OMB declines to review such a
significant action. The procedure for determining that a regulatory
action is not ``significant'' and for obtaining the concurrence of OMB
with that determination is laid out in Section 6(a)(3)(A) of E.O. 12866
and ``Guidance for Implementing E.O. 12866.'' The latter is a
memorandum from Sally Katzen, Administrator for the Office of
Information and Regulatory Affairs, OMB, to the heads of executive
departments and agencies dated October 12, 1993. RSPA routinely follows
this procedure by submitting lists of planned regulatory actions to OMB
and obtaining its concurrence in designations of ``significant'' and
``nonsignificant.'' OMB concurred in the designation of this final rule
as ``nonsignificant'' on February 23, 1994. Finally, RSPA notes that
E.O. 12866 is an internal management tool of Executive branch of the
Federal Government and does not create any right to OMB review
enforceable by any person against RSPA.
Accordingly, the final rule complies with the requirements of E.O.
12866 and OMB, as explained above.
F. Reasonableness
Petitioners argue that the final rule is unreasonable in requiring
modification of line sections when single components are replaced.
Petitioners assert that such modifications result in minimal benefits
and excessive costs. RSPA believes that significant benefits can accrue
from inspections with smart pigs. Both the Colonial Pipeline Company's
and the Texas Eastern Pipeline Company's experiences with pipeline
failures caused by outside force damage demonstrate the benefits of
internally inspecting pipelines using smart pigs. The Colonial failure
on March 28, 1993 resulted in the release of an estimated 408,000
gallons of petroleum into Sugarland Run Creek, a tributary of the
Potomac River. The Texas Eastern failure occurred on March 23, 1994
when a 36-inch gas transmission line exploded. The resulting fire
leveled 128 condominium units in Edison, New Jersey and caused death,
injury, and substantial property damage.
The failure in each case resulted from mechanical damage to the
pipeline caused by external damage that occurred at an indeterminate
time before the failure. Recent technological developments in smart
pigs allow for internal inspections that identify dents, gouges, and
other anomalies that could lead to failure on buried pipelines. Smart
pig inspections done on each pipeline following these failures have
resulted in the detection and removal of anomalies that could, over
time, have led to additional failures.
In addition, smart pig inspections have long been used by pipeline
operators concerned about corrosion.
In each of these cases, serious pipeline failures occurred in high
density populated areas placing a significant portion of the population
at risk. In each case, the ``piggability'' of the pipelines provided a
more certain means to assure that similar incidents would not recur on
those pipelines. Such ``piggability'' is the goal of the final rule.
Requiring a pipeline operator to make necessary modifications in a line
section whenever a replacement is made is not only reasonable, but also
necessary for safety in high-density populated areas.
Accordingly, RSPA finds no reason to reconsider the final rule as
it applies to replacements in line sections in Class 3 and 4 locations.
With respect to gas transmission pipelines in less populated areas,
AGA argues that a requirement to modify the complete line section to
accommodate smart pigs ``will result in a risk to public safety by
diverting limited funds for capital improvement projects--many of them
safety related--to making pipelines accommodate smart pigs in rural
areas where there would be little, if any, benefit to the public.''
After citing two examples of replacement projects that would have had
large enormous increases under the line section modification
requirement, AGA goes on to state that ``this enormous increase in
costs will result in the final rule having an economic impact of well
over $100 million annually for the industry.'' While RSPA does not
accept these costs as typical for modifying the obstructions to smart
pigs in most line sections, we see the need to reconsider the resulting
benefits in less populated areas.
Accordingly, as discussed below, we are proposing to modify the
final rule as it applies to replacements in Class 1 and 2 locations.
Offshore Pipelines
INGAA requests that RSPA reconsider the final rule and except all
new and replaced offshore transmission lines from compliance. INGAA
argues that requiring offshore transmission lines to accommodate smart
pigs is technically infeasible and impracticable and does not meet the
special statutory criteria for pipeline safety standards. Those
criteria, found in 49 U.S.C. 60102(b), require consideration of
relevant available pipeline safety data, appropriateness of the
standards for the particular type of pipeline transportation or
facility, the reasonableness of the proposed standards, and the extent
to which the standards will contribute to public safety and the
protection of the environment.
To support its position, INGAA states generally that RSPA ignored
technical material presented to show that offshore pipelines cannot be
``smart pigged'', including an assertion that most offshore gas
pipelines are not constructed to accommodate smart pigs. RSPA disagrees
strongly with this argument. The issue is not whether existing offshore
lines can be ``smart pigged'' but whether new offshore transmission
lines can be constructed or existing offshore gas transmission lines
can be modified to accommodate smart pigs. RSPA considered technical
material relating to problems such as tight bends, restrictive subsea
connections, and limited space on platforms in deciding that they can
be. No technical information has been submitted to RSPA that concludes
that offshore gas transmission lines would be incapable of
accommodating smart pigs if they are so designed and constructed. Their
construction is not dissimilar from that of offshore hazardous liquid
pipelines, many of which are already constructed in a manner that would
accommodate smart pigs.
INGAA is incorrect in citing 1992 changes to the statutory
authority as the basis for the final rule. As discussed above, that
statutory change was not used to support the final rule. In addition,
INGAA is incorrect that RSPA ignored recommendations of the TPSSC. As
discussed above, RSPA is not obligated to adopt the recommendations of
the advisory committee, only to consider them. Discussion of RSPA's
consideration of those recommendations is included in the preamble to
the final rule, but is commingled with the discussion of RSPA's
response to commenters to the proposed rule. Furthermore, RSPA's
consideration of the criteria contained in 49 U.S.C. 60102(b), the
technical data, and recommendations of the TPSSC resulted in the
exception provided in the final rule for offshore gas transmission
lines less than 10 inches in nominal diameter that transport gas to
onshore facilities.
INGAA also points to the lack of population around offshore lines
and the periodic cleaning of the gas transmission lines that removes
condensates as justification for exception from the rules for these
pipelines. The rationale is that offshore gas transmission lines do not
pose either serious safety or environmental concerns justifying the
cost of assuring that the lines can accommodate smart pigs. RSPA agrees
that we may not have fully considered these factors in applying the
rules to offshore gas transmission pipelines and accordingly propose a
change to the final rule.
INGAA asserts that most offshore gas pipeline operators use
cleaning pigs to periodically sweep condensate to onshore separation
facilities. This keeps the offshore pipelines free from condensate and
greatly reduces the environmental impact of an offshore leak by
eliminating the risk of a condensate sheen. RSPA agrees that a leak in
an offshore gas transmission line, that is free of significant
accumulations of condensate, poses minimal risk to the natural
environment.
As noted, RSPA agrees that the offshore gas pipelines do not pose
the same safety risk as onshore pipelines. The offshore safety risk is
to workers on platforms and to vessels. The latter risk is extremely
remote absent the possibility of a collision between a vessel and an
underwater pipeline. This possibility has been minimized by the
issuance of Sec. 192.612, which required operators to conduct
underwater inspections in shallow waters in the Gulf of Mexico to
determine whether they pose a risk to navigation and to re-bury those
pipelines. RSPA is working on a proposal addressing the need for
similar periodic underwater inspections.
The accident reports for offshore incidents received by RSPA
indicate that risk to workers on platforms comes from gas leaks in the
risers. The leaks are the result of condensate with corrosive agents
that is likely to collect in the riser's elbows and cause internal
corrosion. Also, external corrosion at the riser's ``splash zone'' is
caused by the degradation of protective coatings from wave action. Both
types of corrosion are detectible by smart pigs. However, as INGAA
points out, modification of riser bends in order to accommodate smart
pigs is costly. RSPA notes that there are alternative techniques of
inspecting these risers for corrosion that are generally more effective
(and less costly) than use of smart pigs that survey the entire
pipeline. These include divers, remotely operated vehicles carrying
ultrasonic thickness devices, or specially equipped tethered smart
pigs.
Furthermore, it is important to note the recommendation contained
in a 1994 study of marine pipeline safety by the National Research
Council of the National Academy of Sciences titled--Improving The
Safety Of Marine Pipelines. The study, co-sponsored by the Minerals
Management Services and RSPA, had input from persons in industry,
academia, and state and federal government who are experts in their
fields and knowledgeable about the marine pipeline environment,
suggested that:
* * * marine pipelines already constructed be exempted from
federal or state requirements for the use of currently available
smart pigs for external or internal corrosion detection. New medium-
to large-diameter pipelines running from platform to platform or
platform to shore should be designed to accommodate smart pigs
whenever reasonably practical.
Accordingly, RSPA denies INGAA's petition to except new offshore
gas transmission lines. However, as discussed below, RSPA has
reconsidered benefits associated with the offshore gas transmission
lines and proposes to modify the requirement under Sec. 192.150(b)(7)
of the final rule with respect to replacements in these lines.
Proposed Rules
First, as discussed above in the section titled ``Stay of
compliance with line section replacement,'' RSPA proposes to extend to
February 1, 1995, the compliance date with respect to replacements in
gas transmission lines.
Second, RSPA proposes to modify Sec. 192.150(b) to add a new
exception for replacements in the line sections of existing gas
transmission lines in Class 1 and 2 locations. This exception would be
limited to those situations in which an operator, who wishes to avail
itself of the exception, can demonstrate that modifying the line
section to accommodate smart pigs is not feasible, and not needed for
future safety.
The safety prong of this test requires consideration of the
operating and maintenance history of the line section. RSPA expects
that the operator will take into account such factors as the reason for
the replacement, corrosion history, leak history, and the risk of
outside force damage. For example, if the replacement that triggers the
application of Sec. 192.150(a) is required because of corrosion and the
line section has a history of corrosion problems, or if external damage
from earth movement is a concern, future safety considerations may
require the line section to accommodate smart pigs.
A decision that modifying a line section is not feasible might be
based on the nature and costs of the modification. For example, if
(other than the replacement) the only modification on the line section
needed to accommodate smart pigs is to replace a reduced port valve,
and that modification will allow internal inspection of the entire line
section, then the operator might reasonably conclude that the
modification is feasible. However, if modification of the line section
would require the acquisition of costly new right-of-way to straighten
bends, the operator might reasonably conclude that modification is not
feasible.
In reconsidering the benefits and costs of modifying line sections
in these less populated areas, we have considered that we expect to
promulgate, in the near future, a final rule in Docket No. PS-101,
Excavation Damage Prevention Programs for Gas and Hazardous Liquid and
Carbon Dioxide Pipelines. The notice for this rulemaking (53 FR 24747;
June 30, 1988) proposed to require gas pipeline operators to expand
their damage prevention programs to cover rural areas. Any such
requirement that is in the resulting final rule would increase the
safety of gas pipelines in Class 1 and 2 locations from failures caused
by dig-ins.
Finally, with respect to existing offshore gas transmission lines,
RSPA proposes to allow operators who (1) use cleaning pigs to remove
condensate in offshore transmission lines and (2) inspect platform
risers for corrosion to avoid modification of the complete line section
when a replacement is made. The regular removal of condensates reduces
the likelihood of internal corrosion and of the negative environmental
impact of a large sheen in the event of a significant leak. The regular
inspection of risers for corrosion by any of the effective methods
available provides the necessary assurance of safety for personnel
working on the platform.
Requests for Information From Commenters
The purpose of the questions posed below is to gather new or
updated information relating to the issues in this rulemaking. Much of
the data which RSPA has available were gathered in order to meet the
requirement for a congressionally-mandated study on the feasibility of
requiring the use of smart pigs. To obtain information for this study,
RSPA solicited information from interested parties through a Federal
Register notice titled ``Instrumented Internal Inspection Devices'' (54
FR 20948; May 15, 1989). The data were summarized in Table 1 of the
study titled ``Instrumented Internal Inspection Devices (A Study
Mandated By P.L. 100-561),'' published November 1992. Table 1 indicated
that 136,359 miles of gas transmission lines and 16,275 miles of
hazardous liquid pipelines would not accommodate instrumented pigs for
reasons not relating to the absence of launchers or receivers. Since
this rulemaking only responds to petitions for reconsideration received
from the two gas pipeline trade associations, updating of the mileage
figures for hazardous liquid and carbon dioxide pipelines is not
relevant.
RSPA invites interested persons to forward comments to the docket
as directed under ADDRESSES) that include up-to-date information on the
following:
(1) What is the mileage, current to December 31, 1993, of the gas
transmission lines that would not accommodate smart pigs for reasons
other than lack of launchers and receivers?
(a) Indicate the mileage of onshore gas transmission lines affected
by the final rule.
(b) Indicate the mileage of offshore gas transmission lines
affected by the final rule.
(2) During the five calendar years, 1989 through 1993, what was the
total length of replacements (actual length of replaced pipe, valves,
fittings, or other line components), installed for reasons other than
to accommodate smart pigs?
(a) Indicate the mileage of such replacements in onshore gas
transmission lines affected by the final rule.
(b) Indicate the mileage of such replacements in offshore gas
transmission lines affected by the final rule.
(3) When replacements are made in a gas transmission line affected
by the final rule, are there alternatives to making the line section
accommodate smart pigs that would ensure the entire transmission line
would accommodate smart pigs in a reasonable number of years?
Commenters are requested to support their alternatives with appropriate
data.
Rulemaking Analyses and Notices
Executive Order 12866 and DOT Regulatory Policies and Procedures
This proposed rule is not considered a significant regulatory
action under 3(f) of Executive Order 12866 and, therefore, is not
subject to review by the Office of Management and Budget. The notice is
not considered significant under the regulatory policies and procedures
of the Department of Transportation (44 FR 11034; February 26, 1979);
because it does not impose additional requirements and has the effect
of extending a compliance date. The original regulatory evaluation of
the final rule has been modified because this proposed rule would
reduce costs and is available for review in the docket for this notice.
Federalism Assessment
This proposed rule will not have substantial direct effects on the
relationship between the Federal Government and the states, or on the
distribution of power and responsibilities among the various levels of
government. Therefore, in accordance with Executive Order 12612 (52 FR
41685; October 30, 1987), RSPA has determined that this notice does not
have sufficient federalism implications to warrant preparation of a
Federalism Assessment.
Regulatory Flexibility Act
There are very few small entities that operate pipelines affected
by this rulemaking. To the extent that any small entity is affected,
the effect is minimal because it does not impose additional
requirements and has the effect of extending a compliance date. Based
on these facts, I certify that under section 605 of the Regulatory
Flexibility Act that this proposed rule does not have a significant
impact on a substantial number of small entities.
List of Subjects in 49 CFR Part 192
Pipeline safety, Reporting and recording requirements. In
consideration of the foregoing, RSPA proposes to amend title 49 of the
Code of Federal Regulations part 192 as follows:
PART 192--[AMENDED]
1. The authority citation for part 192 is revised to read as
follows:
Authority: 49 U.S.C. 5103, 60102, 60104, 60108, 60109, 60110,
60113, 60118; 49 CFR 1.53.
2. In Sec. 192.150, the introductory text of paragraph (b) is
republished without change, paragraph (b)(8) would be redesignated as
paragraph (b)(9) and revised, paragraph (b)(7) would be redesignated as
paragraph (b)(8) and revised, a new paragraphs (b)(7) and (d) would be
added, to read as follows:
Sec. 192.150 Passage of internal inspection devices.
* * * * *
(b) This section does not apply to:
* * * * *
(7) Replacements in transmission lines in Class 1 or 2 locations
(other than replaced line pipe, valve, fitting, or other line
component) if the operator can demonstrate that modifying the line
section to accommodate instrumented internal inspection devices:
(i) is not feasible; and
(ii) is not, based on an assessment of the operating and
maintenance history of the line section, needed for future safety.
(8) Offshore transmission lines, other than new transmission lines
10\3/4\ inches or greater in nominal diameter, if the operator can
demonstrate:
(i) that cleaning pigs are regularly run to sweep condensate from
the lines; and
(ii) that platform risers are regularly inspected for corrosion.
(9) Other piping that, under Sec. 190.9 of this chapter, the
Administrator finds in a particular case would be impracticable to
design and construct to accommodate the passage of instrumented
internal inspection devices.
* * * * *
(d) An operator replacing a line pipe, valve, fitting, or other
line component in a transmission line in a Class 1 or 2 location need
not comply, until February 2, 1995, with the requirement in paragraph
(a) of this section that requires modification of the line section
containing the component.
Issued in Washington, DC on September 23, 1994.
D.K. Sharma,
Administrator, Research and Special Programs Administration.
[FR Doc. 94-24080 Filed 9-29-94; 8:45 am]
BILLING CODE 4910-60-P