97-25800. NorAm Gas Transmission Company; Notice of Request Under Blanket Authorization
[Federal Register Volume 62, Number 189 (Tuesday, September 30, 1997)]
[Notices]
[Pages 51096-51097]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 97-25800]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP97-730-000]
NorAm Gas Transmission Company; Notice of Request Under Blanket
Authorization
September 24, 1997.
Take notice that on September 8, 1997, NorAm Gas Transmission
Company (NGT), 1600 Smith Street, Houston, Texas 77002, filed in Docket
No. CP97-730-000, a request pursuant to Sections 157.205 and 157.211 of
the Commission's Regulations under the Natural Gas Act (18 CFR 157.205
and 157.211) for authorization to construct and operate a tap in Hughes
County, Oklahoma to serve ARKLA, a division of NorAM Energy Corp.
(ARKLA), under its blanket certificate issued in Docket Nos. CP82-384-
000 and CP82-384-001, pursuant to Section 7(c) of the Natural Gas Act,
all as more fully set forth in the request which is on file with the
[[Page 51097]]
Commission and open to public inspection.
Specifically, NGT proposes to construct and operate a 2-inch
delivery tap and first-cut regulator to serve ARKLA. NGT says the tap
will be installed on its Line 2-AD in Section 36, Township 5 North,
Range 9 East, Hughes County, Oklahoma. NGT indicates that ARKLA will
install the domestic meter setting. NGT relates that the estimated
volumes to be delivered to this tap are approximately 160 MMBtu
annually and 1 MMBtu on a peak day. NGT states that the tap and first-
cut regulator are to be constructed at an estimated cost of $2,600.00
and that ARKLA will reimburse NGT the cost of construction.
NGT states that it will transport gas to ARKLA and provide service
under its tariff; that the volumes delivered are within ARKLA's
certificated entitlement; and that NGT's tariff does not prohibit the
addition of new delivery points. NGT says it has sufficient capacity to
accomplish the deliveries without detriment or disadvantage to its
other customers.
Any person or the Commission's staff may, within 45 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to Section 157.205 of
the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to
the request. If no protest is filed within the time allowed therefor,
the proposed activity shall be deemed to be authorized effective the
day after the time allowed for filing a protest. If a protest is filed
and not withdrawn within 30 days after the time allowed for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to Section 7 of the Natural Gas Act.
Lois D. Cashell,
Secretary.
[FR Doc. 97-25800 Filed 9-29-97; 8:45 am]
BILLING CODE 6717-01-M
Document Information
- Published:
- 09/30/1997
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 97-25800
- Pages:
- 51096-51097 (2 pages)
- Docket Numbers:
- Docket No. CP97-730-000
- PDF File:
-
97-25800.pdf